Title: EXECUTIVE SUMMARY PRESENTATION
1EXECUTIVE SUMMARY PRESENTATION
- WASTE TO ENERGY PROJECT
- SAN JOSE COSTA RICA
- GASIFICATION TO ENERGY
- Reasonable, Responsible Recycling
2 3Waste to Energy
4Project Essentials
- Adequate tipping fees for all work
- Definitions of work to be performed
- Processing versus End Point.
- Regulatory approvals
- Import Tax Waivers or Tip Fee offset
- Permitting guarranteed
- Location guarranteed
- Offtake contract for power P.P.A.
5 Project Delivery Risk
Vendor Design Bid Build
DBFO - P3
DBO Contract P3
Concession or BOOT
Private Ownership
General Contractor DB
Courtesy Epcor
6Biosphere Gasifier Rendering
Ecology Wet Cell
7Front End Recycling
- We tend to prefer projects which remove
recyclable materials, and non recyclable
materials. - We cant gasify stone and glass, and we should
recycle aluminum cans, etc.
8Front End Recycling,Single Stream.
9Waste Transfer can be clean
- Transfer to Waste Processing can be direct or by
trans shipment. - Baling systems can produce wrapped waste with NO
odor and NO negative image.
10Fully enclosed waste transfer
11Visually neutral.
- Bales weigh approximately 3,500 pounds each.
- Compressed approximately 141 ratio.
- Can be stacked deeply, and held in high
temperatures without problems
12Refuse Derived Fuel
- Municipal solid waste (MSW) is processed into
Refuse Derived Fuel (RDF) in a MRF i.e., in a
Material Recycling Facility - The RDF can be gasified in an Biosphere Gasifier
- The RDF can also be mixed with 82 moisture
content belt pressed Municipal sewage sludge
and gasified in an Biosphere Gasifier
13(No Transcript)
14Prototype 15 Million Btu/h Unit
15Direct-fired lumber kilns
16Indirectly fired dryer in Pulp mill
17Firing lime kiln
18Proven Commercial Performance
- Two units (45,000,000 Btu x 2) have been running
continuously for 27 years. - The machine has lasted longer than most of the
ten forestry product companies who installed
units. - Reliable, robust, solid and proven fluidized bed
updraft gasification that can project finance.
19Miscellaneous Wastes
- Municipal Solid Waste
- Refuse derived fuel
- Bio Solids or Sludge from waste water
- Used Railway Ties Telephone Poles
- Construction and Demolition Debris
- Land Clearing Debris
- Poultry litter
- Cow Manure
- Pig Manure
- Mixtures of the above
20Diagram of 3 - 90 Million Btu/h Biosphere
Gasifiers Externally Co-firing an existing
boiler
21 22 23 24(No Transcript)
25Firing of Steam Turbine
- Biomass is gasified in separate units built
alongside of steam turbine. - Gasifiers 2,000oF 200oF products of combustion
are ducted to Heat Exchangers which drive steam
into the Turbine. - Products of combustion from Heat Exchanger goes
into our special bag houses. - Biomass moisture content up to 65 is OK for
our gasifiers.
26Significant Features, 1
- Four air sources
- Underfire air gasifies biomass in the 1st stage
- Overfire air preheats 1st stage producer gas
to ensure ignition in the 2nd stage - Primary combustion air ignites the preheated
producer gas at the bottom of the 2nd stage - Secondary combustion air completes combustion of
producer gas in the 2nd stage
27Significant Features, 2
- Very large 1st stage grate area
- Hence grate temperature 1,200oF
- Hence essentially zero slag
- Ash can be reclaimed as valuable products
- Very low underfire air flow
- (only need sufficient air to gasify biomass)
- Hence very low particulate elutriation off pile
28Significant Features, 3
- The Biosphere Gasifier can burn biomass with
moisture contents up to 65 (wet basis) and ash
contents up to 35 - 51 turndown ratio is standard 91 is not
uncommon - 15 second response time to step change in Btu
Demand signal - Abort valve permits rapid dumping of products of
combustion in an emergency
29Refuse Derived Fuel
- Municipal solid waste (MSW) is processed into
Refuse Derived Fuel (RDF) in a MRF i.e., in a
Material Recycling Facility - The RDF can be gasified in an Biosphere Gasifier
- The RDF can also be mixed with 82 moisture
content belt pressed Municipal sewage sludge
and gasified in an Biosphere Gasifier - WILL OR WONT, VERSUS, CANT!
30Physical Plant Construction
31(No Transcript)
32CONSTRUCTION
- Estimated direct workforce will be 35 to 40 men
for approximately fourteen months. - Additional jobs will likely be in transportation
and supply.
