Title: Production Sharing Contracts Key Contractual Issues
1Production Sharing Contracts Key Contractual
Issues
Session IV Key Legal Issues in the EP Sector
by
Jatin Aneja, Senior Associate
amarchand mangaldas suresh a. shroff co.
Amarchand Towers216, Okhla Industrial
EstateNew Delhi-110020 Telephone 91 112 690
2500Facsimile 91 112 692 4900
jatin.aneja_at_amarchand.com
2PSCs Key Contractual Issues Presentation
Overview
- Legal framework
- Contractual framework
- Parties
- Term
- Participating interest and operator
- Carry
- The take
- Cost petroleum
- Production sharing and profit petroleum
- Unitization
- Environment and abandonment
- National economic interest provisions
- Assignment
- Force majeure
- Dispute resolution
3PSCs Key Contractual Issues Legal Framework
- Constitution of India, 1950
- The Oilfields (Regulation and Development) Act,
1948 - The Petroleum and Natural Gas Rules, 1959
- Territorial Waters, Continental Shelf, Exclusive
Economic Zone and other Maritime Zones Act, 1976 - Income Tax Act, 1961
- Customs Act, 1962
- Foreign Exchange Management Act, 1999
- Environment Protection Act, 1986
- Arbitration and Conciliation Act, 1996
4PSCs Key Contractual Issues Contractual
Framework
BIDDER 1
CONSORTIUM / CONTRACTOR
Joint Bidding Agreement
Bid
GOVERNMENT
BIDDER 2
License
BIDDER 3
Production Sharing Contract
- Work program budget approvals
- Exploration Activities
- DISCOVERY
- Notification to Government
- Appraisal and testing
- COMMERICAL
- mining lease
- Development and production
5PSCs Key Contractual Issues Parties
- For offshore areas Grant of license and lease
by the Central Government - For onshore areas Grant of license and lease by
the State Government, with prior approval of the
Central Government - Every license or lease granted to contain
additional terms and conditions as provided for
in an agreement between the Central Government
and the licensee or the lessee (the PSC) - Where license or lease to be granted by a State
Government merely an obligation to consult
the State Government
6PSCs Key Contractual Issues Parties
- NELP V Special emphasis on onshore basins
- Issues and options
- In the case of onshore PSCs
- (1) delays in post contract clearances and
- (2) procurement of mining leases from the
State Government seen as a major bottle neck - Though concurrence already received, States
should be better involved by - (1) Involvement at bidding stage
- (2) Involvement as confirming parties to
contracts
7PSCs Key Contractual Issues Term
- Exploration Phase multiple exploration periods
EXPLORATION PHASE II
EXPLORATION PHASE III
EXPLORATION PHASE I
100 of contract area less discovery areas
25 of contract areanot being discovery areas
50 of contract areanot being discovery areas
100 of contract areanot being discovery areas
100 of contract area less discovery areas
RELINQUISHMENT OF CONTRACT AREA
8PSCs Key Contractual Issues Participating
interests and operator
- Clear definition of the participating interests
(share of rights and obligations) of the parties - Several liability to the extent of participating
interest alone - Operator designated to carry out Petroleum
Operations on behalf of contractors vide Joint
Operating Agreement which will also deal with - (1) establishment of operating committee
- (2) decision making and pass marks etc
- Government control over appointment and change of
Operator
9PSCs Key Contractual Issues Carry
- Where a NOC has paid out past costs for EP
activities - Released from obligation to make payments to
extent of paid out past costs contractors will
pay additional sums, adjusted pro rata to the
extent of shortfall - Once such additional amounts equals paid out past
costs, NOC will start making required payments
under PSC - Necessity to clarify rights and obligations of
parties triggers, past amounts due, rights to
benefits, etc.
10PSCs Key Contractual Issues The take
REVENUE
Royalty
Cost Petroleum
Profit Petroleum
Profit Petroleum
Tax
CONTRACTOR TAKE
GOVERNMENT TAKE
11PSCs Key Contractual Issues Cost petroleum
- Cost petroleum linked to volume of petroleum
produced and saved and contract costs - Control over costs a legitimate state concern
- Issues and options
- Inclusive definition - dispute Eg.- local
community or outside contract area operations
costs allowable? Accounting procedures unclear - Options may be examined. For instance
- (1) Expanded, albeit inclusive definition with
a negative definition of unrecoverable costs - (2) Enunciation of criteria for when costs are
acceptable
12PSCs Key Contractual Issues Production sharing
and profit petroleum
- Profit petroleum total value of product saved
from a particular contract area calculated in
specified manner - Use of investment multiple
- Contractors bid on IM
- Complex proportions are intended to make sharing
of oil more favorable to the Government at higher
production levels
13PSCs Key Contractual Issues Production sharing
and profit petroleum
- Government option to take Petroleum either in
cash or in kind - Government has not really exercised the option
to take in kind - Inability of contractors to finalize long term
contracts with buyers - Justified as being mandatory under Petroleum
Rules and Oilfields Act correct interpretation?
