Title: USE OF PROMOTER PIPE WITH DOWNHOLE HEAT EXCHANGER IN KLAMATH FALLS, OREGON
1USE OF PROMOTER PIPE WITH DOWNHOLE HEAT EXCHANGER
IN KLAMATH FALLS, OREGON
- John W. Lund Tonya Toni Boyd
- Geo-Heat Center
- Bill Hack Hachman Bruce Huffman
- Pacific Plumbers, Corp.
2BACKGROUND
- Downhole heat exchangers (DHE) used in Klamath
Falls since the 1930s - Also, used in Rotorua, New Zealand, Moana (Reno),
NV, Turkey, Iceland, Hungary, Russia - Consists of one or more closed-loop pipes
circulating water suspended in a well extracting
only heat - Capacity from 100 kW to several MWt
- In wells up to about 500 ft (150 m) most
economical, but have worked in depths to 1,500 ft
(450 m)
3Typical DHE installation in Klamath Falls
4DHE in Klamath Falls
5TYPICAL DESIGN
- Well 10 to 12-in. (25 to 30-cm) diameter with
8-inch (20-cm) diameter casing - 2-inch (5-cm) diameter heating loop
- 2.5 to 3-inch (6 to 7.5-cm) diameter in larger
installations - ¾ to 1-inch (2 to 2.5-cm) domestic hot water loop
- Well completion must have space between casing
and well bore - Casing perforated at the bottom at live water
flow and just below the minimum static water
level at the top
6OPERATING CONDITIONS
- Rule of thumb 1,500 Btu/hr/ft (1.4 kW/m)
- 140oF (60oC) minimum well water temperature
- Thermo-syphoning gravity feed of water
- 15 - 25 gpm(1.0 - 1.5 L/s)
- 10 - 20oF (5 - 11oC) temperature change
- 3 5 psi (0.2 0.35 bar) pressure difference
between supply and return lines - Vertical velocity in well of 0.04 0.4 fps (0.01
0.1 m/s) with maximum of 2 fps (0.6 m/s)
7Casing completion to provide vertical convection
cell
8PROBLEMS
- If casing not perforated home owners stimulate
vertical flow by pumping and dumping into the
storm sewer. - Normally black-iron pipe used
- Corrosion at the air-water interface
- Cross-linked polyethylene (PEX) pipe used to
solve corrosion problem and for ease of
installation
9(No Transcript)
10Temperature depth diagram before and after
perforating the casing.
11PEX pipes and corrosion of DHE
12NEW ZEALAND EXPERIENCE
- Rotorua high temperature wells up to 320oF
(160oC) cannot be perforated or stand open due to
several layers of cold water - A system using promoter pipes was developed
- Pipe (convector) open at both ends suspended in
the well below the water surface producing a
convection cell bringing hot water up from the
bottom. - DHE installed next to the convector or inside the
convector depending upon the room
13New Zealand promoter pipe installation
14KLAMATH FALLS BACKGROUND
- Many of the earlier wells were not cased to
generated the vertical convection cell - As a results about 60 pumper and dumpers
installed to maximize heat exchange to DHEs - Dumped water to storm sewer
- Cause water levels to drop approximately one foot
(30 cm) per year - A concern to well owners
15Steam rising from storm sewer
16KLAMATH FALLS BACKGROUND
- City of Klamath Falls pass an ordinance in 1985
which prohibited surface disposal of geothermal
fluids by July of 1990. - A well owner either had to drill an injection
well or use a DHE without pumping, if they wished
to continue to use geothermal fluids for heating. - A number of well owners abandoned their well, and
OIT had to drill two injection wells
17OIT injection well drilling
18EARTHQUAKE OF 1993
- Two earthquakes of 5.9 and 6.0 magnitude occurred
at depths of 7.5 miles (12 km) and 16 miles (25
km) northwest of Klamath Falls in September,
1993. - Structures were damaged and water levels rose in
zone of compression and fell in zones of
extension - Increases up to 3 ft (90 cm) and decreases up to
7 ft (2.1 m) were recorded - The Medical Clinic geothermal well started an
artesian flow of 30 gpm (2 L/s) 1.5 months before
the earthquake and increased to 150 gpm (9.5 L/s)
after. - Since this was a natural phenomena, the City
allowed the Clinic to discharge the flow to the
storm sewer.
