Climate change: Meeting the challenge of flood risk - PowerPoint PPT Presentation

1 / 80
About This Presentation
Title:

Climate change: Meeting the challenge of flood risk

Description:

On-site attenuation of the 100 year event. Run off rate = green field site. EA ... 1 Credit Sustainable Urban Drainage attenuate 50% of the peak flow rate to ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 81
Provided by: danmit
Category:

less

Transcript and Presenter's Notes

Title: Climate change: Meeting the challenge of flood risk


1
Climate changeMeeting the challenge of flood
risk
  • James Sharp - Pellings LLP
  • Planning Flood Risk
  • Alan Fogarty - Cundall
  • Flood Risk Assessments
  • Peter Wade - Pellings LLP
  • Flooding Why we should care and what we can do

2
James Sharp
  • Planning Flood Risk

3
Planning and flood risk
  • 2007 The Year of the Flood
  • 13 killed in Northern and Western England
  • 48,000 homes and 7,000 businesses inundated
  • Massive disruption and financial losses

4
Assessment of flood risk
5
Types of flooding
  • Flooding from rivers
  • Flooding from the sea
  • Flooding from land
  • Flooding from ground water
  • Flooding from sewers
  • Flooding from reservoirs, canals, and other
    artificial sources

66 of homes flooded in summer 2007 occurred from
surface water drains, culverts and sewers
6
(No Transcript)
7
PPS25 Development and flood risk
  • Key Objectives
  • Appraising Risk
  • Managing Risk
  • Reducing Risk

8
Key features of PPS25 are as follows
  • A strategic, plan led focus with more front
    loading of flood risk
  • More attention to flooding from sources other
    than rivers and the sea
  • Formalisation of regional flood risk appraisals
    and strategic flood risk assessments,
    contributing to sustainability appraisals and
    soundness tests
  • A stronger sequential approach to allocating land
    and granting permission in areas at risk of
    flooding

9
Key features of PPS25 are as follows
  • Introduction of vulnerability classes for
    different types of development
  • Climate change allowances based on the UK climate
    impact programme 2002 projections to provide a
    quantifiable measure for developers and planners
  • A new Exception Test where development in flood
    zones is needed for wider sustainability reasons
  • A focus on the consequences as well as the
    probability of flooding, because the schemes have
    to be safe over their life time taking climate
    change into account

10
Flood zones
  • Zone 1 Low probability
  • Less than in 1,000 annual probability of river or
    sea flooding in any year
  • Zone 2 Medium probability
  • Between a 1 in 100 and 1 in 1,000 annual
    probability of river flooding or a 1 in 200 and
    1 in 1,000 annual probability of sea flooding in
    any year
  • Zone 3a High probability
  • 1 in 100 or greater annual probability of river
    flooding or 1 in 200 or greater annual
    probability of flooding from the sea in any year
  • Zone 3b The functional flood plain
  • Land where water has to flow or be stored at
    times of flood

11
(No Transcript)
12
(No Transcript)
13
The Exception Test
  • For the Exception Test to be passed
  • It must be demonstrated that the development
    provides wider sustainability benefits to the
    community that outweigh flood risk
  • The development should be on developable
    previously developed land
  • A FRA must demonstrate that the development will
    be safe, without increasing flood risk elsewhere,
    and, where possible, will reduce flood risk
    overall

14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Alan Fogarty
  • Flood Risk Assessments

19
Flood Risk Assessments
20
Introduction
  • Introduction
  • Flood Risk Assessment
  • BREEAM
  • SUDS

21
PPS 25 Development Flood Risk
  • Securing the Future preparing for the climate
  • change that cannot now be avoided
  • Rising sea levels
  • High intensity rainfall
  • River flooding
  • Flash flooding

22
Climate Change
  • Rising Sea Level
  • Land rising in the North
  • Dropping in the South East

23
Climate Change UK 2000
24
Swiss Alps
200?
1875
25
Climate Change Ireland 2000
26
Climate Change
  • Deeper water increased wave height
  • Increased wind speed
  • Greater potential for storm surges

27
Flooding
  • A natural phenomena types
  • River
  • Sea
  • Land
  • Rising Groundwater
  • Sewers

28
Planning Authorities
  • Regional and Local authorities should
  • Appraise Risk Regional flood risk assessment
  • Manage Risk Identify low risk sites and
    restrict development in higher risk sites
  • Reduce Risk Storage, SUDS, Defences

29
Testing
  • Sequential Test Direct development to sites of
    lower risk
  • Exception Test Where Sequential Test cannot
    deliver acceptable sites, but development is
    necessary to avoid social or economic blight and
    the need for essential civil infrastructure to
    remain operation during floods

30
Environmental Agency
  • The Environment Agency has statutory
    responsibility for flood management and defence
    in England
  • Will support the planning system
  • Providing timely information and advice on
    flooding issues that is fit for purpose

