Construction of Crack Free Concrete Bridge Decks TPF5051 - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

Construction of Crack Free Concrete Bridge Decks TPF5051

Description:

Solicitation requests are evaluated as received ... Early Wet Burlap Cure within 10 minutes. Curing. 14 days wet cure with burlap, soaker hoses, and plastic ... – PowerPoint PPT presentation

Number of Views:205
Avg rating:3.0/5.0
Slides: 36
Provided by: Dic950
Category:

less

Transcript and Presenter's Notes

Title: Construction of Crack Free Concrete Bridge Decks TPF5051


1
Construction of Crack Free Concrete Bridge Decks
TPF-5(051)
  • Richard L. McReynolds, P.E.
  • Engineer of Research

2
Approval Process for Transportation Pooled Fund
Projects
  • Solicitation requests are evaluated as received
    by technical area Bureau Chief(s), myself, Chief
    of Transportation Planning, Division Director and
    Asst. Sec. and STE.
  • Typically reviews and approvals of funding are
    completed within a week or two of initial receipt
    using e-mail.
  • With KS as lead state Work plan and project cost
    estimate are prepared for internal review. KDOT
    commitment is determined. Same approvals as above
    are then required before solicitation is posted.

3
Current TPF Project Participation
  • FFY 2005 funds obligated to 19 projects.
  • FFY 2006 funds currently obligated/ committed to
    19/20 projects.
  • FFY 2007 funds committed to 17 projects to date.

4
Pooled Fund Project Budgets
5
TPF Projects as Lead Agency
  • Currently KS is Lead State on 6 active projects.
  • To date since May 2000, 3,184,898 has been
    placed under contract on these projects.
  • Most contracted with KSU and KU.
  • Three are nearing completion.
  • One is ongoing with an annual program.
  • A 7th project has been completed except for final
    close out by the FHWA Finance Office.

6
Construction of Crack Free Concrete Bridge Decks
TPF-5(051)
  • University of Kansas
  • Dr. David Darwin, Co-PI
  • Dr. JoAnn Browning, Co-PI
  • Ken Hurst, Engineering Manager, State Bridge
    Office, KDOT Project Monitor
  • 15 states FHWA have contributed to date
  • 950,000 contract
  • 9/1/2002 to 3/30/2008

7
Project Benefits to Participants
  • With a 60K contribution, each state has an
    option of having the KU research team meet with
    their personnel to discuss and evaluate their
    designs and materials specifications.
  • Team makes recommendations to reduce cracking.
  • Team on site during construction of a control and
    test bridge to observe and do testing.
  • Team will perform periodic crack surveys after
    construction.
  • Materials testing also being done at KU to
    evaluate basic related materials properties.

8
Low Cracking - High Performance Concrete (LC-HPC)
Bridge Decks
  • By
  • David Darwin, JoAnn Browning, Will D.
    Lindquist, Heather K. McLeod, and Swapnil
    Deshpande
  • University of Kansas

2006 Concrete Bridge Conference Reno, Nevada May
7-10
9
Research supported by
  • 15 State DOTs Delaware, Kansas, Idaho, Indiana,
    Michigan, Minnesota, Mississippi, Missouri,
    Montana, New Hampshire, North Dakota, Oklahoma,
    South Dakota, Texas, Wyoming
  • FHWA
  • Lead state Kansas

10
Outline
  • Project scope
  • Why were using LC-HPC
  • Specifications for LC-HPC decks
  • Progress and where were going

11
20 Bridges
Project Scope
  • So far
  • 13 planned for Kansas
  • 2 planned for South Dakota

12
Selection of Bridges
  • Composite steel girder bridges
  • Full-depth slabs
  • Removable forms
  • Matching bridges to serve as a control where
    possible

13
Why LC-HPC?
  • Chlorides
  • Cracks

14
76 mm (3 in.)
Off cracks
15
On cracks
76 mm (3 in.)
16
Specifications
17
Overall Approach
  • Low cement water contents
  • Low slump
  • High strength is not always good
  • Low evaporation rate
  • Construction methods and materials matter
  • More early cracking means more total cracking

18
LC-HPC
  • 1 inch Max Size Aggregate
  • Optimized Aggregate Gradation
  • Cement Content lt 535 lb/yd3
  • Air Content of 8 11/2
  • Max w/c ratio of 0.42
  • Improved curing
  • Controlled temperature

19
Thermal Cracking
  • Rule of Thumb Cracking will result when the
    temperature of the concrete deck exceeds the
    temperature of the girders by more than 20 C
    (36 F).

20
Thermal Cracking
  • PennDOT1 15 C (27 F)
  • KsDOT 14 C (25 F)

1 Pennsylvania Department of Transportation,
Prevention of Cracks in Concrete Bridge Decks
Summary Report, Report No. 89-01, March 1996.
21
Alternatives to Pumping
  • Concrete Buckets
  • Conveyor Belts

22
(No Transcript)
23
Consolidation Requirements
  • Vertically mounted internal gang vibrators

24
Finishing
25
Machine Fogging
26
Early Wet Burlap Cure within 10 minutes
27
Curing
  • 14 days wet cure with burlap, soaker hoses, and
    plastic
  • Followed by curing compound to slow the rate of
    evaporation

28
Trial Slab
  • To demonstrate implementation of the specialized
    process and address problems before bridge deck
    casting.
  • Process
  • Contractor
  • Ready Mix Plant
  • Inspectors

NO SUPRISES
29
Progress and where were going
  • Two LC-HPC and four control bridges constructed
  • First crack surveys completed
  • Three more LC-HPC bridges scheduled for this
    spring.

30
Testing low shrinkage mix designs
  • Fly ash
  • Slag
  • Silica fume
  • Shrinkage reducing admixtures

31
Average Free Shrinkage (Drying Only). 535 lb/yd3
Type I/II Cement
32
Average Free Shrinkage (Drying Only). 535 lb/yd3
Type I/II Cement w/cm 0.42, 23.26 paste
33
Average Free Shrinkage (Drying Only). w/cm
0.42, 23.26 paste
34
Average Free Shrinkage (Drying Only). w/cm
0.42, 23.26 paste
35
Questions?
Write a Comment
User Comments (0)
About PowerShow.com