WBS 6: Magnetic Shielding - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

WBS 6: Magnetic Shielding

Description:

4-layer -metal shielding configuration. Large cylindrical -metal ... confident that we could engineer, fabricate, anneal, and install such a [sized] shield... – PowerPoint PPT presentation

Number of Views:185
Avg rating:3.0/5.0
Slides: 18
Provided by: brad173
Learn more at: https://p25ext.lanl.gov
Category:

less

Transcript and Presenter's Notes

Title: WBS 6: Magnetic Shielding


1
WBS 6Magnetic Shielding
  • B. Filippone and B. Plaster
  • Caltech
  • December 3, 2004

2
Zeroth-Order Concept
4-layer µ-metal shielding configuration
J. Boissevain
J. Boissevain
4K ferromagnetic shield r 40cm l 300cm
superconducting shield r 50cm l
300cm (neither shown here)
Large cylindrical µ-metal shields with
end-caps r 106.7cm, 110.5cm, 114.3cm,
118.1cm l 445.8cm, 453.39cm, 461.0cm, 468.6cm
cos ? coil r 35cm l 300cm
3
Zeroth-Order Concept
4-layer µ-metal shielding configuration
J. Boissevain
J. Boissevain
4K ferromagnetic shield r 60cm l 400cm
superconducting shield r 63cm l
400cm (neither shown here)
Large cylindrical µ-metal shields with
end-caps r 106.7cm, 110.5cm, 114.3cm,
118.1cm l 445.8cm, 453.39cm, 461.0cm, 468.6cm
cos ? coil r 61cm l 393cm
4
Estimated Costs
  • 4K ferromagnetic shield
  • Open cylinder with no end caps
  • 20 mil thickness
  • Cryoperm option
  • Amuneal quote for r 40cm, l 300cm
    30,000
  • Scale up to latest reference design of r 60cm,
    l 400cm 60,000
  • Metglas option
  • Honeywell quote 515/kg
  • 20 mils thick will require 70 kg ? 40,000
  • Al cylinder support frame 8,000
  • VERY LABOR INTENSIVE 5 miles of 2-inch wide
    Metglas strips !!!
  • 300K ferromagnetic shields
  • Cylindrical µ-metal shields with end-caps take
    baseline 62 mils
  • Larry Maltin (President of Technical Products at
    Amuneal)
  • confident that we could engineer, fabricate,
    anneal, and install such a sized shield
  • Cost estimate for largest cylinder with end caps
    60,000 ? 250,000 for 4
  • If want larger spacing between layers 300,000
  • 3 to 6 month lead time (freight truck shipping)
    and will require some on-site assembly
  • 4-layer structure estimated to weigh 2.5 English
    tons

5
Estimated Costs
  • Superconducting shield
  • Not as well thought out at this point
  • Proposed idea is to melt lead and pour into a
    cylindrical Al casting frame
  • Will require design engineering efforts
  • Estimate 100,000
  • 100,000 is estimated cost in pre-proposal
  • No experience yet crude guess is 50,000
  • In-house vs. out-sourcing
  • Room-sized box-type µ-metal shield or large
    tri-axial square Helmholtz bucking coils
  • Estimate for thin (14 mil) box-type (or large
    cylindrical) shield 75,000

6
Estimated Costs
  • AC demagnetization circuit for the ferromagnetic
    shields
  • Demagnetizing prototype Cryoperm and µ-metal
    shields has proven to be difficult (later talk)
  • High-power, variable-frequency, programmable AC
    power supply 25,000
  • Demagnetization circuit supplies 5,000
  • Technical/Engineering/Machining work at Caltech
  • Support for design engineer and machinist for
    assistance with integration of shielding with
    experiment
  • Estimated labor costs 30,000
  • Note We did not include expenses related to
    materials/construction of support structures for
    the shielding (only for design engineering)

7
Costs Roll Up
WBS 6 Magnetic Shielding WBS 6 Magnetic Shielding WBS 6 Magnetic Shielding
6.1 5-Layer Ferromagnetic Shield 360,000 2
6.1a 0.3K Ferromagnetic Shield 60,000 2
6.1b 300K 4-Layer Ferromagnetic Shield 300,000 2
6.2 Superconducting Shield 50,000 3
6.3 Other Shielding (e.g., room-sized) 75,000 2
6.4 AC Demagnetization Circuit 30,000 1
6.5 Technical/Engineering/Machining Support 30,000 2
6 TOTAL 545,000
Risk Level
1 lowest 3 highest
Pre-Proposal 415,000
8
Proposed Schedule
  • Personnel during construction phase (1.0 FTE) 1
    faculty 1 post-doc 1 design engineer 1
    machinist undergraduate student(s) and/or
    1 graduate student
  • Rough Timeline (assuming funding available
    FY2007)