31
Environmental Agency Flood Maps
32
Planning Flood Risk Assessment
  • FRA are required in almost all cases
  • Large developments and high risk areas require
    direct discussions with EA
  • Otherwise directly with the LPA

33
EA Flood Zones
34
Purpose of Flood Risk Assessment
  • Identify whether site at risk from current or
    future flooding
  • Demonstrate that the site is safe and reduces
    overall flood risk
  • Identify any flood risk elsewhere
  • Mitigation

35
Methodology of Flood Risk Assessment
  • Conduct a background search including
    consultation with EA Local Authority or other
    potential sources of data.
  • Review topographic survey of the site and
    proposed site layouts in relation to the
    potential flood risks and procure additional
    survey as required.
  • For surface water drainage, assess the existing
    and proposed surface water runoff from the site
    based on proposed layouts.
  • For fluvial flood risk build a mathematical
    hydraulic model of to confirm the extent of the
    flood risk.
  • Attend project meetings to discuss the
    development of an outline drainage scheme.
  • Assess all other potential sources of flood
    risk-such as overland flow and groundwater
    flooding.
  • Advise the design team on issues that may affect
    the acceptability of the scheme to the
    Environment Agency and Local Authority.
  • Agree mitigation measures through
    discussions/meetings with the Environment Agency.
  • Prepare a flood risk assessment report to submit
    with the planning application to the Local
    Authority. A discussion of mitigation measures to
    minimise the flood risks will be included in the
    report.

36
EA Flood Zones
  • Zone 1 Low Probability site not at risk from
    flooding from adjacent watercourses or marine
    tides. Suitable for all development types.
  • Zone 2 Medium Probability site lies within
    the floodplain of the extreme flood event. Not
    suitable for police/fire stations, basement
    dwellings, permanent caravan parks.
  • Zone 3 High Probability A site lies within
    the floodplain of the 1 probability event.
    Water compatible and essential infrastructure.

37
EA Flood Zones
  • Zone 1 the primary flood risk is to others by
    surface water runoff
  • Mitigation EA
  • Encourages SUDS
  • On-site attenuation of the 100 year event
  • Run off rate green field site

38
EA Flood Zones
  • Zone 2 3 on and off site risk
  • Mitigation EA
  • No habitable spaces below 1 flood level
  • Occupants must be able to evacuate safely
  • Developments should not obstruct flood waters or
    reduce flood plane storage

39
EA Flood Zones
40
BREEAM
  • 2 Credits in a zone with low annual probability
    of flooding or
  • 1 Credit in a zone of medium annual probability
    of flooding and the ground level, car parking and
    access is above the design flood level

1.5 .75
41
BREEAM
  • 1 Credit Sustainable Urban Drainage attenuate
    50 of the peak flow rate to natural watercourses
    or municipal drainage systems, in Zone 1 or
  • 1 Credit Sustainable Urban Drainage attenuate
    75 of the peak flow rate to natural watercourses
    or municipal drainage systems, in Zone 2 or
  • 1 Credit Sustainable Urban Drainage attenuate
    100 of the peak flow rate to natural
    watercourses or municipal drainage systems, in
    Zone 3

1.5
No credit awarded if development has proceeded
against the recommendation of the relevant flood
defence agency
42
Mitigation Traditional Drainage Problems
  • Designed to move rainwater rapidly to either a
    watercourse or soak away
  • Hard surface run-off increase the risk of
    flooding downstream, as well as speed
  • Surface water run-off can contain contaminants
    such as oil, affecting biodiversity and potential
    use
  • Diverting rainfall to piped systems, depletes
    ground water in dry weather

43
Mitigation SUDS
  • Sustainable Urban Drainage Systems
  • Reduce the potential of flooding on new and
    existing developments
  • Helps to protect and enhance ground water quality

44
Mitigation SUDS
Permeable Pavement
45
Mitigation SUDS
Surface Water retention filtration
46
Mitigation SUDS
Attenuation Tanks
47
Summary
  • Increased Planning complexity
  • Early consultation with EA
  • Early consultation with Local Planners

48
Peter Wade
  • Flooding Why we should care and what we can do

49
(No Transcript)
50
(No Transcript)
51
(No Transcript)
52
(No Transcript)
53
(No Transcript)
54
(No Transcript)
55
(No Transcript)
56
(No Transcript)
57
Facts and Figures
  • 1 in 3 new homes will be built on floodplains
  • Two million homes are at risk 1 in 10
  • 200,000 homes are at very high risk
  • 160,000 businesses are at risk
  • The average annual damage from flooding is
    currently 1 billion. This could increase to 20
    billion if we take no effective action
  • Risks from weather are increasing by 2.4 per
    year on ABI evidence

58
Facts and Figures
  • Sea levels are rising by 3.1mm per year
  • High water in London has risen by 0.8 metre per
    century
  • Global mean sea level has risen about 0.22 metre
    per century. With global warming this could
    become 0.33 metre
  • Last years floods led to 55,000 homes being
    flooded and the damage costing 3 billion.
    Average claims were 20,000 per property

