Title: WBS 6: Magnetic Shielding
1WBS 6Magnetic Shielding
- B. Filippone and B. Plaster
- Caltech
- December 3, 2004
2Zeroth-Order Concept
4-layer µ-metal shielding configuration
J. Boissevain
J. Boissevain
4K ferromagnetic shield r 40cm l 300cm
superconducting shield r 50cm l
300cm (neither shown here)
Large cylindrical µ-metal shields with
end-caps r 106.7cm, 110.5cm, 114.3cm,
118.1cm l 445.8cm, 453.39cm, 461.0cm, 468.6cm
cos ? coil r 35cm l 300cm
3Zeroth-Order Concept
4-layer µ-metal shielding configuration
J. Boissevain
J. Boissevain
4K ferromagnetic shield r 60cm l 400cm
superconducting shield r 63cm l
400cm (neither shown here)
Large cylindrical µ-metal shields with
end-caps r 106.7cm, 110.5cm, 114.3cm,
118.1cm l 445.8cm, 453.39cm, 461.0cm, 468.6cm
cos ? coil r 61cm l 393cm
4Estimated Costs
- 4K ferromagnetic shield
- Open cylinder with no end caps
- 20 mil thickness
- Cryoperm option
- Amuneal quote for r 40cm, l 300cm
30,000 - Scale up to latest reference design of r 60cm,
l 400cm 60,000 - Metglas option
- Honeywell quote 515/kg
- 20 mils thick will require 70 kg ? 40,000
- Al cylinder support frame 8,000
- VERY LABOR INTENSIVE 5 miles of 2-inch wide
Metglas strips !!!
- 300K ferromagnetic shields
- Cylindrical µ-metal shields with end-caps take
baseline 62 mils - Larry Maltin (President of Technical Products at
Amuneal) - confident that we could engineer, fabricate,
anneal, and install such a sized shield - Cost estimate for largest cylinder with end caps
60,000 ? 250,000 for 4 - If want larger spacing between layers 300,000
- 3 to 6 month lead time (freight truck shipping)
and will require some on-site assembly - 4-layer structure estimated to weigh 2.5 English
tons
5Estimated Costs
- Superconducting shield
- Not as well thought out at this point
- Proposed idea is to melt lead and pour into a
cylindrical Al casting frame - Will require design engineering efforts
- Estimate 100,000
- 100,000 is estimated cost in pre-proposal
- No experience yet crude guess is 50,000
- In-house vs. out-sourcing
- Room-sized box-type µ-metal shield or large
tri-axial square Helmholtz bucking coils - Estimate for thin (14 mil) box-type (or large
cylindrical) shield 75,000
6Estimated Costs
- AC demagnetization circuit for the ferromagnetic
shields - Demagnetizing prototype Cryoperm and µ-metal
shields has proven to be difficult (later talk) - High-power, variable-frequency, programmable AC
power supply 25,000 - Demagnetization circuit supplies 5,000
- Technical/Engineering/Machining work at Caltech
- Support for design engineer and machinist for
assistance with integration of shielding with
experiment - Estimated labor costs 30,000
- Note We did not include expenses related to
materials/construction of support structures for
the shielding (only for design engineering)
7Costs Roll Up
WBS 6 Magnetic Shielding WBS 6 Magnetic Shielding WBS 6 Magnetic Shielding
6.1 5-Layer Ferromagnetic Shield 360,000 2
6.1a 0.3K Ferromagnetic Shield 60,000 2
6.1b 300K 4-Layer Ferromagnetic Shield 300,000 2
6.2 Superconducting Shield 50,000 3
6.3 Other Shielding (e.g., room-sized) 75,000 2
6.4 AC Demagnetization Circuit 30,000 1
6.5 Technical/Engineering/Machining Support 30,000 2
6 TOTAL 545,000
Risk Level
1 lowest 3 highest
Pre-Proposal 415,000
8Proposed Schedule
- Personnel during construction phase (1.0 FTE) 1
faculty 1 post-doc 1 design engineer 1
machinist undergraduate student(s) and/or
1 graduate student - Rough Timeline (assuming funding available
FY2007)
2007
2008
2009
2010
.....
