Title: KKA 3306 PROCESS AND PLANT DESIGN Lecture 7
1KKA 3306 - PROCESS AND PLANT DESIGN Lecture 7
By Robiah yunus Faculty of engineering Universiti
putra malaysia Serdang,43400 selangor.
2EQUIPMENT SIZING
- INTRODUCTION
- economic analysis of a process requires knowledge
of capital and operating costs. - capital costing is based on equipment sizes,
capabilities and associated costs. - In preliminary design, direct and non-iterative
correlations are used in sizing of equipment
units I.e. using Guthries method - simplified sizing and costing are at 25 to 40
level of accuracy
3EQUIPMENT SIZING PROCEDURES
- Vessel Sizing
- flash drums, storage tanks, decanters, selected
reactors - procedures
- calculate vessel volume (V)
- V 2 FL t/rL
- where FL liquid flow rate, t residence
time (5 min) and rL liquid density - length/diameter ratio, L/D 4
- If D gt 1.2 m, use horizontal vessel
- Pactual 1.5 times Pdesign
- Select materials based on max. operating
temperature.
4EQUIPMENT SIZING PROCEDURES
- Heat Exchanger Sizing
- procedures
- calculate area, A
- A Q/UDTlm
- where Q heat duty, U heat transfer
coefficient (Table 4.3) and DTlm is given by
5EQUIPMENT SIZING PROCEDURES
- Heat Exchanger Sizing
- Phase change operation
- if area, A is greater than 10000 ft2, use
multiple heat exchangers.
6EQUIPMENT SIZING PROCEDURES
- Furnaces and Direct Fired Heaters
- For preliminary design, use Guthries method.
- Based on Material and Pressure Factor (MPF) (see
Table 4.6) - basic configurations
- a box or cylindrical construction with carbon
steel tubes at 500 psig design pressure.
7EQUIPMENT SIZING PROCEDURES
- Reactors
- Determine the volume of reactor from
- V Vcat/(1-e) (e 0.5)
- s 1/t m / (r Vcat)
- Depending on reactor conditions, we may cost the
reactor as either pressure vessel, heat
exchangers or furnace based on its MPF.
8EQUIPMENT SIZING PROCEDURES
- Distillation Column
- Column Vessel Design parameters
- Height, diameter and number of trays
- Design of tray stacks - Guthries method
- based on MPF values ( Table 4.7)
- Use Fenske - Underwood-Gilliland methods to
determine Theoretical R and N or - Use Westerberg method
9Distillation Column Sizing
- Westerberg Method
- Determine Tray number and Reflux Ratio
10Distillation Column Sizing
- Empirical Method
- Minimum Number of Stages
- Fenske Equation
- Nm lnzlk/(1-zlk) /(1-zhk)/zhk/lnalk/hk
- ln xlk/xhkdis xhk/xlkbot /
lnalk/hk - Minimum Reflux
- Underwood
- Erbar-Maddox (Gilliland) Correlation
11Distillation Column Sizing
- Westerberg Method
- Calculate Column Diameter
12Distillation Column Sizing
- Westerberg Method
- 3) Determine Total Column Height
- Tray stack height (N - 1) x 0.6 m
- Extra feed space 1.5 m
- Disengagement Space 3.0 m
- Skirt height 1.5 m
- _____________________________________
- Total Height
- Nactual N /0.2
- 4) Calculate Qcond, Qreboiler
13EQUIPMENT SIZING PROCEDURES
- Absorption column
- Column Vessel Design parameters
- Height, diameter and number of trays
- The sizing procedures are similar to distillation
with the exception of - N - from Kremsers
- Nactual N /0.2
- Pumps - for pumping (P ) liquids
- Wth V DP
- Wb m DP/( r hp hm)
0.9
0.5
viscosity
14EQUIPMENT SIZING
- Compressors and Turbines
- Ideal compression work, W
- W m Hv(P2, T2) - Hv(P1, T1)
- For ideal gas,
- W mCP(T2 - T1) m(g/(g-1 )R (T2 - T1)
- but g CP / Cv and g 1.4 (Ideal)
- For an ideal, adiabatic isentropic compression
- T2 T1 (P2/P1) (g--1/g )
- W m(g/(g-1 )R T1(P2/P1) ((g-1)/ g)-1
- Wb W/ hc hm and hc 0.8
- hm 0.9 (electric)
- hm 0.8 (turbine)
- Maximum Wb 7.5 MW (actual)
15EQUIPMENT SIZING
- Staged Compressors.
