PPPs%20and%20Affordability - PowerPoint PPT Presentation

About This Presentation
Title:

PPPs%20and%20Affordability

Description:

Affordability in principle terms. Affordability and VFM are the benchmarks ... In principle terms, a traditionally procured project is ... practical terms ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 25
Provided by: UFS9
Learn more at: https://www.oecd.org
Category:

less

Transcript and Presenter's Notes

Title: PPPs%20and%20Affordability


1
PPPs and Affordability
  • Philippe Burger
  • University of the Free State

2
  • Affordability in principle terms
  • Affordability in practical terms
  • Affordability and VFM
  • Affordability, limited budget allocations and
    legally imposed budgetary limits
  • Conclusion

3
Affordability in principle terms
  • Affordability and VFM are the benchmarks for PPP
    viability.
  • Because of the off-balance sheet nature of PPPs,
    their use has led to some misconceptions
    regarding their impact on the affordability of
    projects.
  • Though PPPs may enable some projects to become
    affordable, this does not stem from their
    off-balance sheet nature.
  • The point is Affordability not only relates to
    PPPs, but to gov expenditure items in general.

4
  • Confusion about affordability created by the
    off-budget nature of PPPs
  • Impression that because government not
    responsible for the acquisition of the asset,
    that PPPs are cheaper than traditional
    procurement this is a fallacy

5
  • In principle affordability is about whether or
    not a project falls within the long-term
    (intertemporal) budget constraint of government.
  • If it does not, then the project is unaffordable.
  • However, because the cash flows and balance sheet
    treatment of PPPs differ significantly from that
    of traditional procurement, some confusion exists
    about the effect of PPPs on affordability.

6
(No Transcript)
7
  • In principle terms, a traditionally procured
    project is affordable if the present value of the
    future revenue stream of government
  • equals or exceeds the sum of expected future
    interest payments and the present value of
    governments expected capital and non-interest
    current expenditure,
  • while a portion of such future expenditure
    streams is allocated to such a traditionally
    procured project.

8
(No Transcript)
9
  • In principle terms, a PPP is affordable if the
    present value of the future revenue stream of
    government
  • equals or exceeds the sum of expected future
    interest payments and the present value of
    governments expected capital and non-interest
    current expenditure,
  • while a portion of such future expenditure
    streams is allocated to such a PPP.

10
  • In both cases the positive net worth of
    government depends on whether or not the present
    value of expected future primary surpluses (i.e.
    surpluses that exclude interest payments) equal
    or exceed the value of existing public debt.
  • The only essential difference between the two
    cases is between the timing of the flows

11
Affordability in practical terms
  • Even though the above is technically correct, it
    has one shortcoming
  • Although PPPs and the PSC used in PPPs involve
    detailed present value calculations over the
    whole life of a PPP contract, governments rarely
    use present value calculations for the rest of
    their activities.
  • Governments also rarely budget for a longer
    horizon than the upcoming year (although some use
    medium term fiscal forecast).
  • This raises the question how should
    affordability of a PPP be assessed within an
    environment where the planning horizon is not
    very long?

12
  • As with other government activities in such an
    environment a PPP project is affordable if
  • the expenditure it implies for government can be
    accommodated within current levels of government
    expenditure and revenue
  • and if it can also be assumed that such levels
    will be and can be sustained into the future.
  • This working definition of affordability allows
    for the use of present value calculations when
    estimating cost of a PPP vs that of traditional
    procurement (using a PSC), but to do so in an
    environment with a short planning horizon.

13
Affordability and VFM
  • Relative affordability affordability of PPP
    compared to that of traditional procurement
  • Interest rate and efficiency differentials main
    determinants (of relative affordability and VFM)
  • Absolute affordability Can the project
    (delivered either trough a PPP or traditional
    procurement) be accommodated within the budget
    without violating the budget constraint

14
  • UK
  • Procuring authorities must complete affordability
    model for any planned PFI (it includes
    sensitivity analysis)
  • The models based on agreed upon departmental
    figures for the years available and cautious
    assumptions about future dept spending envelopes

15
  • Victoria
  • Decision about how a project is funded is
    separate from the decision about how it is to be
    delivered.
  • Potential PPP compete with other capital projects
    for limited budget funding to ensure that they
    fall within what is considered affordable
  • Funding is approved on the preliminary PSC

16
  • Brazil
  • Project studies must include a fiscal analysis
    for the next ten years. In addition, the
    commitment of the federal budget to PPP projects
    is limited by law to 1 of the net current
    revenue of the government.
  • Hungary
  • From 2007 a limit on the amount of expenditure on
    PPPs within the budget, so that each program has
    to fit within this limit.

17
Affordability, limited budget allocations and
legally imposed budgetary limits
  • Distinction between affordability, limited budget
    allocations and legally imposed budgetary limits
  • In many countries there are
  • Limits on second- and third-tier government
    borrowing.
  • Fiscal rules that limit government expenditure,
    deficits or debt.
  • Thus, project might be affordable, but legally
    imposed budgetary limit prohibits borrowing.

18
  • Further example budgetary allocations of
    government departments and authorities that are
    done from a central budget and within which
    expenditure plans must be fitted.
  • Even if a traditionally procured project would
    not violate the long-term budget constraint of
    government, a project may still exceed the future
    expected budgetary allocations of a specific
    government department.

19
  • Danger less of a focus on VFM and create an
    incentive to get project off the books of
    government
  • Three specific cases when there is an incentive
    to get project of the books of government
  • The first case is one where a project cannot be
    delivered through either traditional procurement
    or a PPP within budgetary limits.
  • Has 3 features, but a short-run focus on the 1st
    and a disregard for the 2nd and 3rd by government
    creates the incentive to go the PPP route

20
  1. Should government use traditional procurement,
    the large initial capital outlay will cause a
    government entity to exceed its allocated budget.
  2. Should entity then decide to go the PPP route, it
    may not be able to make future fee payments to
    private partners without exceeding its expected
    future allocated budgets.
  3. In addition, the private partner also cannot
    impose a user charge on the direct consumers of
    the service.

21
  • Second case shares the same features with the
    first with the exception that instead of
    receiving a fee from gov, the priv partner can
    impose a user charge directly on the consumers of
    the service
  • As a result, the project might fit within the
    budget allocation of the government entity.
  • Additional question Is the higher
    tax-plus-user-charge burden of those individuals
    benefiting from the good or services acceptable?

22
  • Third case occurs when gov operates under a
    fiscal rule that sets a limit on the overall
    fiscal balance of government (or a department
    operates under a budget allocation).
  • Traditional procurement Capital outlays may
    contribute to breaking the budgetary limit in the
    year in which government undertakes outlays.
  • PPP Private sector responsible for initial
    capital outlay and government might be able to
    fit future payment of fees to private partner
    into its budget without exceeding the budget
    limit.

23
  • In all three cases the budgetary limit may be
    main reason why government might want to get
    projects of its books.
  • However, main reason should be higher VFM.
  • This is not an argument against budgetary limits
    and rules rather it is an argument in favour of
    emphasising VFM as the main rationale for going
    the PPP route

24
Conclusion
  • Because of the off-balance sheet nature of PPPs,
    there has been some misconceptions regarding
    their impact on the affordability of projects
  • On the whole, these misconceptions may lead to a
    shift of focus away from VFM as the main
    rationale for doing PPPs
  • The analysis, though, indicates that
    affordability has little, if not nothing, to do
    with the set of books on which the project
    appears
Write a Comment
User Comments (0)
About PowerShow.com