Back up stave test program status - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Back up stave test program status

Description:

Thermal Chock: -35 C. Stave Qualification. Stave Thermal Cycles ... Before this test thermal chocks was also applied (power on on one side of the ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 22
Provided by: vige8
Category:
Tags: back | chock | program | status | stave | test

less

Transcript and Presenter's Notes

Title: Back up stave test program status


1
Back up stave test program status
  • Pre production status
  • Assembling phase comments
  • Geometrical control
  • Stave Qualification
  • Tube pressure tests
  • Tube pressure cycles
  • Stave thermal conduction
  • Stave thermal distortion
  • Stave thermal stability
  • Stave connection
  • Stave insulation
  • Schedule and budget

Eric VIGEOLAS Pixel week December 2000
2
Pre Production status
Up to now 5 back up staves was assembled. One
have been fully tested for the June mechanical
review. One stave was broken during the shipment
(but one half was tested to confirm the thermal
distortions observed on the previous stave) Three
additional stave was manufactured two with an
aluminium tube without parylene, the last one was
manufactured with Parylene coated tube.
This pre production have confirmed that the
assembling tools foreseen for the baseline stave
was suitable for the Back up stave. Only one
additional sequences is needed during the
assembling phase (the grease deposition on the
tube which take a few minutes). One Sequence in
the baseline assembling was changed, the Omega
glue deposition. An manual deposition which
consist to wet the two wings of the Omega was
chosen in order to reduce the amount of Glue.
Eric VIGEOLAS Pixel week December 2000
3
Assembling phase Comments
  • One important result of the stave assembling
    technique is that due to the pressure applied on
    the Omega in the gluing phase, the thickness of
    Omega glue is bellow the expected 0.1mm.
  • 0.1 mm was the nominal grease thickness foreseen.
    This amount of grease was foreseen to permit to
    the tube to have a degree of freedom to avoid
    thermal mismatch. Therefor the tube is in contact
    with the C-C.
  • The main effects of this observation is
  • More thermal deformations due to CTE mismatch,
    but those deformations are reduced by the use of
    5 supports points (presented later), and stays in
    the requirements
  • Better thermal efficiency of the cooling pipe
  • The tube grease layer is less determining is the
    stave reliability.

0.1mm
0.1mm
Pressure applied during the assembling on the
Omega
The tube is in contact with the C-C
Eric VIGEOLAS Pixel week December 2000
4
Geometrical Control (June stave)
  • Each tilted plan of the stave was measured in
    order to estimate the accuracy reached after the
    machining and the assembling.
  • The individual plan geometry accuracy is listed
    in the table bellow.
  • The relative plan location (in R an Z direction )
    accuracy is
  • Z 50?m
  • R 100?m
  • The R location inaccuracy is mainly due to the
    natural bowing if the stave (composite material,
    thermal curing)

Eric VIGEOLAS Pixel week December 2000
5
Geometrical Control (2 November staves)
  • On the new staves received at CPPM the planarity
    of the Tilted plan was measure
  • each plans presented the same S shape
  • The average planarity on 24 plan is 41 ?m
  • The sigma is 13 ?m
  • The best planarity was 19 ?m
  • The worst one was 67 ?m
  • The main risk of a poor planarity is the
    difficulty to deposit a module on the surface
    with the required glue thickness. Two
    consequences are suspected
  • Silicon temperature dispersion if the glue
    thickness is not controlled
  • Impossibility to reduce the remaining force to 0
    grams during the deposition.
  • Two stave was equipped with Si by using the CPPM
    module assembling tool. The main results are
  • During the thermal test no important temperature
    dispersion was shown
  • Remaining forces on Si was existing on a minority
    of plan (lt 100 grams), The consequences of such
    parameter have to be understood (not yet done).

