Title: Back up stave test program status
1Back up stave test program status
- Pre production status
- Assembling phase comments
- Geometrical control
- Stave Qualification
- Tube pressure tests
- Tube pressure cycles
- Stave thermal conduction
- Stave thermal distortion
- Stave thermal stability
- Stave connection
- Stave insulation
- Schedule and budget
Eric VIGEOLAS Pixel week December 2000
2Pre Production status
Up to now 5 back up staves was assembled. One
have been fully tested for the June mechanical
review. One stave was broken during the shipment
(but one half was tested to confirm the thermal
distortions observed on the previous stave) Three
additional stave was manufactured two with an
aluminium tube without parylene, the last one was
manufactured with Parylene coated tube.
This pre production have confirmed that the
assembling tools foreseen for the baseline stave
was suitable for the Back up stave. Only one
additional sequences is needed during the
assembling phase (the grease deposition on the
tube which take a few minutes). One Sequence in
the baseline assembling was changed, the Omega
glue deposition. An manual deposition which
consist to wet the two wings of the Omega was
chosen in order to reduce the amount of Glue.
Eric VIGEOLAS Pixel week December 2000
3Assembling phase Comments
- One important result of the stave assembling
technique is that due to the pressure applied on
the Omega in the gluing phase, the thickness of
Omega glue is bellow the expected 0.1mm. - 0.1 mm was the nominal grease thickness foreseen.
This amount of grease was foreseen to permit to
the tube to have a degree of freedom to avoid
thermal mismatch. Therefor the tube is in contact
with the C-C. - The main effects of this observation is
- More thermal deformations due to CTE mismatch,
but those deformations are reduced by the use of
5 supports points (presented later), and stays in
the requirements - Better thermal efficiency of the cooling pipe
- The tube grease layer is less determining is the
stave reliability.
0.1mm
0.1mm
Pressure applied during the assembling on the
Omega
The tube is in contact with the C-C
Eric VIGEOLAS Pixel week December 2000
4Geometrical Control (June stave)
- Each tilted plan of the stave was measured in
order to estimate the accuracy reached after the
machining and the assembling. - The individual plan geometry accuracy is listed
in the table bellow. - The relative plan location (in R an Z direction )
accuracy is - Z 50?m
- R 100?m
- The R location inaccuracy is mainly due to the
natural bowing if the stave (composite material,
thermal curing)
Eric VIGEOLAS Pixel week December 2000
5Geometrical Control (2 November staves)
- On the new staves received at CPPM the planarity
of the Tilted plan was measure - each plans presented the same S shape
- The average planarity on 24 plan is 41 ?m
- The sigma is 13 ?m
- The best planarity was 19 ?m
- The worst one was 67 ?m
- The main risk of a poor planarity is the
difficulty to deposit a module on the surface
with the required glue thickness. Two
consequences are suspected - Silicon temperature dispersion if the glue
thickness is not controlled - Impossibility to reduce the remaining force to 0
grams during the deposition. - Two stave was equipped with Si by using the CPPM
module assembling tool. The main results are - During the thermal test no important temperature
dispersion was shown - Remaining forces on Si was existing on a minority
of plan (lt 100 grams), The consequences of such
parameter have to be understood (not yet done).
Eric VIGEOLAS Pixel week December 2000
6Stave QualificationTube pressure tests
- The Aluminium Tube was individually pressurised
in order to control it pressure stiffness. The
tube flat edge deformation was measured to
control eventual remaining distortions. - The tube has resist to an internal pressure of 15
bar without remaining deformations. - At 4 Bars absolute the tube have a flat face
bowing of 15 ?m. - At 8 Bars the flat face bowing is about 25 ?m.
F
Eric VIGEOLAS Pixel week December 2000
7Stave QualificationTube pressure Cycles
- 500 Pressure cycles was applied from 1 Bar to 7.5
Bar in order to control if any creep appear. The
creep rate observed after the full tests was 0.1
which is negligible. - By maintaining the pressure in the tube after the
tests no leaks was observed. Further leak tests
will be done with He.
Eric VIGEOLAS Pixel week December 2000
8Stave QualificationStave Thermal Cycles
Thermal Chock -35C
Eric VIGEOLAS Pixel week December 2000
9Stave QualificationStave Thermal Cycles
- The Thermal cycles was performed with full power
on the stave (134W), by just switching on and off
the power supply. The main variation in the
temperature are driven by the inertia of the
cooling system (stabilisation of the intern stave
pressure, flow rate stabilisation) than by any
effect of the stave thermal conduction changes. - Before this test thermal chocks was also applied
(power on on one side of the stave and power off
on the other side and vice and versa (temperature
decrease up to -35C) switch off of the cooling
with an immediate switch on (temperature goes up
to 60C) ). - Moreover during these tests the stave was handle
on two points, with allows the mobility of this
one. This was the worst conditions (high
displacements) to test the reliability of the
thermal conduction. - Finally this test gave precious informations
about the reliability of the NEA123 UV Glue
CGL7018 Grease for the module attachment.
Eric VIGEOLAS Pixel week December 2000
10Stave QualificationStave Thermal conduction
(June stave)
- The Temperature measured at full power was
uniform along the stave. The average Silicon
temperature is -12C. - The pressure drop was lt 0.05 bar, this involve a
very low ?T along the tube lt 2C. - The temperatures measured on the C-C shows a low
?T in the cross section of the silicon lt3C. The
?T between the fluid and the silicon is lt 12C - The Back up stave meet perfectly the thermal
requirements.
