Open access challenges

1 / 13
About This Presentation
Title:

Open access challenges

Description:

Further, VSL entered into a PPA Tata Power Trading Company Limited for sale of ... and for that Tata Power Trading sought open access which was denied by KPTCL on ... – PowerPoint PPT presentation

Number of Views:153
Avg rating:3.0/5.0
Slides: 14
Provided by: gau120

less

Transcript and Presenter's Notes

Title: Open access challenges


1
Open access challenges way forward
  • S.K. Chatterjee
  • Deputy Chief (RA),CERC
  • 7th August, 2009

2
In this presentation..
  • Open Access Status
  • Challenges in Implementation of Open Access
  • Way Forward

3
Open access Status
4
Short term Inter-State Open Access
5
Status of Open Access at Distribution Level
6
Comparison of cost of power through Intra-State
Open Access and Distribution Utility -
Illustrative Cases for a typical 5MW at 11kv/33kv
consumer
7
Comparison of cost of power through Intra-State
Open Access and Distribution Utility -
Illustrative Cases
Tariff for an embedded consumer of 5MW at 11 KV
(33 KV in some cases). Effective Open Access
Charges for consumer of 5MW at 11 KV (33 KV in
some cases) in addition with a assumption of
power purchase cost of 4 Rs./KwH.
8
OPEN ACCESS CHARGES
  • Transmission Charges
  • Wheeling Charges
  • Imbalance (UI) Charges
  • Reactive Energy Charges
  • Surcharge
  • Interconnection Charges
  • Operating Charges ( SLDC charges)
  • Connectivity Charges..etc.

9
STATUS OF OPEN ACCESS IN DISTRIBUTION(As on
31.06.2009)
  • Total OA Applications received 230
  • OA Capacity Applied for 22905.35 MW
  • Total OA Applications approved 163 (71)
  • OA Capacity Approved 19933.33 MW(87)
  • OA Transaction Implemented 6343.73 MW (28)

10
(No Transcript)
11
OPEN ACCESS Challenges AND way forward
12
CHALLENGES IN OPEN ACCESS
  • Segregation/Unbundling of transmission and
    trading.
  • Independent functioning and capacity building of
    SLDCs.
  • Issues of standby charges.
  • Open Access Charges and Cross Subsidy Surcharge
  • Adequate metering, billing, balancing and
    settlement mechanism
  • Resistance of incumbent licensees / Role of SLDCs
  • State Governments issuing orders under Sec 11

13
WAY FORWARDIN Open Access
14
SEGREGATION OF TRANSMISSION AND TRADING
ASSESSMENT OF PRESENT SITUATION
  • EA 2003 debars transmission companies from
    trading to
  • bring about neutrality in transmission business
    and
  • make discoms responsible for planning and
    procurement of power
  • SEBs have been reorganized in several States but
    not in true spirit
  • TRANSCOs, divested of trading responsibilities
    but another trading arm created to perpetuate
    single buyer model.
  • In many States a holding company continues to
    oversee the subsidiaries created for transmission
    (controlling SLDCs) , distribution, trading etc.
  • The conflict of interest sought to be removed
    through the provision of law continues to haunt
    and frustrate efforts at non discriminatory Open
    Access.
  • Major Role of State Govt. for overcoming these
    constraints

Way Forward.
15
INDEPENDENT FUNCTIONING OF SLDCs (FOR
Recommendations)
  • SLDC not to report to transmission or trading
    licensee.
  • Reporting requirements could be lines of
    reporting pattern for State Electoral Officer
    under Election Commission.
  • Operation of SLDC an appropriate reporting
    system
  • in terms of administrative control and recording
    of confidential remarks
  • with STU - as a subsidiary of transmission
    utility as stop-gap arrangement
  • by a separate entity as soon as possible
  • Urgent need of delegation of financial powers to
    SLDCs . CERC to make regulations for RLDCs to
    ensure recovery of not only operating and capital
    servicing costs but also generation of adequate
    surplus to provide equity for future investments.
    Same to be adopted by SERCs for SLDCs.
  • State Governments be advised to phase out single
    buyer model

Way Forward.
16
CAPACITY BUILDING OF SLDCs (FOR
Recommendations)
  • Requirement of deploying personnel with certain
    pre-defined minimum qualifications and
    certification of competence in Load Despatch
    Centres to be incorporated in the Grid Code
  • A model scheme for technological upgradation of
    SLDCs recommended.
  • Recommendations of the Committee constituted by
    MoP regarding staffing pattern, organisation
    structure and necessary incentives for attracting
    qualified personnel in Load Despatch Centres,
    endorsed.

Way Forward.
17
STANDBY CHARGES (FOR Recommendations)
  • Standby arrangement for open access consumers
  • by levying retail tariff as applicable for
    respective consumer categories only for the
    period during which such standby support is
    requested..
  • No fixed demand charges should be levied on open
    access consumer during the period when no standby
    support is availed
  • The charges for Standby power support should
    comprise only energy charge.
  • The demand charge for six weeks may be uniformly
    spread across the year.
  • Beyond duration of six weeks, the open access
    consumer will have to avail regular supply from
    concerned distribution license

Way Forward.
18
METERING, BILLING, BALANCING AND SETTLEMENT
MECHANISM (FOR Recommendations based on
internal TF report)
  • All open access schedules must be specified in
    MW (not in energy terms).
  • All open access customers should have meters
    which record energy for each 15-minute time
    block.
  • All Special Energy Meters for intra-State
    entities should be installed by the State
    Transmission Utility.
  • Uniform mechanism for settlement on lines of
    inter-state scheme preferable. However, SERCs
    may adopt alternative mechanisms.