Eric VIGEOLAS Pixel week December 2000
6
Stave QualificationTube pressure tests
  • The Aluminium Tube was individually pressurised
    in order to control it pressure stiffness. The
    tube flat edge deformation was measured to
    control eventual remaining distortions.
  • The tube has resist to an internal pressure of 15
    bar without remaining deformations.
  • At 4 Bars absolute the tube have a flat face
    bowing of 15 ?m.
  • At 8 Bars the flat face bowing is about 25 ?m.

F
Eric VIGEOLAS Pixel week December 2000
7
Stave QualificationTube pressure Cycles
  • 500 Pressure cycles was applied from 1 Bar to 7.5
    Bar in order to control if any creep appear. The
    creep rate observed after the full tests was 0.1
    which is negligible.
  • By maintaining the pressure in the tube after the
    tests no leaks was observed. Further leak tests
    will be done with He.

Eric VIGEOLAS Pixel week December 2000
8
Stave QualificationStave Thermal Cycles
Thermal Chock -35C
Eric VIGEOLAS Pixel week December 2000
9
Stave QualificationStave Thermal Cycles
  • The Thermal cycles was performed with full power
    on the stave (134W), by just switching on and off
    the power supply. The main variation in the
    temperature are driven by the inertia of the
    cooling system (stabilisation of the intern stave
    pressure, flow rate stabilisation) than by any
    effect of the stave thermal conduction changes.
  • Before this test thermal chocks was also applied
    (power on on one side of the stave and power off
    on the other side and vice and versa (temperature
    decrease up to -35C) switch off of the cooling
    with an immediate switch on (temperature goes up
    to 60C) ).
  • Moreover during these tests the stave was handle
    on two points, with allows the mobility of this
    one. This was the worst conditions (high
    displacements) to test the reliability of the
    thermal conduction.
  • Finally this test gave precious informations
    about the reliability of the NEA123 UV Glue
    CGL7018 Grease for the module attachment.

Eric VIGEOLAS Pixel week December 2000
10
Stave QualificationStave Thermal conduction
(June stave)
  • The Temperature measured at full power was
    uniform along the stave. The average Silicon
    temperature is -12C.
  • The pressure drop was lt 0.05 bar, this involve a
    very low ?T along the tube lt 2C.
  • The temperatures measured on the C-C shows a low
    ?T in the cross section of the silicon lt3C. The
    ?T between the fluid and the silicon is lt 12C
  • The Back up stave meet perfectly the thermal
    requirements.

Tube sensors
C-C sensors
Eric VIGEOLAS Pixel week December 2000
11
Stave QualificationStave Configuration (June
stave)
  • The stave configuration was as follow one Pt100
    sensor was glued on each silicon(13 sensors),4
    Pt100 was glued on the edge of the C-C, Two Pt100
    was glued on the tube at the inlet and the
    outlet. The maximum power applied was 107 Watts
    on the full stave.
  • This test was done at CERN with C3F8 fluid.

Estimations of Silicon temperature by
calculations shows that the uniformity of the
temperature(?T on Si) is lt 5C
Estimations of C-C temperature by calculations
shows that it is very close to the silicon one
(-11C)
Heaters
Back thermal sensor on C-C
Eric VIGEOLAS Pixel week December 2000
12
Stave QualificationStave Configuration
(November stave)
  • The stave configuration was as follow one Pt100
    sensor was glued on each silicon(13 sensors), Two
    Pt100 was glued on the tube at the inlet and the
    outlet. The maximum power applied was 134 Watts
    on the full stave.
  • This test was done at CERN with C3F8 fluid.

Thermal Sensor
Heaters
Eric VIGEOLAS Pixel week December 2000
13
Stave QualificationStave thermal conduction test
(November stave, before pressure cycles)
  • The Si temperature average values is -11.07 C on
    the tilted Si, and -7.05C on the middle Si.
  • The Pressure drop along the stave is 0.1 Bar.

Eric VIGEOLAS Pixel week December 2000
14
Stave QualificationStave thermal conduction test
(November stave, After the Temperature cycles)
  • The Si temperature average values is -12.96 C on
    the tilted Si, and -7.34C on the middle Si.
  • The Pressure drop along the stave is 0.2 Bar.

