Title: Market Readiness Scorecard: Summary Findings
1Market Readiness Scorecard Summary Findings
April 30, 2001
2Readiness Scorecards
- Readiness Scorecards are issued on a weekly basis
- Scorecards issued to MP project managers
- Data Conversion (TDSPs)
- One TDSP having minor conversion problems
- TDSP as LSE issues (IOU TDSPs)
- Private WAN Connection (QSEs and TSPs)...
- Market Operations Interface, API (QSEs).
- On Track
- At Risk
- Problem
Green
Yellow
Red
3Readiness Scorecards (contd)
- Registration and Agreements
- Generation Asset Data Forms (Resources)
- ERCOT-Polled Metering Proposals (TDSPs).
- NOIE meter point Registration (TDSPs)..
- EDI Testing (CRs and TDSPs).
- Market Operations Interface, Portal (QSEs).
- Real Time Communications RTU (QSEs)
4Registration and Agreements
- 329 Market Participation Applications Received
- 37 QSEs (29 expect to be in pilot)
- 102 LSEs (13 REPs expect to be in pilot)
- 126 TDSPs
- 66 Resource entities
5Registration and Agreements
- Issues
- TDSPs 2 Munis and 1 Coop have not registered
- LSEs 6 of 101 applications pending
identification of a QSE - All CRs participating in pilot have QSEs
designated - Resources 4 of 66 applications pending
identification of a QSE - Action Plan
- ERCOT PUCT contacting unregistered Munis and
Coops - LSEs and Resources understand the need to
identify QSE under negotiations
6Generation Asset Data Forms
497 Units connected to ERCOT Grid
286
Action Items ERCOT contacting Resource
Entities ERCOT validating forms received
7Metering Design Proposal Status
Network Model EPS Proposals Identify 497 Units
As of 04-30-2001
107
258
70
17
45
Action Items ERCOT contacting TDSPs ERCOT
working with TDSPs to approve pending proposals
8NOIE Meter Point Registration Status
121 Munis and Coops Identified
As of 04-30-2001
105
16
Action Items ERCOT contacting missing
NOIEs ERCOT validating forms received
9EDI Testing
- Issues
- On 4/23, ERCOT sent transactions to the TDSPs for
processing. TDSPs identified deviations from
test scripts in transactions submitted by CRs - CRs resubmitted corrected transactions, which
ERCOT forwarded to TDSPs - TDSPs are currently working to return the
transactions to ERCOT - Action Plan
- Parties have agreed to implement some
contingencies to make up lost time due to delays - ERCOT continues to work with all parties on
additional contingency measures to enable
switches by 5/31
10Market Operations Interface (Portal)
- Issues
- Portal functionality improved this week
qualification testing proceeding - 9 QSEs will use portal only during mock market
and beginning of pilot (none will represent
generation) - Action Plan
- Functional qualification will be performed in
parallel with subsequent weeks of mock market - ERCOT is working with vendor on system fixes
identified during the mock market test
11Real Time Communications (RTU)
- Issues
- Completed technical testing of RTU with all 20
QSEs - Resource specific testing proceeding requires
data submission from all generation units for
each QSE - Data from many generation units in network model
is missing as QSEs finalize relationships - Action Plan
- ERCOT is working with resource owners to expedite
submission of data forms
12Entities Not Registered
- Muni/Coop
- City of Sanger Needs Transmission and/or
Distribution Service Provider Application - City of Whitesboro Needs Transmission and/or
Distribution Service Provider Application - Rio Grande Electric Cooperative Needs Load
Serving Entity Application and Transmission
and/or Distribution Service Provider Application - Non-ERCOT Entities
- Entergy No Load Serving Entity application
filed TDSP application filed but not signed
Standard Agreement - Southwestern Public Service No Load Serving
Entity application filed applied as TDSP and
signed TDSP Standard Agreement
13Generation Owners w/Units Not Registered
- Austin Energy 1 Unit (New Unit)
- Brownsville Public Utility Board 4 Units
- Calpine Corporation 7 Units
- Enterprise Products 1 Unit
- Exxon Corporation 9 Units
- Shell 4 Units
- Oxy Chemical 3 Units
- Celanese 1 Unit
- Owner Unknown 3 Units
- TOTAL 33 Units
- Note This list is for information only Some of
these units may intend to only be self-serve.
However, if ERCOT does not have a signed Resource
agreement (and there is no QSE designated), there
is no agreement for payment. If they generate
and put power on the grid the power will be
positive UFE and uplifted to the market.
14EPS Meter Proposals Not Submitted
- AEP/CPL (Mostly issues with QFs) 14 Units
- Public Utility Board of Brownsville (very limited
contact) 4 Units - Reliant HLP (actively working on issues) 7
Units - Unknown TDSP 20 Units
- TOTAL 45 Units
- Researching TDSP on Unknown category some may be
self-serve facilities
15NOIEs Meter Point Registration
No Registration of Wholesale Delivery Points
received