Title: Earned Value Management
 1USING EARNED VALUE MANAGEMENT FOR BETTER CONTRACT 
ADMINISTRATION
November 4, 2004 
 2What is Earned Value Management?
- Its a Management Tool 
 - A snapshot in time. 
 - Compares where the project is now with (1) 
previous work accomplished and (2) where the 
project was planned to be.  - Early warning system to detect deficient or 
endangered progress. 
  3EVMS Is Important to Effective Contract 
Administration
- EVMS gives early warning of potential problems. 
 - As the Contracting Officer (CO), you are a member 
of the Integrated Project Team.  - Its YOUR job, as the CO, to protect the 
Governments rights if performance does not show 
satisfactory progress!  - You must work with the other IPT members and the 
contractor to avoid or mitigate performance 
problems. 
  4Survey says..
- over 800 DoD programs show that ...... 
 - no program has ever improved their performance 
better than the performance at the 15 complete 
point  - which means that performance will only get worse 
despite the assurances of the contractor and 
others!  -  
 
No one pays enough attention in the early stages! 
 5The Earned Value Process
Define the Work
Plan the Work
Work the Plan
Collect Results
Measure Performance
Change Control
Analyze Deviations
TakeCorrective Action
ExternalChanges 
 6Basic Principles of EVM
- Break down the work scope into discrete, 
measurable elements and assign responsibility  - Plan and integrate the scope, schedule and cost 
into a time-phased plan and control changes to 
the plan.  - Objectively assess progress and accomplishments 
 - Use actual costs 
 - Analyze variances from the plan 
 - Use the information to manage
 
  7Why Use Earned Value Management?
- Ensures a clear definition of work prior to 
beginning that work  - Presents a logical plan for accomplishing the 
work  - Provides an objective measure of accomplishments 
 - Early and accurate identification of trends and 
problems  - Accurate picture of contract status 
 - cost, schedule, and technical 
 - Basis for course correction 
 - Supports mutual goals of contractor and customer 
 - bring project in on schedule and cost 
 
  8Earned Value Management measures progress
 Progress  movement towards a goal 
- to measure progress, there must be a standard 
against which the movement may be compared  - EVMS establishes that standard as the 
Performance Measurement Baseline and measures 
progress against that baseline. 
  9Key questions that EVM answers
We analyze past performanceto help us control 
the future
PAST PRESENT 
 FUTURE
Are we on schedule? Are we on cost? What are the 
significant variances? Why do we have 
variances? Who is responsible? What is the trend 
to date? 
 When will we finish? What will it cost 
at the end? How can we control the trend?
The Two Key Questions
1. Did we get what we wanted for what we 
spent? 2. At the end of the project, is it likely 
that the cost will be less than or equal to the 
original estimate? 
 10What do we measure progress against?
- Performance measurement baseline 
 - budget is spread over . . . 
 - time, to accomplish the scope of 
 - work against which progress can be measured 
 - Earned Value is a key concept 
 - how much progress did I make against my original 
plan?  - expressed in dollars or hours
 
  11Ways of Earning Value
- Should be a quantitative and discrete whenever 
possible  - Discrete  tangible end product 
 - e.g. delivery of a specification, vendor parts 
contract awarded, foundation completed  - Should be integrated with with success criteria 
or technical measures  - e.g., successful completion of clean-up, a 
specific test, reliability growth curve 
  12Traditional Management Systems
In these systems, you budget work and then record 
actual expenditures. Example I budget 5 
widgets at 100 hrs per widget. At the end of the 
month 400 hrs had been expended. 
GREAT! I'm 100hrs under budget
But what does this mean? Is this really the true 
status of work? What did I accomplish? 
 13Many management systems measure expenditures not 
work
 Well, Ive spent 400 hrs , Does that mean Ive 
 accomplished 400 hrs of Work? 
- Actual Cost is not an indication of work 
progress, only an indication of hours/money 
spent.  -  
 
  14Management Using Earned Value
Earned Value  is an objective measure of how 
much work has been accomplished.
Example I plan to build 5 widgets this 
month. Each widget should take 100hrs. I will 
measure Earned Value based on  widgets 
completed 
At Month End...
Budget Plan
Earned Value
Actual
500
300
400
(3 Widgets  100 hrs) 
 15Earned Value adds new dimension to traditional 
tracking systems
 Oh boy! I better figure out what
 is going on. I've got 200hrs worth of
 work to catch up on, and I've 
already overspent by 100 hrs. 
 16Using Performance Data for Decision-making
-  Behind Schedule 
 -  - How critical is schedule? 
 -  - Can I afford to work overtime to recover? 
 -  - Can I do tasks concurrently? 
 -  - Are there technical innovations which could 
speed up the process?  -  - Am I gold plating instead of just meeting 
requirements?  -  - Should I do a schedule risk assessment to 
project impact to program?  -  Over Cost 
 -  - Can I reschedule tasks? (Time phasing) 
 -  - Is there a less costly facility I can use? 
 -  - Are there tasks which can be deleted? 
 -  - Should the element be added to my risk 
management profile? 
  17Five Basic Performance Questions Answers 
 18Analysis Techniques
- Sort on significant variances 
 - eliminate almost complete, just starting, etc. 
 - Graph and analyze trends 
 - Look at comparative data 
 - e.g. cumulative performance vs. projected 
performance  - Examine written analysis by contractor 
 - does it answer why? 
 - adequacy of corrective action plans 
 - Analysis of schedule trends, critical path 
 - Analysis of EAC realism
 
what are the drivers? what can we do about them? 
 19Contractors Variance Analysis
- Should address significant variances 
 - Separate discussion of cost and schedule 
variances  - Clear description of reason for variance 
 - Quantity variances (e.g., price vs. usage) 
 - Be specific, not general 
 - Include corrective action 
 - Technical, schedule, and cost impacts 
 - Impact to estimate at completion 
 - Should be written by the individual controlling 
the work! 
 A big hammer for a big variance! 
 20What is a significant variance?
-  variance (e.g., gt10) 
 -  variance (e.g., gt50,000 at the control account 
level)  - critical path element 
 - risk/complexity 
 - impact to other elements 
 - Top 10, Top 20, etc. 
 - contractor defined
 
