Title: Presentation for Conventry Conference
1Dave Stockton BT Laboratories
Cost Benefit Analysis of Modern Cable
Installation Techniques
Welcome
2Scope
- Traditional Ducted Methods
- Comparison Technique
- Alternative Ducted Methods
- Sub-duct Issues
- Direct In Ground Installation
- Comparison Results
- Conclusions and Recommendations
3Traditional Ducted Methods
- Winched cable
- Figure-eighting to extend installation length.
Step 1
Step 2
Step 3
4Comparison Technique
- Installation time only compared
- Installation of whole job analysed
- Man hour requirement for all tasks assigned
- Tasks grouped into categories for analysis
- Three representative standard routes used.
5Task Groupings
Road Works Guarding
Cable Installation
Preparation
Entire Job Consists of
Gas Testing
Sub-duct Installation
Rope Installation
6Rural Standard Route
6
1
2
2.6 km
7
3
5
4
18
Node
8
Position
16
Exchange
17
9
Manhole
15
10
500
0
14
11
m
12
13
7Task Group Analysis (Man Hours)
Traditional Unsub-ducted Installation (Rural
Route)
8BT Duct Environment
Mid 70s onward - PVC
90mm bore
6m Length
Pre-Mid 70s - Mainly Earthenware
Similar Bore Shorter lengths
9Alternative Ducted Methods 1
Cable Blowing
- Several systems available
- Longer installation lengths than winching
claimed - Low tensile force - weaker, cheaper cables
- Capabilities highly dependant on cable and duct
size - High cost equipment.
10Alternative Ducted Methods 1
Standard Sub-duct
Loose Tube 96 fibre (18mm) heavy 300g/m
Requires 50 fill for blowing
N/A
25/32mm
Compact 96 fibre (13mm) light 100g/m
Attractive
11Alternative Ducted Methods 2
Blown Fibre
- Precedes cable blowing - on smaller scale
- Patented by BT.
Glass
Blown Fibre Tube
microspheres
(3.5/5mm)
4 fibres
Polyethylene
Sheath
Low modulus
High modulus
buffer layer
outer coating
Aluminium
Water Barrier
1mm
20mm
12Alternative Ducted Methods 3
Cable Floating
- Longer installation lengths than winching
claimed - Strain on cable is evenly distributed
- Weaker, cheaper cables can be installed
- Bulky equipment.
13Alternative Ducted Methods 4
Mid-assist Capstan Winch
- Eliminates the need to figure-eight
- Multiple winches if necessary
- Reduced public disruption.
14Alternative Ducted Methods 5
Cable Fleeting Machine
- Direct alternative to figure-eight
- Fleets at up to 100m / minute
- Reduced public disruption.
15Sub-duct Issues
- Long, continuous, low friction route
- Operational advantages
- Additional stores cost of the sub-duct
- Reduced efficiency of duct space usage
- Self-rodding sub-duct.
16Installation Time Comparison Results 1
Rural Route
Figure-8
Capstan
No Sub-duct
Fleeter
Winched
Installation Method
Blown
Sub-duct
Self-rodded
Self-rodded Blown
0
20
40
60
80
100
Man Hours (Normalized)
17Installation Time Comparison Results 2
Urban Route
Figure-8
Capstan
No Sub-duct
Fleeter
Installation Method
Winched
Blown
Sub-duct
Self-rodded
Self-rodded Blown
0
20
40
60
80
100
Man Hours (Normalized)
18Task group Analysis (Man Hours) 1
Traditional Unsub-ducted Installation (Rural
Route)
19Task Group Analysis (Man Hours) 2
Traditional Sub-ducted Installation (Rural Route)
20Traditional vs Self-rodded Sub-duct
Self-rodded Sub-duct (Rural Route)
Traditional Sub-duct (Rural Route)
21Installed Cost Comparison Summary
Technique
Time Saving
Cheaper Cable
Equipment
Cost
Mid-point Capstan
Very Low
No
Medium
Fleeting Machine
Very Low
No
Medium
Blown Cable
Low
Yes
High
Floated Cable
Low
Yes
High
Self-rodded Sub-duct
High
No
Low
22Conclusions
- Alternative cable installation techniques -
small time savings - Reducing cable cost - high impact
- Sub-duct - large time savings
- Self-rodding sub-duct - up to a further 40
time saving.
23Recommendations
- Evaluate the whole installation process
- Consider differences in stores and equipment
costs - Installed cost comparison if possible.
24Thank You
Dave Stockton BT Laboratories Tel 01473
642043 Email STOCKTDJ_at_boat.bt.com