3Clayton County Water Authority
W.J. Hooper, 20mgd
Freeman Road, 10mgd
J.W. Smith, 12mgd
4Conservation Plan
- CCWA has a conservation plan on file with EPD
- System management
- Treatment plant management
- Rate-making policies
- Recycle Reuse
- Public education
5Standard Plumbing Code
- Low-flow fixtures enforced for new development
6Metropolitan North Georgia Water Planning
District
7Demand Projections
- No conservation measures
- With SF toilet retrofit
8Drought Contingency
- Outdoor watering restrictions
- Flushing suspension
- Hydrant maintenance suspension
- Purchase from neighbors
Notice to customers of the Clayton County Water
Authority Non-essential Outdoor Water Use
Definitions The ban on non-essential use is
intended to reduce the demand on water reserves
from lawn watering and car washing.
9Georgia lt10 Wisconsin 25
10Survey of State Agency Water Loss Reporting
Practices
- the Georgia Environmental Protection Division
defines unaccounted-for water as the difference
between the total amount of water pumped into the
water system from the source(s) and the amount of
metered water use by the customers of the water
system expressed as a percentage of the total
water pumped into the system (Rules and
Regulations of the State of Georgia Chapter
391-3-2-.02 Definitions, Amended). - Final report to the American Water Works Assn,
1/02.
11- Production
- Purchased
- (Gallons billed)
- (Leaks Flushing)
- Gallons unaccounted
127.81
10.82
13CCWA Leak Detection Services
14Flow Metrix
- Connect both field sensing units (FSU) to the
water distribution system
- FSUs can be connected to meters, service lines,
fire hydrants and valves
15Flow Metrix
- Once the base and the FSU radios are linked, the
correlation process will begin automatically - The peak that develops in the correlation
function indicates a leak - It usually takes between 1-30 seconds for a peak
to develop
Leak
16Z-Corr Digital Correlating Logger
17Z-Corr Digital Correlating Logger
- Place unit in the field, on valve, meter, etc.
- Retrieve unit
- Download data
- Computer correlates and shows leak location
18Leak Detection Monthly Report
19Meter Testing and Repair
- Meter is stopped
- Work order generated by data processing if meter
readings dont change
20Meter Testing and Repair
- Meter tested up to standard
21- 850 MG/yr 3.5 M/yr
- Jan 99 Aug 00 All 3 and larger meters were
tested - repaired/replaced
22- 69,909 meters 99.25 accuracy
23Hydro-Guard Automatic Flushing Device
24Summary
- CCWA metered our flushing program. Before
installing the Hydro-Guard Automatic Flushing
Device we were flushing 3,384,000 gal/mo,
manually spending at least 15 hrs/wk in personnel
time. - After installing the device, our gallons flushed
dropped to 933,300 gal/mo and 1-1/2 hrs/wk in
personnel time. - Cost savings in flushed water estimated to be
above 4500/mo or 2.5 MG/mo
25Production Plant Programs
26Metered Raw, Finished, Backwash, Process
27(No Transcript)
28(No Transcript)
29(No Transcript)
30Backwash Recycling
31Reclamation Plant Programs
32Reclamation Plant Programs
17,000,000 gal/mo
33CCWA Practices What it Preaches
- Saved 17,000,000 gal/mo at biosolids pelletizing
plant by using reclaimed water for scrubber/dust
removal system and sludge press belt wash.
- Saved 1,200,000 gal/mo at the W.B. Casey Water
Reclamation Facility by converting chlorinators