Title: Simulation
1Simulation Prototyping of a Sand-Cast
Component MY4130 Final Project Steve Tarnowski
Anna Keranen Fall Semester, 2004 Michigan
Technological University December 9, 2004
2Table of Contents
- Introduction
- Objectives
- Procedure
- - Casting design
- - Magmasoft simulation
- - Prototype sand casting
- IV. Results
- - Initial gating system
- - Gating system 2 with risers
- - Gating system 3
- V. Conclusions
3Introduction
- Steering arm component (heavy military truck)
- Commercially squeeze-cast
- D357-T6 aluminum
- Machined after heat-treatment
4Project Objectives
- 1.) Prototype the part as an A354 aluminum sand
casting - 2.) Design an appropriate gating and risering
system - 3.) Perform casting simulations with Magmasoft
- 4.) Correlate simulation results with prototype
casting
5Procedure
- 1.) Design an initial gating system
- 2.) Magmasoft simulation of initial gating system
- 3.) Create a sand mold and gravity-cast a
prototype part - 4.) Modify gating system design risers, if
necessary - 5.) Validate risering system with Magmasoft
6Initial gating system
- Horizontal parting line
-
- Sprue
Runners
7Gating 1 filling simulation (1.5 sec)
8Gating 1 filling simulation (3 sec)
9Gating 1 filling simulation (6 sec)
10Gating 1 filling simulation (12 sec)
11Gating 1 solidification (2 min, 56 sec)
12Gating 1 solidification (7 min, 56 sec)
13Gating 1 Simulated Cooling Curve
14Gating 1 Predicted porosity defects
15Gating system 2 Added a riser
Riser was calculated with a modulus (1.1) x
(casting modulus)
16Gating 2 filling simulation (1.5 sec)
17Gating 2 filling simulation (6 sec)
18Gating 2 filling simulation (15 sec)
19Gating 2 solidification (5 minutes)
20Gating 2 solidification (12 minutes)
21Gating 2 Porosity prediction
22Gating system 3
Sprue at part mass center Risers on the ends
23Gating 3 filling simulation (3 sec)
24Gating 3 filling simulation (10.5 sec)
25Gating 3 Solidification (5 min, 41 sec)
26Gating 3 Solidification (12 min, 38 sec)
27Gating 3 Porosity prediction
28Sand mold gravity casting
Gating system 1 was prototyped for correlation
with Magmasoft simulation Oil-bonded sand
Pour temperature of 825 C and pour time of 15
seconds Poured approximately 20 lb of A354
aluminum Existing part was used as the pattern
to create the mold Used a horizontal parting
line
29Sand cast steering arm
lots of flash
external macro shrinkage
Surface porosity is evident, especially at
corners
30Sand cast steering arm
Shrinkage lt 1 on overall dimensions Overall
part quality is good, except for excess flash
31Conclusions
Magmasoft prediction was reliable External
macro shrinkage was accurately predicted Gating
2 and 3 corrected the macro shrinkage Gating
3 further improved the casting quality at the
ends of the part and does not require runners.
Gating 2 casting yield is about 71 Gating 3
casting yield is about 77, thus it is the more
economical option for production
Squeeze-casting is still a better way to produce
this part because of better casting quality,
yield and cycle times.
32Future Development Work
Microstructural porosity analysis Hardness
testing Tensile testing Casting trials of
improved gating systems Ultrasonic or X-ray
inspection