59
What can be done?
  • A new Thames Barrier is planned along with
    improvements to flood defences
  • The new Thames Tideway Tunnel is planned to
    assist with sewer surcharge
  • Owners of properties should carry out audits to
    establish which ones are at risk
  • Owners should undertake physical measures where
    possible such as moving equipment out of basement
    areas, installing electronic warning devices and
    having temporary barriers, airbrick covers etc
    ready in the event of imminent flooding

60
What can be done?
  • New buildings should be designed to cope with
    flooding
  • Elements of both existing and new buildings can
    be designed to be more resilient to flood waters
    such as use of render plaster, keeping electrics
    above flood levels and making basement and ground
    storeys watertight where possible
  • In the event of imminent flooding, valuable or
    essential items should be moved away from the
    flood risk areas
  • Take a photographic record of the existing
    condition of the property particularly where
    historic buildings are involved

61
What can be done?
  • Prepare a flood plan and ensure all occupiers
    know what to do and agree evacuation routes
  • If flooding is likely, turn off electrical power
    and gas supplies
  • Avoid moving in flood water as it is nearly
    always contaminated. Following a flood,
    sterilisation of internal areas is important and
    power supplies should be checked before being
    re-connected
  • Check with the Environmental Health Department
    whether contaminants are likely to be present
  • Soil beneath timber floors may need to be
    completely removed if contaminated

62
What can be done?
  • With historic buildings special care is needed
    and consent may be required to replace damaged
    timber and plaster finishes
  • Dry out buildings slowly or else historic
    features could be damaged. Where possible use low
    background heating, natural ventilation and
    dehumidifiers
  • With new buildings, minimise the use of hard
    landscaping to avoid excessive run-off and
    surcharging of drains
  • With new drainage installations in vulnerable
    areas, install one-way valves and ensure drainage
    connections can be turned-off if surcharging is
    likely

63
What can be done?
  • Check all drains following a flood as silt and
    debris can cause blockages
  • Monitor timber for evidence of fungi and rot for
    at least six months after a flood
  • Some defects will only become apparent many
    months after the building has dried out

64
(No Transcript)
65
(No Transcript)
66
(No Transcript)
67

68

69
(No Transcript)
70
(No Transcript)
71
(No Transcript)
72
The Thames Barrier
  • It was 1922 when central London last flooded
    killing 14 people and causing widespread damage
  • 1953 was a major wake-up call. A storm surge
    caused 300 deaths and this largely affected the
    lower parts of the Thames
  • The barrier was designed in the 1970s when sea
    levels were rising by 1.8mm per year. Levels are
    now rising by 3.1mm per year
  • The barrier opened in 1984 at a cost of around
    500 million
  • The barrier is designed to cope with 8mm of sea
    rise per year and should cope with a 1 in 1,000
    year storm surge up to 2030

73
The Thames Barrier
  • A new barrier is currently being planned as the
    predictions are worsening
  • Current climate predictions are optimistic and it
    is thought that by 2030 the current barrier may
    not be able to cope
  • Much depends on the rate of melting of the
    Greenland and Antarctic ice sheets. Latest
    evidence shows these to be melting at an alarming
    rate
  • It could take 20 years to design and construct a
    new barrier and associated flood defences

74
(No Transcript)
75
(No Transcript)
76
Thames Tideway Tunnel
  • In 2006 the Minister of State for Climate Change
    and the Environment approached Thames Water to
    look at ways of tackling Londons sewer
    overflows. This was following recent discharges
    of raw sewage directly into the River Thames.
    This is a regular occurrence
  • Thames Water produced two options, the most
    likely one being the construction of a 30km long
    tunnel beneath the Thames
  • This tunnel will be 7 metres in diameter and the
    work will also include improvements to the
    Beckton Sewage Works and other major sewers
  • The latest estimated cost is 1.7 billion

77
Thames Tideway Tunnel
  • The work will be subject to a Public Enquiry and
    the purchasing of land
  • It is likely that the work will take up to 13
    years to complete and there is a need to complete
    some of the work in time for the Olympics
  • At the present rate, the work could add up to 50
    to each of Thames Waters customers annual bills
  • In addition to reducing raw sewage discharge into
    the Thames, it is hoped that surcharging of
    secondary sewers throughout London will be
    alleviated. This risk increases with increased
    development
  • Remember that last year 66 of homes flooded was
    due to drain and sewer surcharges

78
(No Transcript)
79
Sources of Information
  • The following websites are useful sources
  • Environment Agency www.environment-agency.gov.uk
  • Environment Agency postcode search facility
    www.environment-agency.gov.uk/subjects/flood
  • Thames Water www.thames-water.com
  • English Heritage www.english-heritage.org.uk
    (use search box for the Technical Advice Notes)
  • Association of British Insurers www.abi.org.uk
  • In addition the internet is an excellent source
    of flood prevention productswww.aquatitesystems.
    com, www.floodark.co.uk, www.floodguards.com,
    www.floodgate.ltd.com

80
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com