Finalize shield design/geometry Finalize/integrate
support structure Procure ferromagnetic
shields Construct/test superconducting
shield Procure AC demagnetization
equipment Install all magnetic shielding Install/t
est AC demagnetization circuit
.....
potential hold-ups
9300K Four-Layer Shield
r 106.7cm, 110.5cm, 114.3cm, 118.1cm (nominal
design) r 106.7cm, 115.0cm, 125.0cm, 135.0cm
r 106.7cm, 120.0cm, 135.0cm, 150.0cm
10WBS 7Magnets
- B. Filippone and B. Plaster
- Caltech
- December 3, 2004
11Overview of Magnets
- Magnets to be constructed
- cos ? coil for static field
- 1-10 mGauss DC field 0.1 spatial uniformity
10-6 temporal stability - Solenoid as p/2 r.f. 3He and neutron spin-flip
coil - 0.1 mGauss AC field 3.165 Hz 1.58 second
duration - Spin-dressing cos ? coils
- Field parameters to be defined
- Accompanying instrumentation needs
- Highly-stable AC and DC power supplies
- Mapping hardware and probes for field monitoring
- Labor costs (design engineering and
machining/construction) and raw materials will
comprise the core costs for WBS 7 - As opposed to mostly procurement costs for WBS 6
12Zeroth-Order Concept
static cos ? coil
p/2 r.f. solenoid
y
x
superconducting shield
?
spin-dressing cos ? coils 180 phase difference
4K ferromagnetic shield
13Estimated Costs
- Design and construction of static cos ? coil
130,000 - ¼-scale prototype already constructed at Caltech
? have acquired experience with design and
machining efforts (later talk) - Design engineering/integration labor costs
20,000 - Materials and supplies 30,000
- Machining/production labor costs 80,000
- Assuming out-sourcing in-house could lead to
reduction - Design and construction of p/2 r.f. solenoid
20,000 - Solenoid ? design and construction should be
simpler (in principle) - Design engineering/integration labor costs
5,000 - Materials and supplies 10,000
- Machining/production labor costs 5,000
14Estimated Costs
- Construction/integration of spin-dressing coils
150,000 - Prototype AC cos ? coils to be built as part of
the 2005-2006 RD efforts at Caltech - Design engineering/integration labor costs
20,000 - Materials and supplies 50,000
- Machining/production labor costs 80,000
- Assuming out-sourcing in-house could lead to
reduction - AC and DC power supplies 60,000
- Require highly-stable power supplies and
stabilization circuits - DC power supply with accompanying stabilization
circuit for the static cos ? coil 30,000 - Low-frequency AC power supply for p/2 r.f.
spin-flip solenoid 10,000 - High-frequency AC power supply for spin-dressing
coils 10,000 - Computer-controlled interface for all power
supplies 10,000 - Possibly coupled to AC demagnetization circuit in
WBS 6
15Estimated Costs
- Mapping hardware and probes for (possible)
in-situ real-time field monitoring 80,000 - DC field profile independent of 3He
co-magnetometry - Appropriate tuning of AC fields
- Computer-controlled positioning/stepping hardware
and readout (difficulties due to the cryogenic
environment) 50,000 - Engineering for integration 10,000
- Cryogenic 3-axis fluxgate magnetometers and
probes 20,000
16Costs Roll Up
WBS 7 Magnets WBS 7 Magnets WBS 7 Magnets
7.1 Static Field cos ? Coil 130,000 2
7.2 r.f. Spin-Flip Coil 20,000 2
7.3 Spin Dressing Coils 150,000 2
7.4 AC and DC Power Supplies 60,000 1
7.5 Field Monitors 80,000 1 and 3
7 TOTAL 440,000
Risk Level
1 lowest 3 highest
Pre-Proposal 270,000
17Proposed Schedule
- Personnel during construction phase (2.0 FTE) 1
faculty 1 post-doc 1 professional staff
member 1 design engineer 1 machinist
1 graduate student (?) undergraduate
student(s) - Rough Timeline (assuming funding available
FY2007)
2007
2008
2009
2010
.....
Finalize magnet parameters/geometry Construct/test
static cos ? coil Construct/test p/2 r.f.
spin-flip coil Construct/test spin-dressing
coils Procure/test AC and DC power
supplies Design/construct field monitors Procure
magnetometer/probes Install all components
potential hold-ups