33Construction Major Trades
- Heavy Equipment operators
- Electrical, Major and sub-systems
- Machinists, Welders and fitters
- Power Equipment, Cranes, Concrete
- Refractory
34Environmental Compliance
35KYOTO PROTOCOL TO THE UNITED NATIONS FRAMEWORK
CONVENTION CLIMATE CHANGE
- Reducing the greenhouse gas effects of the
combustion of fossil fuels is exactly the value
produced by a biomass and refuse derived fuel
based power plant. - ZERO new CO2 production cycle.
36Biosphere Gasifier
- 1st Stage gentle updraft gasification on very
large grate - 2nd Stage vigorous, double vortex, cyclonic
combustion - Emissions (untreated) CO lt 1 ppm, NOxlt 15 ppm,
particulate lt 100 mg/Nm3
(lt 0.125 lb/106 Btu lt 0.04 gr/dscf) - Emissions listed are prior to treatment, Bag
House _at_ PM2.5 and Wet Tubular Electrostatic
Precipitators are planned for projects. - Units in continuous operation for 25 years
37Significant Features, 4
- Staged combustion permits operating with excess
air levels as low as 15 - The lime kiln test unit burned 55 moisture
content hog fuel and supplied 2,200oF flue gas to
the kiln _at_ ? 15 - Staged combustion and low temperatures (due to
wet fuels) combine to produce virtually zero
thermal NOx
38Significant Features, 5
- Dioxins and Furans Destroyed, viz.,
- Chlorine can react with cellulose to form dioxins
and furans in the 1st stage - However, these gases are destroyed in the 2nd
stage with its 1,800oF plus brick walls - No black waterwalls are present to chill - and
lock in - dioxins or furans in the 2nd stage
39Dioxins Furans M.A.C.T.
- M.A.C.T. is maximum available control technology.
(Also sometimes known as B.A.C.T. or Best
Available Control Technology). - While we should not have any issue with this on
our gasification, we include special bag houses
that would automatically catch any dioxins or
furans at 40 below the current A7 Ontario
Standards. Very, very clean.
40Natural Exposure is Forest Fire
41SWEDISH EXPERIENCE
- 29 Waste to Energy plants operating at this time.
- GUESS What is their total output of dioxins, all
29 plants, annually?
42Catalytic Filter System
43Metals, Sulphur etc.
44Metals removed (not supposed to be there)
Maximum liquid and direct burn Maximum
sludge burn Maximum bulk solids burn
45(No Transcript)
46(No Transcript)
47(No Transcript)
48NOx M.A.C.T.
- The Idaho National Laboratory has come up with a
way to insert a re-burn chamber for NOx on the
exit ducting of our gasification unit. - Given the low proteins in municipal waste product
and very low thermal NOx this would be a very
conservative move that we would do more for PR
than any need but this is a test we are
interested in and will pursue.
49Agricultural Wastes
- With a grate temperature of 1,200oF, potassium
(potash) and sodium (soda) in agricultural and
animal waste do not vaporize to form alkali
deposits on boiler tubes - Potassium vaporizes at 1,400oF and sodium
vaporizes at 1,616oF - The potash and soda remain in the 1st stage, from
which they are removed by the built-in ash
removal system and sold to farmers depending on
what else is present
50Economics, Job Benefits
51Biosphere Gasifier Rendering
Ecology Wet Cell
52What would we like?
- Letter of intent for projects from the
Government, waiver of import duties. - Waste contracts for all of the Various cities
waste at 40/ton PPA of 0.099 - PPP of some kind on the recycling portion of the
project. - Political support in complying with all of the
appropriate requirements.
53Letter of Commitment question, funding
- The short answer is "YES", we can obtain
commitment letters "subject to", but, -
- make no mistake, we would not take this to our
funding groups at this juncture because we have
not done ANY of our homework. We don't even have
the MOU signed and returned. -
- 1. We have no waste composition or proximate
or ultimate analysis on which to base our
engineering opinions to our own funders and
partners. We have no assurances that the waste
which would be characterized will be maintained
within normal variance. We have no moisture
content and inert contents review done. We have
had no discussions on the disposal of inerts
which will prove to be critical to this project
in a "no landfills" mandate. - 2. We have no letters of intent from any of
the Cities we are going to be working with to
provide us with take or pay contracts which
underpin our deals both on the Waste Off take
contracts and on the Power Purchase agreement.
We have no economic basis for even basic deal
economic evaluation. No tipping fees outline
with escalators, no PPA rates and acceptance
terms, no nothing! - 3. We have no site or location selected with
a logistics and permitting study, even a basic
one, done. - 4. We have no property tax deal, no
governmental guarantee on the waste contracts and
the land purchase and no waiver of import duties
in place.
54Thank you.
- We look forward to answering any of your
questions on all of the topics covered in this
presentation. - You can reach Paul Finestone at 818-995-6706, or
on email paul_at_biosphereenergy.com - Thank you.