UK Electronics Status - PowerPoint PPT Presentation

About This Presentation
Title:

UK Electronics Status

Description:

http://www.hep.ph.ic.ac.uk/calice/electronics/electronics.html. Overview of requirements ... Rob Halsall, Adam Baird (RAL), Greg Iles (IC), John Lane (UCL) ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 12
Provided by: paulda6
Category:

less

Transcript and Presenter's Notes

Title: UK Electronics Status


1
UK Electronics Status
  • Paul Dauncey
  • Imperial College London

2
Overview of requirements
  • Back end electronics for ECAL
  • 30 layers, 18?18 pads/layer, total 9720 channels
  • Each channel amplified at front end by VFE chip
  • CR-RC shaper, peaking time 180ns
  • 18 channels/VFE chip, multiplexed analogue output
  • Need to generate sample-and-hold at peak time
  • Need to drive multiplex shift register
  • Need to digitise with 14 bits range, 10 bits
    precision
  • Need to send calibration voltage for pulse
    injection
  • Need to run at 100Hz sustained, 1kHz peak rate
  • Read out all channels every event for pedestal
    and noise studies
  • For more details, see
  • http//www.hep.ph.ic.ac.uk/calice/electronics/el
    ectronics.html

3
Original proposed system
  • Readout board most complex part
  • Each cable handled by slave FPGA
  • Whole board controlled by master FPGA
  • 15 readout boards
  • Each handles digitisation of 2 layers
  • 1 trigger board
  • Holds off further triggers until readout complete
  • 1 test board (not shown)
  • For testing cable connections of readout board

4
Conceptual Design Review, 11 Oct
  • CDR was held on 11 Oct at RAL four external
    reviewers
  • Rob Halsall, Adam Baird (RAL), Greg Iles (IC),
    John Lane (UCL)
  • Technically, design considered good
  • Overall concept thought sound and should be kept
  • Minor issues and suggested improvements (see
    report)
  • Cost estimate reasonable
  • But schedule thought unrealistic
  • Loss of RAL ID effort since July impacted more
    than foreseen so schedule further behind than
    anticipated
  • RAL drawing office for layout heavily booked (by
    LHC!) so unlikely to get effort when required
  • N.B. extra three months to Mar 2004 already
    factored in at CDR

5
How to get back on schedule?
  • Rob Halsall and Adam Baird negotiated 1 month RAL
    ID effort for themselves to work with us up to
    PPRP approval they propose
  • Taking an existing design with similar
    architecture
  • Only rework the parts which have to be different
  • Save layout and engineering effort of rest of
    board
  • They will help us evaluate feasibility and
    resources required
  • Suggest start from CMS Tracker Front End Driver
    (FED)
  • Will be used to read out CMS silicon tracker
  • CMS needs 500 FEDs in final system
  • Already taken 10 man-years of design effort (IC
    and RAL)
  • First full-specification prototypes due in Dec
    2002

6
CMS Tracker FED
5V
3.3V
Run/Halt
Config E2PROM
Id E2 Prom
1.5V
5V
3.3V
1.5V
1
0V
3.3V
Compact Flash
1
Test Connector
1
VME
LEDs
4x Prog Delay
1
Dual ADC
12x Opto Rx
1
Power Good
VME64x Interface FPGA
FPGA
Synch Processing
Boundary Scan
System ACE
Buffer Jumper Matrix
-5V
ASIC
12x trim dac
Vref
VME
FE 1
PD Array
3
6
4x Prog Delay
12V
12
Dual ADC
LEDs
Temp Sense
5V
Front End FPGA
3.3V
FPGA
Temp Sense
Clock Control Data
2.5V
1.5V
2.5V
0V
LEDs
2
1.5V
QDR SSRAM
-5.0V
spare
Over temp
LEDs
TTS
TTCrx
TTC
DAQ
Readout Synch Control
ASIC
FLT
LEDs
EMU
FSYNC
Spare
Process
Back End FPGA
LEDs
Transfer
VME
Temp Sense
43
85
22
Readout
Clock Control Data
4x Prog Delay
3.3V
1.5V
Dual ADC
8
Busy
12x Opto Rx
8
LEDs
error
FPGA
halted
Synch Processing
ASIC
12x trim dac
Vref
FE 8
PD Array
24
4x Prog Delay
48
5.0 V
96
E-Fuse Hot swap DC-DC
3.3 V
Front End FPGA
Dual ADC
FPGA
2.5V
Temp Sense
1.5V
-5.0V
extract
Hot swap cycle
SW
Live extract request
SW
7
FED board compared to readout board
8
FED layout
  • Ideally, keep everything to the right, redo
    everything to the left
  • Restricts readout board to same I/O and
    inter-FPGA paths as FED
  • No show-stopper seen so far

9
Other aspects
  • FED is designed to operate in large system for
    many years
  • High emphasis on reliability and operation
    efficiency
  • Hot swap capability, multiple-level temperature
    cut-outs, etc.
  • Way over-engineered for a beam test
  • May not mount all components to save on cost
  • FED FPGAs need much greater functionality than
    readout board
  • FPGAs are much higher grade (and more expensive)
  • FED VME FPGA can do VME64 doubles VME data rate
  • FED size is 9U not 6U cannot reduce without
    redoing layout
  • 9U board more expensive board cost 3k?6k
  • Bigger, so aim to get more cables per board
    6?16
  • Less boards needed 15?6
  • 9U crate also more expensive 5k?10k
  • Only need one VME crate for whole system

10
Trigger and test boards
  • CMS take data out through non-VME backplane pins
  • Custom data path as VME too slow
  • Unused in readout board implementation
  • Enough bandwidth to route trigger board signals
    into BE FPGA
  • Aim to implement trigger board functions in part
    of BE
  • All readout boards will be identical
  • Select one slot for trigger functions to be
    turned on
  • Saves engineering and layout for second PCB
  • Still need to do firmware
  • Most of FED debugged before used as readout board
  • Testing much less of an issue
  • Sophisticated board (5k plus engineering)
    considered excessive
  • Test board will be much simpler, less functional
    (1k)

11
Cost, effort, schedule
  • Cost needs careful evaluation probably come out
    very close
  • 9U and expensive FPGAs push it up
  • Less boards and crates pull it down
  • Effort needed from RAL estimated to be slightly
    higher
  • Layout effort 3 months, down from 4
  • Engineering effort 15 months total, up from 12
  • Need engineer for duration of project now goes
    to Mar 2004
  • Would be significantly higher without reusing
    FED design
  • Implies underestimate originally, or
    insufficient progress over summer
  • Schedule should fit into later end date of Mar
    2004
  • Delayed first layout until Apr 2003, after LHC
    work
  • Also gives more time for RAL engineer to get up
    to speed
  • Reduced prototype test time from 6 to 5 months
Write a Comment
User Comments (0)
About PowerShow.com