14PSCs Key Contractual Issues Unitization
- Article 12 - Joint Development Plan - where
there is a common reservoir in two contract areas
to safeguard against (1) capture and consequent
competitive drilling along the lease lines and
(2) for securing more effective recovery - Internationally - Unit Operating Agreements to
develop a common reservoir as a single unit - Each party owns all unit property and unitised
petroleum in undivided shares in proportion to
unit equity - On discovery, parties will enter in to ancillary
agreements (1) data exchange (2) joint
studies etc leading to a penultimate pre
unitization agreement
15PSCs Key Contractual Issues Unitization
- On establishment of a commercial discovery,
parties will enter in to the unitization
agreement which supersedes the pre unitization
agreement - Issues and options
- Typically protracted, lengthy negotiations. If
no unitization agreement within time period
Government intervention. To mitigate against
this - (1) Incorporation of principles of pre
unitization agreements in the MPSC - (2) Time limits
- (3) Pre-set criteria
16PSCs Key Contractual Issues Unitization
- Other issues
- Precise definition of unit area
- Tract participation based on initial
determination based on detailed technical
rules - first technical determination and then
fiscal determination - Reevaluation of tract participation based on
principles of re-determination at specified time
intervals for changes above a de-minimis
percentage if below this level, party calling
for re-determination to bear costs - Pass mark for fair and efficient decision
making - Default provisions and ancillary agreements
17PSCs Key Contractual Issues Environment and
abandonment
- Abandonment Plan
- Contingency plans and emergency operations
- All payouts to be cost recoverable what about
penalties, fines and damages? - Site Restoration Scheme involves a sinking fund
and annual contributions based on estimated pay
outs at abandonment - Issues
- Need to examine alternatives such as securing
payment obligations by guarantees, etc. - Protection from absolute liability?
18PSCs Key Contractual Issues National Economic
Interest Provisions
- Local employment
- Local goods, services and resources
- Technical assistance agreements
- Data transfer
- Issues and options
- Contracts in Malaysia and China strong
emphasis on NEIPs - Incentivising compliance with non mandatory
NEIPs cost recoverable vs. non cost
recoverable
19PSCs Key Contractual Issues Assignment
- Generally - with prior approval of Government
- To affiliates with prior approval of Mgmt
Committee - Change in shareholding leading to change in
control with prior approval of Government - Link to shareholding questionable degree of
control - Two tier up change covered?
- Change in control other than through change in
shareholding covered? - Deemed approval
- Minimum participating requirement
20PSCs Key Contractual Issues Assignment
- Facilitating financing
- The broader issues of step in rights vs.
government control - Clarity required
- Direct Agreement?
-
21PSCs Key Contractual Issues Force Majeure
- Standard principles of Force Majeure apply
- Extension of time specific mention of extension
of exploration phase and all dates stand
extended for period of downtime caused by force
majeure - Extended force majeure principles?
- Differential treatment for different phases
- Minimum period of two years
- Political / non political force majeure?
22PSCs Key Contractual Issues Dispute resolution
- Governing law is Indian law
- Best efforts to settle disputes
- Certain matters reserved for determination by
Expert - Issues and options
- Expert is not arbitrator decisions -
enforceable? - Arbitration covers only matters other than
those referred to expert backdoor to civil
court litigation? - Possible options include
- (1) Making decision of expert a binding
agreement - (2) Only recourse to expert decision
arbitration
23PSCs Key Contractual Issues Dispute resolution
- Article 30.6 till NELP III - If circumstances
that would otherwise result in termination are
the subject matter of dispute resolution process
there will no termination during the pendency of
such process - NELP IV onwards deleted
- Unresolved issues. For instance
- termination occurs, arbitration rules it
invalid after a period of time and contractor
has been expelled? - termination occurs, arbitration rules it
invalid and on account of interruption in
operation economic/ physical difficulty
resulting in abandonment no remedy?
24PSCs Key Contractual Issues Dispute resolution
- Similarly, section 1.9.7 (accounting procedures)
- notwithstanding any reference under dispute
resolution provisions, in case any amount is
claimed as due to the Government, the Contractor
shall deposit such claimed amount in a escrow
account - Government agreed to an amendment
- Amendment at its sole discretion Government
may instead of requiring a deposit into an escrow
account, accept bank or corporate guarantee - Unprecedented One sided discretion with
Government - Cost of capital locked interest payments?
25PSCs Key Contractual Issues
Thank you !
Jatin Aneja, Senior Associate
amarchand mangaldas suresh a. shroff co.
Amarchand Towers216, Okhla Industrial
EstateNew Delhi-110020 Telephone 91 112 690
2500Facsimile 91 112 692 4900
jatin.aneja_at_amarchand.com