- 3 types of operations Adiabatic compression,
Staged compression, Isothermal compression. - Staged compression is able to increase a desired
gas pressure with less work by having
inter-cooling after each compression stage
16EQUIPMENT SIZING
- Staged Compressors.
- For fixed number compressors ,N, minimum work
occurs when all compression ratios are equal - P1/P0 P2/P1 P3/P2 P4/P3 PN/PN-1
(PN/P0)1/N - Work required
- W m N (g/(g-1 ))R T0 (PN/P0)(g-1)/g N - 1
- when N 1, the equation reduces to adiabatic
compression - When N --gt?
- W m R T0 ln (PN/P0)
- Trade-off between work (operating cost) and
compressor cost (capital cost), since as N ?, W ?
17EQUIPMENT SIZING
- Reciprocating Compressors.
- Reciprocating compressor perform work and
pressure change through a piston and cylinder
(change in volume) - Best for low capacities and high changes in
pressure. - Work required
- W m (g/(g-1 ))R T0 (PN/P0)(g -1)/g - 1/
- 1 - ( c (PN/P0)1/g - 1
- where c V4/(V2 - V4)
- clearance factor (0.05 to 0.10)
- Compressor selection depends on gas flow rates
and DP (Refer to Ulrich or Perrys handbook)
18EQUIPMENT SIZING
- Refrigeration
- If any process stream is to be below 300K,
refrigeration is required. - Refrigeration cycle and its phase diagram.
- COP Q/W , select COP 1.4
- Qc W Q 5/4 Q
- Some industrial applications require moderately
low temperature which involves large temperature
change. Hence it requires multiple cycles, N
19EQUIPMENT SIZING
- Refrigeration
- Rules in selecting refrigerant and cycle
conditions - Refrigerant , R must always be below its critical
temperatures and pressures - Tcond, max 0.98 TcR
- If cooling water is used as refrigerant, then
- Tcond, max gt TCW DTmin
- In the evaporator
- Tevap gt T boil,R
- Pevap gt 1 atm
- Choose DTmin around 5K for both condenser and
evaporator.
20EQUIPMENT SIZING
- Refrigeration
- Guidelines and Short Cut Model in Analyzing
Multiple Cycles Refrigeration
21EQUIPMENT COSTING
- Biegler, Grossman and Westerberg
- Process Equipment
- BC Co (S/So)a (Table 4.12)
- Cylindrical Pressure Vessel
- BC Co (L/Lo)a (D/Do)b (Table 4.11)
- Updated Bare Module Cost (BMC)
- BMC UF(BC)(MPF MF -1)
- UF Update Factor (CE Plant Index)
- Present Cost Index/Base Cost Index
- MPF From Equipment Sizing
- MF Module factor
- Fixed Capital BMC (10.250.4)
22EQUIPMENT COSTING
- Sinnot (Vol 6)
- Purchased Equipment Cost, PCE
- PCE BC (from graph) x MF x PF
-
- (Graphs 6.3 to 6.6)
- Updated PCE/Plant Cost
- Use Figure 6.1
- Fixed Capital Cost using Langs Factorial Method
- PPC PCE (1 ?1 ?2?3 . . . ?9)
- Fixed Capital (FCC) PPC (1 ?10
?11?12) - Working Capital 10-20 of FCC
- Total Capital Investment FCC WCC
-
23ECONOMIC EVALUATION
- OPERATING/MANUFACTURING COSTS
- Fixed Costs (A)
- Maintenance 5-10 of FCC
- Operating Labor From ME
- Laboratory Costs 20-23 of Item 2
- Supervision 20 of Item 2
- Overheads 50 of Item 2
- Capital Charges 1 5 of FCC
- Local Taxes 2 of FCC
- Insurance 1 of FCC
- Royalties (License Fees) 1 of FCC
- Variable Costs (B)
- Raw Materials From ME
- Utilities From ME
- Other Materials 10
of Item 1 - Shipping and packaging Negligible
- Direct Production Costs A B
- Indirect Production Costs C 0.25(AB)