Title: Schedule
1Schedule
2Introduction
Load Estimation
Terminology
Basic Equipment
Codes and Standards
Power Distribution Final Circuit
Standby Generator and Power Supplies
Protection Cable Wiring
Earthing
Design of Electricity Distribution
3Introduction and Load Assessment
- Date 23 October 2008
- Module Code
Ir. KF Cheung
4Objectives
- To understand the roles and duties of building
services engineers - To enable students to design simple power
distribution systems - To appreciate various power distribution design
5(No Transcript)
6Question
- Power requirements of HVAC system
- By HVAC engineer?
- By Electrical engineer?
7- 1 Definition
- 2 Load Assessment
- 2.1 Code of Practice (CoP)
- 2.2 Practice At Early Stage
- Detailed Design Stage
81. DefinitionA) Active Power (Useful Power) - 1
- Active Power Real Power
- Time average of instantaneous power when the
average is taken over a complete cycle of an A/C
waveform. - Expressed in Watt (W)
91. DefinitionA) Active Power (Useful Power) - 2
- For Single Phase
- P V I cos ø
-
- For Balanced Three-Phase
- P v3 Vph-ph I cos ø
101. DefinitionB) Apparent Power
- For Single Phase
- AP VI
- For Three Phase
- AP v3 V(ph-ph) I
Expressed in Volt-ampere (VA)
111. DefinitionC) Connected Load
- The Sum of all the loads connected to the
electrical system. - This is usually expressed in watts.
121. DefinitionD) Demand Factor
- This is the factor applied to the connected load
of an installation to assess the maximum demand
value. - Demand Factor Maximum demand
- Connected load
131. Definition(E) Load Factor
- Load Factor is the ratio of the average demand to
the maximum demand over a defined interval. - In most commercial building, for example between
the hours of 900 to 1800 the load factor is
usually close to unity.
141. Definition(E) Load Factor
Typical Load Profile for an Office Building
151. Definition(F) Power Factor
- Power Factor is defined as the ratio of the
apparent power in a circuit (V.A) to the useful
power (W) if the voltage and current are
sinusoidal - Power Factor kW/ kV.A
16Example - 1
- Calculate the current demand of a residential
flat (single phase 220V)with - 6 nos. of 100W light bulbs and 4 nos. of 40W
fluorescent lights - 1 no. of 1.5HP and 2 nos. of 1HP Air conditioners
- 1 no. of 3000W Electric Power
- 2 set of 30A Ring Circuits for 13A Socket Outlets
17Example 1Answer
Total Connected Load
182. Load Assessment
- Fundamental to electric design
- Feasibility of a project
- Cost
192. Load Assessment
- How to assess Electrical Load?
- COP for the Electricity (Wiring) Regulation
- Practice
202.1 Load Assessment Current Demand
- The Current rating of a circuit should not be
less than the current demand of the circuit
212.1 Load Assessment Determination of Current
Demand
- General
- The information and value given in this CoP for
determination of current demand are intended for
general guidance only as it impossible to specify
the appropriate allowances for diversity for
every type of electrical installations
222.1 Load Assessment Determination of Current
Demand
- For circuit supplying non- simultaneous or cyclic
loads - For a circuit having non- simultaneous or cyclic
loads such that only one of these loads can be in
use at any one time, the greatest of these loads
should be used in calculating the current demand
of the circuit.
232.1 Load Assessment Determination of Current
Demand
- For final circuit
- According with CoP Code 6, current demand of the
circuit concerned should be the same as the
rating of overcurrent protective device of the
circuit
242.1 Load Assessment Determination of Current
Demand
- For final circuit
- Each socket outlet in a radial final circuit
should be assumed to demand its rated current
rating - Lighting outlets should be assumed to demand the
connected lad with a minimum of 100W per
lampholder - Current using equipment of a rating not greater
than 5VA may be neglected - Discharge lighting should assumed to have a
demand in volt-amperes of the rated lamp wattage
multiplied by not less than 1.8. - All other fixed equipment should be assumed to
demand the rated or normal current
252.1 Load Assessment Determination of Current
Demand
- Allowance for Diversity - 1
- This table is applicable to installation having a
current demand not exceeding 400A in each phase.
