Production Programme - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Production Programme

Description:

First PPMs in USA15 for Calorimeter signal checks Sept 2005 ... Complete integration of PPr with Calorimeter Receivers Jan 2006 ... – PowerPoint PPT presentation

Number of Views:14
Avg rating:3.0/5.0
Slides: 12
Provided by: stenhe
Category:

less

Transcript and Presenter's Notes

Title: Production Programme


1
Production Programme Q2-Q4 2005
2
(No Transcript)
3
Installation Plans for 2005/6
Milestone Target
date First PPMs in USA15 for Calorimeter signal
checks Sept 2005Complete JEP sub-system tests
in Mainz/Stockholm Nov 2005Complete integration
of PPr with Calorimeter Receivers Jan
2006Complete integration of PPr with JEP May
2006Complete commissioning of PPr with
Calorimeters July 2006 Calorimeter trigger
available in situ Aug 2006 Calorimeter trigger
commissioned Oct 2006 Full level-1 trigger
system available Oct 2006Cosmic ray run
Jan 2007
4
(No Transcript)
5
(No Transcript)
6
Spring 2005
  • Install TCPPs (not yet built) and RPPPs (not yet
    designed)
  • Install Tilecal Receivers (already at CERN)
  • Short Analogue Cables (four sets) LVDS digital
  • Install cables as soon as TCPP, RPPP and cable
    management are ready

August 2005
  • Install and test our system which will look at
    Tilecal signals
  • Aim is to ensure that it fully works before
    Tilecal integration starts in September.

September December 2005
  • Connection and checking of Tilecal trigger
    signals.
  • Need a clear understanding of which group
    (Tile/L1Calo) will do what
  • During checks, must confirm connectivity, noise,
    signal quality, gain,

7
  • This will need a rotating group of 3-5 people
    always at CERN (more at the start)
  • including a PP expert and a software expert and a
    cable mapping expert.
  • more people if Tilecal need L1Calo 2 shifts/day
    (need to know soon)
  • average of 7-11 days at CERN for every member of
    L1Calo!!

8
November December 2005
  • Complete preparations for testing LAr trigger
    signals
  • Install PP crates in EM PP Racks
  • Install remaining analogue cables?

January - June 2006
  • Connection and Testing of LAr Barrel Endcap,
    HEC and FCal trigger signals.
  • 360 cables each to check, or up to 1800 calo
    cells/day.
  • In Feb/March 2006, production PPMs come to CERN
  • installed and cabled first to the LAr signals
    ahead of the wave of testing.
  • Then into other parts of LAr and Tilecal.
  • Also in parallel, CP and JEP and Readout systems
    should be installed.

9
June October 2006
  • L1 Trigger available and complete by Oct 2006.
    Therefore
  • Attach L1Calo to CTP_In, verify connectivity.
  • Connect DAQ (ROS) and RoIB S-Links.
  • Test strategy for RoIB S-Links needs to be
    defined.
  • Sort out combined timing, trigger menus, DAQ,
  • Meanwhile, continue with test and calibration
    runs with calorimeters.
  • The next steps would be Cosmic Runs

10
Production Programme Q1/2 2005
11
Installation and Commissioning 2005/6
Write a Comment
User Comments (0)
About PowerShow.com