Title: Chesterfield Borough Councils
1Case Study
Chesterfield Borough Councils Operational
Services Division Project CHRIS (Chesterfield
Housing Repairs Information System) Selecting
the best IT solutions Planning the cultural
changes Delivering real improvements
NOMAD / J Howe /Nov 06
2Operational Services Division
- In-house contractor- Domestic Housing, Civic
Industrial - General Building Construction Maintenance
(joinery, plumbing, bricklaying, roofing,
plastering, painting) - Heating and ventilation/gas fitting
- Electrical installation and repair
- Statistics
- Wide client and skills base
- 17m turnover
- 220 f.t.e employees (160 craft/productive
employees) - 34,000 responsive repair jobs 24,000 planned
works orders p.a. - 6,000 jobs out of hours emergency repairs.
- Appointments including evening/weekends are
offered for all internal works and for certain
external works orders. - Payroll Bonus scheme
- Depot based stores, Vans with imprest stock
- Purchases from local builders' merchants for
non-stock items. - Specialist plant and equipment 130 fleet
vehicles
3Why change
- Why change?
- New Tender Specification Private Sector
competitors - Reduce Cost Base
- Improve Service Customer Satisfaction Levels
- Efficiency Demands (Egan / Gershon)
- What needed to change?
- Identify key improvement opportunities
- Update IT
- Reduce Overhead Structure
- Strive for excellence (ISO / IIP / EMAS)
4How good / bad were we?
- Benchmarks and Best Practice
- Direct Works Forum (DWF)
- Association of Public Service Excellence (APSE)
- Yorkshire and Humberside DLO Managers Group
- Beacon Authorities
- Benchmarking Clubs - PS Net / Checkmate etc
5Understand the business end to end
6Understand the detail
7Look for solutions
GPS ?
8Create the Vision
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
9Create the Vision
Manage
Request
Planning Software
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
Mobile Handhelds Software
10I.S. Requirements Specification
Item
Function
Process reference
Vendor Response
Importance
Mandatory
Do Job
11Implement the vision
- Plan the organisation cultural changes
- New Procedures
- Training in systems AND process
- Marshall resources
- Select System Vendor(s)
- Measure Success
- Modify
- Re-implement
- Roll-out
- Re-measure Broadcast!
12Ownership involvement
CBC Management Team
Steering Group
QITs
IT Specification Team
Communication Team
Procurement Team
Training Development Team
13Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
- 3 Planner Supervisors
- Improved flexibility
- More appointments
- Combined visits
Do Job
Invoice
Complete
QA
14Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
- Pre-allocated stock to job
- Materials automatically logged to job
- Improved stock management
- Positioned for e-procurement
Do Job
Invoice
Complete
QA
15Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
- Improved Out of Hours Qualification
-
Complete
QA
16Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
17Benefit Projection
Manage
- Home based
- Lone worker
- Reduced administration time
- Reduced aborted calls
- More jobs per day
- 100 Rubbish collections
- Reduced variances
- Lower Fleet Vehicle costs
-
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
18Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
- Reduced manual timecard payroll activity
- Automated material invoice matching
- Reduced invoice to council lag time
- Reduced variance resolution
- Reduced paperwork
- Improved auditing
-
Material
Non- Emergency
Do Job
Invoice
Complete
QA
19Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
- Improved Service to Tenant Client
- Driver for further improvements
-
QA
20Benefit Projection
Manage
Request
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
- Reduced firefighting, better decisions
- Opportunity to win external contracts
-
Invoice
Complete
QA
2180 of ICT improvement projects fail
22Best practice approach
Best
PROCESSES
Current
Worst
Time
23Our new processes were not perfect
- Run the new processes
- Prevent old habits reappearing
- Prevent work-arounds
- Continuous improvement
- Problem solving
- Improvement targets
- Roles and Responsibilities
- Ownership through involvement
24Some of the difficulties
- Persuasion / selling job!
- Leap of Faith - Elected Members and workforce
- ICT integration harder than expected
- Council systems new - interface delays
- Big Bang approach
- People issues
- Implementation ran concurrent with major
re-structure of service area - morale at a low
ebb / much re-training needed - System discipline
- Van Stocks
- Hand-held use (training and repeat training)
25Timetable
- Sept 04 - GPS Introduced
- Operatives working from home and enjoying greater
flexibility - Better work life balance
- Coping with out of hours appointments / reduced
emergency call out costs - Jan 05 (Phase 1) - 24 Field Operatives with
Hand-Helds - Plumbing, Gas Electrical Fitters
- May 05 (Phase 2) - 38 more admitted to system
- Bricklayers Joiners
26System procurement
Prime contractor - Orange GPS - Orange
Fleetlink Main software application (Metrix) -
CSG Prolog Scheduler - CSG Prolog PDA
software application - Pervasic
27Capital Outlay and Running Costs
The capital outlay and running costs for the
first 5 years is New technology (software,
hardware, licensing, GPS etc) 500k Training,
downtime and dual running costs 100k
28GPS Costs
- Project CHRIS total costs for 5 years
(Net cost inclusive of
implementation
and applied discounts)
600,000 - Hardware software costs
(following discount
of 160k) 500,000 - GPS fitted to 125 vehicles
(GPS Inst and
5 year running costs before discount)
198,480 - GPS (5 Year costs following
proportional discount) 135,000 - GPS
(Cost per
vehicle) 1,080/year
(approx 3.00/day)
29Annual Financial Savings
Initial savings have been realised on a phased
basis during the first 2 years of operation -
projected annual savings based on these results
are- Overhead staff savings of
243,400 Fuel Savings
24,100 Transport Savings
14,400 Productivity increases measured at
10.58 221,400 503,000
30CHRIS - Cumulative Savings
31Service improvements achieved (1)
- 96.4 of all responsive repairs completed on
time against far tighter targets - Void re-let times reduced by average of 20 days
- Same volume of work produced by fewer employees
- Gas service access problems improved through use
of integrated systems - More Appointments offered (up to 95 of all work
carried out by fixed or loose appointments) - Customer satisfaction has increased from 80 to
91 - Single visit completions achieved through
improved co-ordination of multiple repair
requests, better work scheduling, improved
vehicle stocks and increased number of
appointments
32Service improvements achieved (2)
- Right first time targets improved by on site
electronic variation request / authorisation - Improved management control information (real
time visibility) - Improved rubbish collection service
- Reduction in fuel and paper use resulting in
environmental benefits. - Lone worker safety and security enhanced by
better control methods
33Is the system sustainable?