Eric VIGEOLAS Pixel week December 2000
15
Stave QualificationStave thermal distortion on
three aligned points test (June stave)
  • The stave shows an asymmetric behaviour in the
    two configurations. On side stays within the
    requirements with a maximal R displacement of 30
    ?m. The other side get out of the specifications.
    This asymmetry was shown on all the staves
    measured. Phenomena to be studied..
  • Two measurements was done in a cold box for a ?T
    of 25C.
  • On of the measurement was done without silicon
    glued on the stave, the second one with silicon
    glued on the stave in order to control the module
    influence on the stave deformation.

Eric VIGEOLAS Pixel week December 2000
16
Stave QualificationStave thermal distortion on
five aligned points test (November stave)
  • The stave shows an asymmetric behaviour. On side
    have a maximal R displacement of 10 ?m. The other
    side have a maximal R displacement of 30 ?m .
    This confirm what was said before about the
    asymmetry shown on every staves.
  • This measurement was done in a cold box for a ?T
    of 25C.
  • The stave was equipped with Si heaters

Eric VIGEOLAS Pixel week December 2000
17
Stave QualificationStave thermal stability on
five aligned points test (November stave)
  • This test was done on half of the stave. This
    consist of applying a power on Si to maintain a
    ?T of 10C in between The Si and The Coolant.
  • And switch off the power on one and three modules
    in between two support to control the stave
    mobility.
  • The Cooling system available at CPPM works at
    constant cooling power (and not at Temperature
    constant as for C3F8). This is a worst condition
    because more parts of the stave will have
    temperature changes, which involve more
    displacements.
  • The Maximum displacement after Three modules off
    was 3 ?m (indicative value which is inside the
    tolerance of our CMM)

Module3
Module2
Module1
Supports
Eric VIGEOLAS Pixel week December 2000
18
Stave QualificationStave thermal stability on
five aligned points test (November stave)
Eric VIGEOLAS Pixel week December 2000
19
Stave Connection
  • Connection project still under study. This
    subject have took two months of delay due to the
    use of the induction Power supply by an other
    experiment.
  • Meanwhile the first Cupro-Nickel Tests pieces was
    Brazing. The design program is
  • Complete the study concerning the Cupro-Nickel
  • Study the feasibility of an Aluminium pieces
    brazing
  • Each study is split in several qualifications
    tests
  • Corrosion inspection (visual inspection after a
    metallurgical polishing)
  • Pressure test (leak tests coupled with pressure
    cycles)
  • Traction and shear tests coupled with He leak
    tests
  • Remaining studies concerns
  • The layout of the piping (designed as close as
    possible than the baseline one)
  • The scenarios of the the pipes assembling (staves
    connection and deconnection).
  • .

Eric VIGEOLAS Pixel week December 2000
20
Stave Insulation
  • The stave insulation will be handle by the
    Parylene deposition on the tube.
  • The insulation resistance is gt 20MOhm (limit of
    our measurement instrument) in between the
    internal face of the tube (non coated) and the
    external one.
  • The first stave prototype equipped with a
    Parylene coated tube was assembled a few weeks
    ago, and the thermal conduction of this one
    should be done by January (to verify the effected
    of the additional thermal resistance due to
    Paryelene).

Eric VIGEOLAS Pixel week December 2000
21
Schedule and Budget
  • Concerning the additional tasks required for the
    Back up stave assembling, this have no influence
    on the schedule of the Baseline stave assembling
    (the additional tasks take a few minutes). All
    these tasks will be done at Plyform Which
    actually is involved in the baseline assembling
    and which have built the three previous backup
    staves.
  • The tube delivery is 7 weeks 4 weeks needed for
    the Parylene deposition.
  • The tube price plus the Parylene deposition have
    a price of 50000 ChFr.
  • The additional cost due the the new tasks needed
    at Plyform is not known.

Eric VIGEOLAS Pixel week December 2000
Write a Comment
User Comments (0)
About PowerShow.com