  21Using Performance Data To Validate Estimates
- New estimates at completion take on more meaning 
when you employ performance information  - To recover from a CPI of .5, the project would 
have to work at an efficiency greater than 1.  - The Estimate At Completion (EAC) can be 
predicted by the performance index  - The overrun will never be less than it is at the 
15 complete point!  
  22Why do we need accurate EACs?
- Variance at Completion vs. Contractor Loss 
 - Positive VAC 
 - EAC lt BAC underrun contractor gain 
 - Negative VAC 
 - EAC gt BAC share area contractor partial loss 
 - EAC gt ceiling overrun contractor loss (100) 
 - Government develops top level EAC for comparison 
 - government should limit progress payments if EAC 
is greater than ceiling  - government needs accurate forecast of fund 
requirements  - May still have time to change the final outcome
 
  23EARNED VALUE PROBLEM INDICATORS
- GOAL To Verify That Effective Variance Analysis 
Processes Are Applied  -  To Identify, Correct, And Report 
Problems  -  POTENTIAL PROBLEM INDICATORS 
 -  Zero variances 
 -  Monthly trends turning negative or downward 
 -  Schedule variances generally indicate cost will 
follow  -  Actuals gt Latest Revised Estimates (LRE) 
 -  BCWP increases with no increase in ACWP 
 -  Negative data elements
 
  24DOE EVM Requirements
- OMB Requirement (A-11) 
 - Use of EVM on acquisitions of capital assets 
 - Report performance annually 
 - Certify contractors system 
 - DOE Requirement (DOE M 413) 
 - Use of EVMS on projects gt20M 
 - Report performance monthly 
 - Certify contractors system
 
  25Applicability of EVM to DOE Contracts
- Program applicability 
 - All programs including NNSA 
 - Contract applicability 
 - Acquisition contracts providing assets and 
capabilities, including  - Prime contracts, subcontracts 
 - Applies to all contract types 
 - Cost plus, fixed price, time and materials 
 - Services contracts providing development  
integration 
  26Pending EVMS FAR Case Requirements
- For Major Acquisitions 
 - EVMS compliant with ANSI/EIA 748 
 - Certified for EVMS compliance 
 - Integrated Baseline Review (IBR) 
 - Manage performance through analysis of EV data 
 - Continued surveillance to ensure continued 
compliance 
  27The First Step - Integrated Baseline Review
- Determines that the Performance Measurement 
Baseline is responsive to the scope of work 
required  - Joint assessment of 
 - Coverage of SOW 
 - Scheduling of work 
 - Resource allocation 
 - Earned Value methodologies 
 - Technical content of PMB 
 - Realism and Risks 
 - Should be done pre-award but no later than 180 
days post-award (FAR Clause may influence 
requirement) 
  28The Contractors EVMS
- Describes system in sufficient detail to 
determine compliance  - Includes prior Certification/Acceptance 
 - If no EVMS in place, Contractor must submit a 
comprehensive plan for compliance  - System description 
 - Necessary modifications 
 - Compliance map 
 - Process descriptions 
 - Recent evaluation or self assessment results 
 - Identify major subcontracts for application of 
criteria  - Verify baseline integrity is maintained 
 - Contains plan and procedures for surveillance and 
self assessment  
  29Contractors Surveillance Plan Contents
- Methods and techniques 
 - Inclusion of new scope 
 - Customer coordination 
 - Schedule 
 - Analysis 
 - Ensure that reliable and timely, cost, schedule 
and technical performance information is generated 
  30What Are My Responsibilities Regarding the EVMS?
- Contracting Officers Preaward Responsibilities 
as a Member of the IPT  - Identify application of Earned Value Management 
System in acquisition plans, solicitations and 
contracts  - Define reporting and electronic submission 
requirements  - Define evaluation criteria for source selections 
 - Factor EVMS into contract management planning 
 
  31What Are My Responsibilities Regarding the 
EVMS?(continued)
- Contracting Officers Post Award Responsibilities 
as a Member of the IPT  - Integrate performance monitoring with EVMS into 
Award/Incentive plans  - Monitor performance with IPT using the EVMS 
 - Act when performance is at risk (communication 
with contractor, show cause and cure notices, 
etc.)  - Evaluate the contractors EVMS implementation 
plan  - Evaluate the contractors EVM systems for 
compliance with the standard  - Conduct Integrated Baseline Reviews to ensure all 
the work scope is included in the baseline 
  32Want to know more?
- DOE Project Management Career Development Program 
has a longer course on EVM  - The Defense Acquisition University has a 
continuous learning module on EVM  - Participate on teams led by DCMA to conduct 
certification reviews of DOE contractors EVMS  - Access the OECM website for tutorials on EVMS 
 - Attend the Integrated Program Management 
Conference (held every Nov in Tysons Corners)