Market Readiness Scorecard: Summary Findings PowerPoint PPT Presentation

presentation player overlay
1 / 15
About This Presentation
Transcript and Presenter's Notes

Title: Market Readiness Scorecard: Summary Findings


1
Market Readiness Scorecard Summary Findings
April 30, 2001
2
Readiness Scorecards
  • Readiness Scorecards are issued on a weekly basis
  • Scorecards issued to MP project managers
  • Data Conversion (TDSPs)
  • One TDSP having minor conversion problems
  • TDSP as LSE issues (IOU TDSPs)
  • Private WAN Connection (QSEs and TSPs)...
  • Market Operations Interface, API (QSEs).
  • On Track
  • At Risk
  • Problem

Green
Yellow
Red
3
Readiness Scorecards (contd)
  • Registration and Agreements
  • Generation Asset Data Forms (Resources)
  • ERCOT-Polled Metering Proposals (TDSPs).
  • NOIE meter point Registration (TDSPs)..
  • EDI Testing (CRs and TDSPs).
  • Market Operations Interface, Portal (QSEs).
  • Real Time Communications RTU (QSEs)

4
Registration and Agreements
  • 329 Market Participation Applications Received
  • 37 QSEs (29 expect to be in pilot)
  • 102 LSEs (13 REPs expect to be in pilot)
  • 126 TDSPs
  • 66 Resource entities

5
Registration and Agreements
  • Issues
  • TDSPs 2 Munis and 1 Coop have not registered
  • LSEs 6 of 101 applications pending
    identification of a QSE
  • All CRs participating in pilot have QSEs
    designated
  • Resources 4 of 66 applications pending
    identification of a QSE
  • Action Plan
  • ERCOT PUCT contacting unregistered Munis and
    Coops
  • LSEs and Resources understand the need to
    identify QSE under negotiations

6
Generation Asset Data Forms
497 Units connected to ERCOT Grid
286
Action Items ERCOT contacting Resource
Entities ERCOT validating forms received
7
Metering Design Proposal Status
Network Model EPS Proposals Identify 497 Units
As of 04-30-2001
107
258
70
17
45
Action Items ERCOT contacting TDSPs ERCOT
working with TDSPs to approve pending proposals
8
NOIE Meter Point Registration Status
121 Munis and Coops Identified
As of 04-30-2001
105
16
Action Items ERCOT contacting missing
NOIEs ERCOT validating forms received
9
EDI Testing
  • Issues
  • On 4/23, ERCOT sent transactions to the TDSPs for
    processing. TDSPs identified deviations from
    test scripts in transactions submitted by CRs
  • CRs resubmitted corrected transactions, which
    ERCOT forwarded to TDSPs
  • TDSPs are currently working to return the
    transactions to ERCOT
  • Action Plan
  • Parties have agreed to implement some
    contingencies to make up lost time due to delays
  • ERCOT continues to work with all parties on
    additional contingency measures to enable
    switches by 5/31

10
Market Operations Interface (Portal)
  • Issues
  • Portal functionality improved this week
    qualification testing proceeding
  • 9 QSEs will use portal only during mock market
    and beginning of pilot (none will represent
    generation)
  • Action Plan
  • Functional qualification will be performed in
    parallel with subsequent weeks of mock market
  • ERCOT is working with vendor on system fixes
    identified during the mock market test

11
Real Time Communications (RTU)
  • Issues
  • Completed technical testing of RTU with all 20
    QSEs
  • Resource specific testing proceeding requires
    data submission from all generation units for
    each QSE
  • Data from many generation units in network model
    is missing as QSEs finalize relationships
  • Action Plan
  • ERCOT is working with resource owners to expedite
    submission of data forms

12
Entities Not Registered
  • Muni/Coop
  • City of Sanger Needs Transmission and/or
    Distribution Service Provider Application
  • City of Whitesboro Needs Transmission and/or
    Distribution Service Provider Application
  • Rio Grande Electric Cooperative Needs Load
    Serving Entity Application and Transmission
    and/or Distribution Service Provider Application
  • Non-ERCOT Entities
  • Entergy No Load Serving Entity application
    filed TDSP application filed but not signed
    Standard Agreement
  • Southwestern Public Service No Load Serving
    Entity application filed applied as TDSP and
    signed TDSP Standard Agreement

13
Generation Owners w/Units Not Registered
  • Austin Energy 1 Unit (New Unit)
  • Brownsville Public Utility Board 4 Units
  • Calpine Corporation 7 Units
  • Enterprise Products 1 Unit
  • Exxon Corporation 9 Units
  • Shell 4 Units
  • Oxy Chemical 3 Units
  • Celanese 1 Unit
  • Owner Unknown 3 Units
  • TOTAL 33 Units
  • Note This list is for information only Some of
    these units may intend to only be self-serve.
    However, if ERCOT does not have a signed Resource
    agreement (and there is no QSE designated), there
    is no agreement for payment. If they generate
    and put power on the grid the power will be
    positive UFE and uplifted to the market.

14
EPS Meter Proposals Not Submitted
  • AEP/CPL (Mostly issues with QFs) 14 Units
  • Public Utility Board of Brownsville (very limited
    contact) 4 Units
  • Reliant HLP (actively working on issues) 7
    Units
  • Unknown TDSP 20 Units
  • TOTAL 45 Units
  • Researching TDSP on Unknown category some may be
    self-serve facilities

15
NOIEs Meter Point Registration
No Registration of Wholesale Delivery Points
received
Write a Comment
User Comments (0)
About PowerShow.com