262.1 Load Assessment Determination of Current
Demand
- Allowance for Diversity -2
272.1 Load Assessment Determination of Current
Demand
- Allowance for Diversity -3
282.1 Load Assessment Determination of Current
Demand
- Allowance for Diversity - 4
29Example 2Applying Diversity Factor
Total Current Demand
30Example - 3
- Calculate the load demand of the shop (3 phase
380V) with - 40 nos. of 100W Light Bulbs
- 24 nos. of 60W Fluorescent Lights
- 2 set of 12kW 3 phase machines with 0.87 power
factor and 90 efficiency - 3 nos. of 18kW 3 phase electric heaters
- 3 set of 30A ring circuits for 13A socket outlet
31Example 3Answer
Total Current Demand 132.3A
322.2 Load Assessment - Practice At Early Stage
- At Early Stage
- Statistic
- Historical Data/ Experience
- Type of Buildings
332.2 Load Assessment - Practice At Early Stage
- Residential Building
- What are the key parameters?
342.2 Load Assessment - Practice At Early Stage
- Commercial Building
- What are the key parameters?
352.2 Load Assessment - Practice At Early Stage
- Industrial Building
- What are the key parameters?
-
362.2 Load Assessment - Practice At Early Stage
- Purpose Built Plant
- What are the key parameters?
372.2 Load Assessment - Practice At Early Stage
Minimum design load capacities for lighting and
small power equipment for various types of
building
Measured total maximum demand loads for
representative sample of large office buildings
382.2 Load Assessment - Practice At Early Stage -
Example
- Calculate the load of a Residential Tower
- 2-bedroom flats (93 nos.)
- (UFA less than 50m2)
- 3-bedroom flats (51 nos.)
- (UFA less than 50-80m2)
- 3-bedroom flats
- (UFA more than 80m2) (4 nos.)
- Lifts (4 nos.)
- General Lighting Power (1 lot)
- Plumbing Drainage System (1 lot)
392.2 Load Assessment - Practice At Early Stage -
Example
- Calculate the load of a Commercial Tower
- Carpark Lighting Power (13500m2)
- Arcade Lighting (1000m2)
- Escalator (12 nos.)
- Lifts (4 nos.)
- Podium Lighting Power (excluding arcade
lighting) (1 lot) - Plumbing Drainage System (1 lot)
402.3 Load Assessment Practice B) At Detailed
Design Stage
- The electrical load within most commercial
buildings can be arranged into the following
broad categories - Lighting
- Small power and special user equipment
- HVAC equipment
- Lifts and escalators
412.3 Load Assessment - PracticeB) At Detailed
Design Stage
- Lighting
- Lighting Load between 8 and 18 W/m2 for
maintained illuminance levels of 350-500lux - For large office building, lighting load between
12-20 W/m2 is reasonable - In some area of a building special-purpose
lighting is likely to result in higher electrical
loads greater than this.
422.3 Load Assessment Practice B) At Detailed
Design Stage
- What is Special-Purpose Lighting?
432.3 Load Assessment Practice B) At Detailed
Design Stage
- Small Power and Special User Equipment
- Small Power and user equipment generally consists
of items which are plugged into socket outlets or
permanently connected. - Most of this type of equipment is brought into
the building by the occupants and not selected by
the building services designer.
442.3 Load Assessment Practice B) At Detailed
Design Stage
- HVAC
- In modern ventilated and air conditioned building
the load required for HVAC apparatus can
represent 40-50 of the total building load. - Such loads are affected by the nature of the
building fabric, fresh air requirements and
internal heat gains from lighting, people and
equipment.
452.3 Load Assessment Practice B) At Detailed
Design Stage
- Lift
- The evaluation of lift requirements must be
undertaken by a lift specialist who, on the basis
of the building population, should determine - Number of Lift
- Speed of Lift
- Capacity of Lift
- Start Current of Large Lift motor
46Q A
47The End