2007
2008
2009
2010
.....
Finalize shield design/geometry Finalize/integrate
support structure Procure ferromagnetic
shields Construct/test superconducting
shield Procure AC demagnetization
equipment Install all magnetic shielding Install/t
est AC demagnetization circuit
.....
potential hold-ups
9
300K Four-Layer Shield
r 106.7cm, 110.5cm, 114.3cm, 118.1cm (nominal
design) r 106.7cm, 115.0cm, 125.0cm, 135.0cm
r 106.7cm, 120.0cm, 135.0cm, 150.0cm
10
WBS 7Magnets
  • B. Filippone and B. Plaster
  • Caltech
  • December 3, 2004

11
Overview of Magnets
  • Magnets to be constructed
  • cos ? coil for static field
  • 1-10 mGauss DC field 0.1 spatial uniformity
    10-6 temporal stability
  • Solenoid as p/2 r.f. 3He and neutron spin-flip
    coil
  • 0.1 mGauss AC field 3.165 Hz 1.58 second
    duration
  • Spin-dressing cos ? coils
  • Field parameters to be defined
  • Accompanying instrumentation needs
  • Highly-stable AC and DC power supplies
  • Mapping hardware and probes for field monitoring
  • Labor costs (design engineering and
    machining/construction) and raw materials will
    comprise the core costs for WBS 7
  • As opposed to mostly procurement costs for WBS 6

12
Zeroth-Order Concept
static cos ? coil
p/2 r.f. solenoid
y
x
superconducting shield
?
spin-dressing cos ? coils 180 phase difference
4K ferromagnetic shield
13
Estimated Costs
  • Design and construction of static cos ? coil
    130,000
  • ¼-scale prototype already constructed at Caltech
    ? have acquired experience with design and
    machining efforts (later talk)
  • Design engineering/integration labor costs
    20,000
  • Materials and supplies 30,000
  • Machining/production labor costs 80,000
  • Assuming out-sourcing in-house could lead to
    reduction
  • Design and construction of p/2 r.f. solenoid
    20,000
  • Solenoid ? design and construction should be
    simpler (in principle)
  • Design engineering/integration labor costs
    5,000
  • Materials and supplies 10,000
  • Machining/production labor costs 5,000

14
Estimated Costs
  • Construction/integration of spin-dressing coils
    150,000
  • Prototype AC cos ? coils to be built as part of
    the 2005-2006 RD efforts at Caltech
  • Design engineering/integration labor costs
    20,000
  • Materials and supplies 50,000
  • Machining/production labor costs 80,000
  • Assuming out-sourcing in-house could lead to
    reduction
  • AC and DC power supplies 60,000
  • Require highly-stable power supplies and
    stabilization circuits
  • DC power supply with accompanying stabilization
    circuit for the static cos ? coil 30,000
  • Low-frequency AC power supply for p/2 r.f.
    spin-flip solenoid 10,000
  • High-frequency AC power supply for spin-dressing
    coils 10,000
  • Computer-controlled interface for all power
    supplies 10,000
  • Possibly coupled to AC demagnetization circuit in
    WBS 6

15
Estimated Costs
  • Mapping hardware and probes for (possible)
    in-situ real-time field monitoring 80,000
  • DC field profile independent of 3He
    co-magnetometry
  • Appropriate tuning of AC fields
  • Computer-controlled positioning/stepping hardware
    and readout (difficulties due to the cryogenic
    environment) 50,000
  • Engineering for integration 10,000
  • Cryogenic 3-axis fluxgate magnetometers and
    probes 20,000

16
Costs Roll Up
WBS 7 Magnets WBS 7 Magnets WBS 7 Magnets
7.1 Static Field cos ? Coil 130,000 2
7.2 r.f. Spin-Flip Coil 20,000 2
7.3 Spin Dressing Coils 150,000 2
7.4 AC and DC Power Supplies 60,000 1
7.5 Field Monitors 80,000 1 and 3
7 TOTAL 440,000
Risk Level
1 lowest 3 highest
Pre-Proposal 270,000
17
Proposed Schedule
  • Personnel during construction phase (2.0 FTE) 1
    faculty 1 post-doc 1 professional staff
    member 1 design engineer 1 machinist
    1 graduate student (?) undergraduate
    student(s)
  • Rough Timeline (assuming funding available
    FY2007)

2007
2008
2009
2010
.....
Finalize magnet parameters/geometry Construct/test
static cos ? coil Construct/test p/2 r.f.
spin-flip coil Construct/test spin-dressing
coils Procure/test AC and DC power
supplies Design/construct field monitors Procure
magnetometer/probes Install all components
potential hold-ups
Write a Comment
User Comments (0)
About PowerShow.com