- Planned to have a 5 year life to match contract
duration but has the capability for ongoing
development especially into other areas of the
Authority - Looking to refine and enhance some processes
- Improved PDAs and network coverage by adapting
to 3G - Text messaging service linked to appointments
- On site copying of CP12 certificate etc
- Pit stop approach for re-stocking vans
- Electronic ordering of materials from suppliers
- PDAs to be issued to surveyors for instant
order raising in the field
34Why does CHRIS appear to work when other systems
falter?
- Well researched before embarked - best fit for
Chesterfield - External assistance during feasibility and
implementation stages - Bespoke specification - complete system
integration - Operatives pay linked to correct use of system,
no outputs no pay - Involved operatives, T Unions and back office
staff from the start - Ownership - (QIT teams, focus groups, steering
groups etc..) - Led end to end by senior managers - (needs drive
and enthusiasm) - Regular reviews and corrective actions
- Linked to scope of ISO QA Scheme - complete
re-write of systems procedures - Data dump/fault logs - griping sessions - Team
Briefings with regular feedback
35Project CHRIS - Some external achievements to
date.
- Winner - IMBM - The British Building
Maintenance Awards 2006 - Winner of APSE Best Efficiency Initiative
2006 - Seen by IDeA as an E -Gov Best Practice Model
- Used by Audit Commission as an example of
Notable practice and forms a benchmark for UOR
VFM comparisons - Has helped to attain and maintain BS EN ISO
9001 2000 / I.I.P EMAS - NOMAD case study
36End of Presentation
Thank you for your interest
37Ring-fence our sphere of influence
38Identify current process problems
39Create the Vision
Manage
Request
Planning Software
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
40Create the Vision
Manage
Request
Planning Software
Schedule Job
Client
Emergency
Material
Non- Emergency
Do Job
Invoice
Complete
QA
Mobile Handhelds Software
41Create the Vision
Manage
Request
Planning Software
Schedule Job
Client
Emergency
Automatic Scheduling
Material
Non- Emergency
Do Job
Invoice
Complete
QA
Mobile Handhelds Software
42Look for solutions
43Create the Vision
Management Reporting
Manage
Request
Planning Software
Schedule Job
Client
Emergency
Automatic Scheduling
Material
Non- Emergency
Do Job
Invoice
Complete
QA
Mobile Handhelds Software
44(No Transcript)
45Schedule/Planning
46Schedule/Planning Board
These Operatives shown as on Holiday for this
period
47J SMITH
01246 452146
GEORGE
22/8/2006
48(No Transcript)
49THE MOBILE DEVICE
THE MOBILE DEVICE WHICH IS USED BY THE OPERATIVES
TO RECEIVE THEIR WORK
50WHAT THE OPERATIVE SEES
ADDRESS AND JOB DETAILS
APPOINTED JOB FOR MONDAY AT 8.00am
ACCESS NOTES
51WHAT THE OPERATIVE SEES
ACCESS NOTES DETAILS
52WHAT THE OPERATIVE SEES
TENANT DETAILS
ACCESS DETAILS
53WHAT THE OPERATIVE SEES
RELEVANT JOB DETAILS
OPTION TO ORDER MATERIALS IN ADVANCE FROM STORES
54WHAT THE OPERATIVE SEES
Renew double base unit 2/5/2006 Repair
double socket in kitchen
15/6/2006 Replace damaged
sink base unit (TEAK Effect)
5/9/2006
PREVIOUS ASSOCIATED REPAIRS
55WHAT THE OPERATIVE SEES
OPERATIVES OPEN UP THIS SCREEN ONCE ON SITE AND
HAVE THE FOLLOWING OPTIONS AVAILABLE TO THEM
56WHAT THE OPERATIVE SEES
CONFIRMS ON SITE AND STARTS WORK
57WHAT THE OPERATIVE SEES
RECORDS MATERIALS USED ON THE JOB FROM THE VAN
STOCK
58WHAT THE OPERATIVE SEES
CONFIRMS THE JOB HAS BEEN COMPLETED
59WHAT THE OPERATIVE SEES
RECORDS THAT RUBBISH HAS BEEN CREATED AND
REQUIRES REMOVAL
CONFIRMS THE ACTIVITY ON SITE
60WHAT THE OPERATIVE SEES
THE OPERATIVE CONFIRMS THE JOB IS COMPLETED
TENANT SIGNS TO SAY THE JOB IS COMPLETED AND IS
TO THEIR SATISFACTION
61WHAT THE OPERATIVE SEES
JOB COMPLETED OFF THE JOB LIST
62WHAT THE OPERATIVE SEES
RUBBISH JOB HAS NOW BEEN ISSUED TO THE RUBBISH
TEAM ON THE DEVICE FOR COLLECTION
63(No Transcript)
64(No Transcript)
65(No Transcript)
66GPS VEHICLE TRACKER
67GPS VEHICLE TRACKER
LOCATION OF VEHICLE
68(No Transcript)
69Crystal Report