Title: DECK PROTECTION SYSTEMS FOR POSTTENSIONED SEGMENTAL CONCRETE BRIDGES
1DECK PROTECTION SYSTEMS FOR POST-TENSIONEDSEGMENT
AL CONCRETE BRIDGES
- Michael M. Sprinkel, P.E.Associate
DirectorVirginia Transportation Research Council
2INTRODUCTION
- Post-tensioned segmental concrete bridge
construction is economical for many applications. - The economy increases as the number of segments
increases. - Concern cost effective repair if chlorides reach
critical reinforcement in the superstructure. - A deck protection system is required to prevent
the infiltration of chloride ions.
3OBJECTIVE
The objective of this paper is to compare
conventional and new deck protection systems for
post-tensioned segmental concrete bridges.
4Conventional Deck Protection Systems
- Thin bonded hydraulic cement concrete overlay
- Waterproof membrane overlaid with asphalt
5New Deck Protection Systems
- Thin bonded epoxy concrete overlay
- Monolithically cast concrete
- Low permeability concrete segments
6Thin Bonded Hydraulic Cement Concrete Overlay
7Waterproof Membrane Overlaid With Asphalt
8Thin Bonded Epoxy Concrete Overlay
9Monolithically Cast Concrete
10Low Permeability Concrete Segments
11Thin Bonded Hydraulic Cement Concrete Overlay
complex, expensive, high risk of failure
- High bond strength often a problem
- Low permeability easily obtained
- Few cracks often a problem
- Good skid resistance, ride quality, and surface
appearance typically not a problem
12Thin Bonded Concrete Overlay milling surface of
segments causes fractures that result in low bond
strength
13Thin Bonded Concrete Overlay poor consolidation
of bottom of 3-in thick overlay causes low bond
strength
14Thin Bonded Concrete Overlay shrinkage cracks
reduce protection and increase risk of
delamination of overlay
15Waterproof Membrane Overlaid With Asphalt
complex, expensive, high risk of failure
- Waterproof membrane must be carefully constructed
so that it does not leak - Asphalt must be appropriate mixture
- Asphalt overlay must be properly compacted
- New membrane and overlay after 15 years
16Thin Bonded Epoxy Concrete Overlay simple, low
cost, low risk of failure
- Shot blast concrete surface
- Place two layers of epoxy and aggregate
- 15 to 30 year life
- Easy to repair and replace
- Spall is not a major problem because of 0.25-in
thickness
17Thin Bonded Epoxy Concrete Overlay 2 layers of
epoxy and broadcast aggregate provide 0.25-in
wearing, protective surface
18Monolithically Cast Concrete simple, low cost,
low risk of failure
- Extra concrete is placed as segment is
constructed - Extra concrete removed years later when
contaminated with chloride - New thin bonded overlay placed after removing
chloride contaminated concrete
19Low Permeability Concrete Segments simple, low
cost, low risk of failure
- Low permeability concrete is placed as segment is
constructed - Concrete does not become contaminated with
sufficient chloride to cause corrosion for more
than 100 years - Separate deck protection system not required
20Permeability,1 year, concrete deck mixtures,
coulombs (AASHTO T277)Ref. 1 Ozyildirim, TRR
1610, 1998
21Time to Corrosion of 1970 Concrete and 2003 Low
Permeability Concrete Ref. 2 Pyc, VTRC 00-R16,
2000
22Low Permeability Concrete
- The use of a protection strategy other than
casting the segments with low permeability
concrete is difficult to justify.
23Construction Steps Required For Deck Protection
Systems
24Construction Steps Required For Deck Protection
Systems
25Cost Data For Deck Protection Systems
- Average values based on bid tabulations between
1999 and 2002 obtained from the Virginia
Department of Transportation bridge office. Bid
data is for many types of bridges with concrete
decks (cast in place concrete on beams,
prestressed box beams, prestressed slabs,
post-tensioned segmental).
26Cost of Deck Protection Systems,/yd2
27Conclusions
- Use of low permeability concrete in segments is
the most practical and economical deck protection
system. Concretes with low water to cement
ratios and pozzolans or slag should provide a
service life of more than 150 years. - Monolithic concrete is practical and economical
when a sacrificial concrete cover is required.
28Conclusions
- Thin epoxy overlays are practical when an
impermeable overlay is required. Low cost and
ease of maintenance make it ideal for
post-tensioned segmental concrete bridges. - Use of thin bonded hydraulic cement concrete
overlays and waterproof membranes overlaid with
asphalt should be reduced. These protection
systems are the most complicated and expensive
and come with a high risk of failure.
29Thank You