Way Forward.
19
CROSS SUBSIDY SURCHARGE (FOR Recommendations)
  • The cross-subsidy surcharge needs to be
    calculated as per the formula given in the Tariff
    Policy unless there are valid reasons for
    deviation.
  • Note Chhattisgarh ERC has adopted average cost
    method by recording reasons as follows
    Agricultural consumers and the BPL consumers in
    the State are highly subsidized as compared to
    the industrial and commercial consumers who are
    cross-subsidizing them. The formula in the Tariff
    Policy thus does not reflect the real position
    and hence has not been adopted by the
    Commission.

Way Forward.
20
CERC Orders on Denial of Open Access
Way Forward.
21
Case I
  • In the matter of non approval of Open Access
    communicated by Southern Regional Load Despatch
    Centre on ground of non- receipt of consent from
    SLDC-OPTCL for transmission of power generated by
    Nava Bharat Ventures Ltd through M/s. Reliance
    Energy Trading Ltd, to the distribution utilities
    in Andhra Pradesh
  • Commissions observations
  • There is no transmission constraint or congestion
    as accepted by Orissa State Load Despatch Centre.
  • The requirements of procuring and erecting PLCC
    and other communication equipment have already
    been complied with by the petitioner.
  • Neither Orissa Grid Code nor the Orissa State
    Electricity Regulatory Commission orders put any
    restriction in granting open access.
  • Commission did not find any justification for
    denial of open access on the ground of lack of
    facilities for real time monitoring.

Ruling
Commission directed that open access shall be
allowed as required by RETL since there are no
transmission constraints and surplus transmission
capacity is available on the intra-State
transmission system
Way Forward.
22
Case II
  • In the matter of petition for direction to RRVPNL
    to pass order on concurrence as per the Central
    Electricity Regulatory Commission (Open Access in
    inter-State Transmission) Regulations, 2008.

Commissions Ruling
The Commission concluded that the objections on
the basis of which open access was denied were
not germane to the issue at hand and held that
action of RRVPNL was unfair and illegal. The
Commission observed that such action appeared to
be an attempt to create a situation whereby GFL
was forced to sell its output within the State,
which was against the intent and content of the
Electricity Act, 2003.
Taking a stern view of denial of open access by
Rajasthan SLDCs, CERC issued show cause notices
to Rajasthan SLDC and Rajasthan Rajya Vidyut
Prasaran Nigam Ltd. (RRVPNL) to explain why
action should not be initiated against them for
violating the CERCs regulations on open access
in inter-State transmission. The complaint was
filed by Gujarat Flurochemicals Ltd. (GFL), a
company that owns wind generation facility in the
Jaisalmer district of Rajasthan.
Way Forward.
23
Case III
  • M/s Viswanath Sugar Ltd. (VSL), M/s Ugar Sugar
    Ltd. and M/s Shree Dhoodhaganga filed petition
    their petitions stating that open access was not
    granted by WRLDC.

VSL had executed a PPA initially with KPTCL to
supply power to HESCOM. As per PPA, in the event
of any payment default by HESCOM for a continuous
period of three months, VSL can sell power to
third parties. HESCOM has defaulted payment for
more than 3 months. Further, VSL entered into a
PPA Tata Power Trading Company Limited for sale
of 7.5 MW of power on round-the-clock basis and
for that Tata Power Trading sought open access
which was denied by KPTCL on ground of its
previous PPA with VSL.
Commissions Ruling
The Commission observed that as an independent
operator and statutory body under the Electricity
Act, 2003, SLDC should consider the applications
for open access in an impartial manner and in
line with provisions of Electricity Act, 2003 and
the open access regulations. Any denial of open
access on considerations other than those
prescribed under the law and taken note of in the
above analysis, will attract the penal provisions
of the Electricity Act, 2003.
Way Forward.
24
State govt. orders under section 11 of EA 2003
Way Forward.
25
Section 11 of Electricity Act
  • 11. Directions to generating companies.-
  • (1) The Appropriate Government may specify that
    a generating company shall, in extraordinary
    circumstances, operate and maintain any
    generating station in accordance with the
    directions of the Government.
  •  
  • Explanation.- For the purpose of this section,
    the expression extraordinary circumstances mean
    circumstances arising out of threat to security
    of State, Public order or natural calamity or
    such other circumstances arising in the public
    order or natural calamity or such other
    circumstances arising in the public interest.
  •  
  • (2) The Appropriate Commission may offset the
    adverse financial impact of the directions
    referred to in sub-section (1) on any generating
    company in such manner as it considers
    appropriate,

Way Forward.
26
Orders under sec 11
  • Karnataka and Tamil Nadu have issued orders under
    Section 11 of the Act
  • requiring generators to sell power only within
    the state at a specified rate and denying open
    access
  • State of Karnataka has, in fact, passed generator
    specific orders in terms of which they have
    specified the price at which generators can sell
    power to distribution utilities
  • The States of Andhra Pradesh, Rajasthan and
    Maharashtra have also imposed restrictions on the
    right to open access

Way Forward.
27
Effects
  • requiring private generators to compulsorily sell
    power to state distribution utilities and not
    other third parties
  • fixing the price at which power can be sold
    through executive diktat
  • imposing restrictions on the right of third party
    sale and
  • denial of open access.

Orders issued under Section 11 are subjudice
Way Forward.
28
THANK you
Write a Comment
User Comments (0)