19High angle normal faults
Major earthquake epicenters
Klamath Falls
EARTHQUAKE MAP OF 1993
20EARTHQUAKE
- The artesian flow at the Clinic dropped below the
casing top with time - A suction pump was then installed to bring up
heat from the bottom of the well and the water
discharged to the storm sewer. - Finally, the City in 2008, served notice to the
Clinic that they would have to cease pumping and
dumping to the sewer.
21Artesian flow from well suction pump
22MEDICAL CLINIC PROJECT
- Pacific Plumbers of Klamath Falls was hired to
solve the pump and dump problem. - Geo-Heat Center was consulted as to possible
solutions, as only the bottom of the 12-inch
(30-cm) diameter casing was perforated for the
live flow thus, no convection cell produced - Ripping perforations at the casing top
- Installing a smaller, perforated casing inside
- Lengthening the DHE
- Installing a promoter pipe
23 MEDICAL CLINIC DHE
- Well has 12-inch (30-cm)
a 10-inch (25 cm) casing - SWL at 8 feet (2.5 m)
- Well drilled to 364-ft (111 m)
- temperature 204oF (96oC)
- artesian flow 280 gpm (18 L/s)
- DHE of 2.5-inch (6.4-cm)
- Decided to use a 4-inch (10-cm) diameter
promoter pipe to save removing the DHE
24MEDICAL CLINIC HEATING
- They were having trouble heating the facility
even with the pump and dump system running. - Especially true for cold morning and warm
afternoons where the system had to adjust
temperature down to 100oF (38oC) inside building - During the winter of 2007-2008 temperatures as
low as 5oF (-15oC) with average low of 20oF
(-7oC) and average highs of 40oF (4oC) and max.
of 50oF (10oC) - Clinic area of 12,000 ft2 (1,115 m2) with a peak
heating load of 240,000 Btu/hr (252,000 kJ/hr)
(70 kW) domestic hot water heating
25PROMOTER PIPE
- March, 2008 installed 355 ft. (108 m) of 4-inch
(10-cm) diameter promoter pipe. - One-inch (2.5-cm) diameter holes torch cut near
top and bottom over a 3 to 5 ft. (1-1.5 m)
length - Well water temperature measured inside the pipe
before and after cutting the holes. - Pipe suspended off the bottom to avoid fines
sloughing at the bottom and covering the holes.
(10 foot 3 m) of open hole at bottom.
26Installing the promoter pipe and temperature
logging the well
27Installing promoter pipe and cutting holes
28RESULTS
- Temperature profile before showed 155oF (68oC) at
the top of the well and increasing to 193oF
(89oC) at the bottom, thus the DHE was only
exposed to the cooler well water with no
convection cell - With the promoter pipe installed the temperature
was 170 to 180oF (77 to 82oC) over the entire
well depth in March, 2008 - Temperature inside the building was increase to
around 170oF (77oC) - Outside low temperature around 28oF (-2oC) and
highs around 50oF (10oC)
29Before
After
Well temperature profiles
30RESULTS II
- A 2nd set of reading taken in August, 2008.
- Artesian flow had increased, flooding the cellar
around the well - Water level has come up about 7 feet (2 m)
- Temperature profile increased from191 to 193oF
(88 to 89oC) - 190oF (88oC) inside the building
- The system is working too well!!!
31August temperature profile
Temperature profile in August, 2008
32CONCLUSIONS
- Installing a promoter pipe solved the problem of
pumping and dumping to the storm sewer - Increased the temperature of the well water
throughout the water column - Increased the temperature of heat supplied to the
building - Cost to the Medical Clinic 10,000
- Annual savings in heating 7,000
33Thank You