Title: Construction of Crack Free Concrete Bridge Decks TPF5051
1Construction of Crack Free Concrete Bridge Decks
TPF-5(051)
- Richard L. McReynolds, P.E.
- Engineer of Research
2Approval Process for Transportation Pooled Fund
Projects
- Solicitation requests are evaluated as received
by technical area Bureau Chief(s), myself, Chief
of Transportation Planning, Division Director and
Asst. Sec. and STE. - Typically reviews and approvals of funding are
completed within a week or two of initial receipt
using e-mail. - With KS as lead state Work plan and project cost
estimate are prepared for internal review. KDOT
commitment is determined. Same approvals as above
are then required before solicitation is posted.
3Current TPF Project Participation
- FFY 2005 funds obligated to 19 projects.
- FFY 2006 funds currently obligated/ committed to
19/20 projects. - FFY 2007 funds committed to 17 projects to date.
4Pooled Fund Project Budgets
5TPF Projects as Lead Agency
- Currently KS is Lead State on 6 active projects.
- To date since May 2000, 3,184,898 has been
placed under contract on these projects. - Most contracted with KSU and KU.
- Three are nearing completion.
- One is ongoing with an annual program.
- A 7th project has been completed except for final
close out by the FHWA Finance Office.
6Construction of Crack Free Concrete Bridge Decks
TPF-5(051)
- University of Kansas
- Dr. David Darwin, Co-PI
- Dr. JoAnn Browning, Co-PI
- Ken Hurst, Engineering Manager, State Bridge
Office, KDOT Project Monitor - 15 states FHWA have contributed to date
- 950,000 contract
- 9/1/2002 to 3/30/2008
7Project Benefits to Participants
- With a 60K contribution, each state has an
option of having the KU research team meet with
their personnel to discuss and evaluate their
designs and materials specifications. - Team makes recommendations to reduce cracking.
- Team on site during construction of a control and
test bridge to observe and do testing. - Team will perform periodic crack surveys after
construction. - Materials testing also being done at KU to
evaluate basic related materials properties.
8Low Cracking - High Performance Concrete (LC-HPC)
Bridge Decks
- By
- David Darwin, JoAnn Browning, Will D.
Lindquist, Heather K. McLeod, and Swapnil
Deshpande - University of Kansas
2006 Concrete Bridge Conference Reno, Nevada May
7-10
9Research supported by
- 15 State DOTs Delaware, Kansas, Idaho, Indiana,
Michigan, Minnesota, Mississippi, Missouri,
Montana, New Hampshire, North Dakota, Oklahoma,
South Dakota, Texas, Wyoming - FHWA
- Lead state Kansas
10Outline
- Project scope
- Why were using LC-HPC
- Specifications for LC-HPC decks
- Progress and where were going
1120 Bridges
Project Scope
- So far
- 13 planned for Kansas
- 2 planned for South Dakota
12Selection of Bridges
- Composite steel girder bridges
- Full-depth slabs
- Removable forms
- Matching bridges to serve as a control where
possible
13Why LC-HPC?
1476 mm (3 in.)
Off cracks
15On cracks
76 mm (3 in.)
16Specifications
17Overall Approach
- Low cement water contents
- Low slump
- High strength is not always good
- Low evaporation rate
- Construction methods and materials matter
- More early cracking means more total cracking
18LC-HPC
- 1 inch Max Size Aggregate
- Optimized Aggregate Gradation
- Cement Content lt 535 lb/yd3
- Air Content of 8 11/2
- Max w/c ratio of 0.42
- Improved curing
- Controlled temperature
19Thermal Cracking
- Rule of Thumb Cracking will result when the
temperature of the concrete deck exceeds the
temperature of the girders by more than 20 C
(36 F).
20Thermal Cracking
- PennDOT1 15 C (27 F)
- KsDOT 14 C (25 F)
1 Pennsylvania Department of Transportation,
Prevention of Cracks in Concrete Bridge Decks
Summary Report, Report No. 89-01, March 1996.
21Alternatives to Pumping
- Concrete Buckets
- Conveyor Belts
22(No Transcript)
23Consolidation Requirements
- Vertically mounted internal gang vibrators
24Finishing
25Machine Fogging
26Early Wet Burlap Cure within 10 minutes
27Curing
- 14 days wet cure with burlap, soaker hoses, and
plastic - Followed by curing compound to slow the rate of
evaporation
28Trial Slab
- To demonstrate implementation of the specialized
process and address problems before bridge deck
casting. - Process
- Contractor
- Ready Mix Plant
- Inspectors
NO SUPRISES
29Progress and where were going
- Two LC-HPC and four control bridges constructed
- First crack surveys completed
- Three more LC-HPC bridges scheduled for this
spring.
30Testing low shrinkage mix designs
- Fly ash
- Slag
- Silica fume
- Shrinkage reducing admixtures
31Average Free Shrinkage (Drying Only). 535 lb/yd3
Type I/II Cement
32Average Free Shrinkage (Drying Only). 535 lb/yd3
Type I/II Cement w/cm 0.42, 23.26 paste
33Average Free Shrinkage (Drying Only). w/cm
0.42, 23.26 paste
34Average Free Shrinkage (Drying Only). w/cm
0.42, 23.26 paste
35Questions?