Title: Welcome to Cornerstone Christians Congregation Meeting
1Welcome to Cornerstone Christians Congregation
Meeting
2Agenda
- Review of April 6th Comments
- Recommended Parking
- Recommended Chapel Renovations
- Recommended Schedule
- Upcoming vote
3April 6th Review
- The purpose of the move to Tuckahoe was requested
by several congregational members - Allow us to bring 2 separated congregations
together in order to better provide more
effective ministries internally and to the local
community - Schedule would require fair compromise
- Better Covenant relationship is a part of our
ministry and is not a landlord/tenant business
agreement - Parking would have to be improved
4April 6th Review (continued)
- Tuckahoe merger was a joining of 2 Churches,
there was no promise not to modify the Chapel - History of the Chapel was discussed
- Proposed floor plan was shown and discussed
- Replace Pews with chairs
- Would require removal of Baptismal and removing
the back interior wall - When we build larger worship area we would put
chapel back as it is today - Does everything have to be finished initially?
5(No Transcript)
6(No Transcript)
78 Rows of pews 2 Sections per per Assuming 20
per seat each section will hold 3.5 adults Each
pew will hold 6 adults 8 x 6 x 2 96 6
102 Assume 80 is capacity 82 Adults
comfortably
Existing Design Seats approx. 100
89 rows of chairs (per side) 8 chairs per
row Assuming 21 per seat 9 x 8 x 2 144
Assume 80 is capacity 116 Adults
comfortably Overflow 9 x 9 x2 162
98 rows of chairs (per side) 8 chairs per
row Assuming 20 per seat 8 x 8 x 2 128
Assume 80 is capacity 103 Adults
comfortably Side aisles for access
communion Overflow 8 x 9 x 2 144
10(No Transcript)
11(No Transcript)
12Projected Expenses for Chapel Upgrade
- Sound System 9,000
- Video System 4,000
- Carpet 3,400
- 140 Chairs 5,600
- Carpentry/Paint 1,000
- Misc. 2,000
- Total 25,000
13Approximate Balances
- Current Checking 47,000 (19,000 reserved)
- Building Fund 10,000
- General Fund 64,000
- CD 88,500
- Total 209,500
14- 2008 Budget 208,290
- 2008 Budget Rev.1 190,869
- Jan-April Income 80,041.65
- Projected Income 240,000
- 2008 Capital Expenses Approved 55,950
- HVAC 35,000
- Roof 15,500
- Parking 5,450
15- Projected Savings (assume September start)
- School Rent 6,715
- Projected 2008 Spending
- 190,869 - 6,715 29,000 213,154
- Projected 2008 Income 240,000
- Surplus 26,846
- Honorarium / Memorial for 2008 Chapel Renovation
16Recommended Sunday Schedule
- 800 900 Traditional Worship Service
- 900 930 Combined Fellowship Time
- 930 1030 Sunday School (combined?)
- Lighthouse
- 930 1045 Contemporary Worship Service
- 1100 - 1200 Sunday School (all groups)
- 1130 130 Better Covenant Worship Service
-
17Thank you