Tube sensors
C-C sensors
Eric VIGEOLAS Pixel week December 2000
11Stave QualificationStave Configuration (June
stave)
- The stave configuration was as follow one Pt100
sensor was glued on each silicon(13 sensors),4
Pt100 was glued on the edge of the C-C, Two Pt100
was glued on the tube at the inlet and the
outlet. The maximum power applied was 107 Watts
on the full stave. - This test was done at CERN with C3F8 fluid.
Estimations of Silicon temperature by
calculations shows that the uniformity of the
temperature(?T on Si) is lt 5C
Estimations of C-C temperature by calculations
shows that it is very close to the silicon one
(-11C)
Heaters
Back thermal sensor on C-C
Eric VIGEOLAS Pixel week December 2000
12Stave QualificationStave Configuration
(November stave)
- The stave configuration was as follow one Pt100
sensor was glued on each silicon(13 sensors), Two
Pt100 was glued on the tube at the inlet and the
outlet. The maximum power applied was 134 Watts
on the full stave. - This test was done at CERN with C3F8 fluid.
Thermal Sensor
Heaters
Eric VIGEOLAS Pixel week December 2000
13Stave QualificationStave thermal conduction test
(November stave, before pressure cycles)
- The Si temperature average values is -11.07 C on
the tilted Si, and -7.05C on the middle Si. - The Pressure drop along the stave is 0.1 Bar.
Eric VIGEOLAS Pixel week December 2000
14Stave QualificationStave thermal conduction test
(November stave, After the Temperature cycles)
- The Si temperature average values is -12.96 C on
the tilted Si, and -7.34C on the middle Si. - The Pressure drop along the stave is 0.2 Bar.
Eric VIGEOLAS Pixel week December 2000
15Stave QualificationStave thermal distortion on
three aligned points test (June stave)
- The stave shows an asymmetric behaviour in the
two configurations. On side stays within the
requirements with a maximal R displacement of 30
?m. The other side get out of the specifications.
This asymmetry was shown on all the staves
measured. Phenomena to be studied..
- Two measurements was done in a cold box for a ?T
of 25C. - On of the measurement was done without silicon
glued on the stave, the second one with silicon
glued on the stave in order to control the module
influence on the stave deformation.
Eric VIGEOLAS Pixel week December 2000
16Stave QualificationStave thermal distortion on
five aligned points test (November stave)
- The stave shows an asymmetric behaviour. On side
have a maximal R displacement of 10 ?m. The other
side have a maximal R displacement of 30 ?m .
This confirm what was said before about the
asymmetry shown on every staves.
- This measurement was done in a cold box for a ?T
of 25C. - The stave was equipped with Si heaters
Eric VIGEOLAS Pixel week December 2000
17Stave QualificationStave thermal stability on
five aligned points test (November stave)
- This test was done on half of the stave. This
consist of applying a power on Si to maintain a
?T of 10C in between The Si and The Coolant. - And switch off the power on one and three modules
in between two support to control the stave
mobility. - The Cooling system available at CPPM works at
constant cooling power (and not at Temperature
constant as for C3F8). This is a worst condition
because more parts of the stave will have
temperature changes, which involve more
displacements.
- The Maximum displacement after Three modules off
was 3 ?m (indicative value which is inside the
tolerance of our CMM)
Module3
Module2
Module1
Supports
Eric VIGEOLAS Pixel week December 2000
18Stave QualificationStave thermal stability on
five aligned points test (November stave)
Eric VIGEOLAS Pixel week December 2000
19Stave Connection
- Connection project still under study. This
subject have took two months of delay due to the
use of the induction Power supply by an other
experiment. - Meanwhile the first Cupro-Nickel Tests pieces was
Brazing. The design program is - Complete the study concerning the Cupro-Nickel
- Study the feasibility of an Aluminium pieces
brazing
- Each study is split in several qualifications
tests - Corrosion inspection (visual inspection after a
metallurgical polishing) - Pressure test (leak tests coupled with pressure
cycles) - Traction and shear tests coupled with He leak
tests - Remaining studies concerns
- The layout of the piping (designed as close as
possible than the baseline one) - The scenarios of the the pipes assembling (staves
connection and deconnection). - .
Eric VIGEOLAS Pixel week December 2000
20Stave Insulation
- The stave insulation will be handle by the
Parylene deposition on the tube. - The insulation resistance is gt 20MOhm (limit of
our measurement instrument) in between the
internal face of the tube (non coated) and the
external one. - The first stave prototype equipped with a
Parylene coated tube was assembled a few weeks
ago, and the thermal conduction of this one
should be done by January (to verify the effected
of the additional thermal resistance due to
Paryelene).
Eric VIGEOLAS Pixel week December 2000
21Schedule and Budget
- Concerning the additional tasks required for the
Back up stave assembling, this have no influence
on the schedule of the Baseline stave assembling
(the additional tasks take a few minutes). All
these tasks will be done at Plyform Which
actually is involved in the baseline assembling
and which have built the three previous backup
staves. - The tube delivery is 7 weeks 4 weeks needed for
the Parylene deposition. - The tube price plus the Parylene deposition have
a price of 50000 ChFr. - The additional cost due the the new tasks needed
at Plyform is not known.
Eric VIGEOLAS Pixel week December 2000