Description:

PWM H-bridge motor Drive has gone EOL. End of Life Buy. Review ... HCF/SMH. DADF. Description Continued. Task. Redesign the effect assembles such that they ... – PowerPoint PPT presentation

Number of Views:73
Avg rating:3.0/5.0
Slides: 9
Provided by: davidkar
Category:

less

Transcript and Presenter's Notes

Title: Redesign for Obsolescence


1
Redesign for Obsolescence
  • Xerox University of Rochester
  • Presenter
  • David Karasiewicz

2
Description
  • Problem
  • PWM H-bridge motor Drive has gone EOL
  • End of Life Buy
  • Review possible drop in replacements
  • Redesign the effected assemblies
  • Assembles Effected
  • HCF/SMH
  • DADF

3
Description Continued
  • Task
  • Redesign the effect assembles such that they are
    drop in replacement.
  • Carry the implementation through to end product
    cut-in.
  • Goals
  • Bring forward old design
  • Review all components for potential EOL issues
  • Improve manufacturability

4
Requirements
  • Assembly
  • Form, Fit, and Function of present assemblies.
  • No SW or FW changes
  • Motor Driver requirements
  • 24VDC, Current limited at 2.5A, Bidirectional,
    Dynamic Braking, PWM
  • End Product to meet EMC
  • EN55024 CISPR 22 Class B
  • FCC Part 15 Class B

FOR Details see project proposal
5
Team/Resources
  • Project Eng is David Karasiewicz
  • Equipment
  • Scopes, Power Supplies, Life test fixture
  • Environmental chambers
  • EMC chamber
  • PWB layout by MSL
  • PWBA manufacture is Apsco International

6
Cost Estimates
  • Internal
  • Engineering 65 40 8 20,800
  • Support Organization 8,500
  • Safety and EMC 3,850
  • External
  • Manufacturing
  • ICT test fixture 13,800 3 41,400
  • NRE 1,150 3 3,450
  • Sample Units 385 30 11,550
  • PWB Layout
  • MSL design support 3,200 3 9,600

7
Schedule

Jan 05Product intentparts in house
April 16BA Complete
Oct 01Peer Review
Aug 25Product Cut-in
March 1BA ImpactingPrints Completed Testing
Completed
Oct 31Design completedLayout starts
Aug 15Start Design
8
Current Status
  • First set of production intent parts received
  • Preliminary EMC testing passed
  • No foreseeable delays
  • Issues
  • Key Engineer Resource