The Challenger Shuttle Challenge - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

The Challenger Shuttle Challenge

Description:

... consist of a tang and clevis joint held together by 177 clevis pins. ... the O-Rings, shims are inserted between the tang and outside leg of the clevis. ... – PowerPoint PPT presentation

Number of Views:119
Avg rating:3.0/5.0
Slides: 28
Provided by: videoserv6
Category:

less

Transcript and Presenter's Notes

Title: The Challenger Shuttle Challenge


1
The Challenger Shuttle Challenge
  • An Ethical Scenario
  • Engineering Concepts
  • Dr. Ron Eaglin

2
The facts
  • On January 28, 1986 Seven astronauts were killed
    when the space shuttle Challenger exploded 72
    seconds after liftoff from the Cape Canaveral Air
    Force Station.
  • Official cause of the accident was failure of
    O-Rings on the Solid Rocket Boosters and
    subsequent leakage of hot gasses which ignited
    the propellant causing an explosion.

3
Background
  • Competition from the European Space Agency
    required NASA to demonstrate that the shuttle
    could fly a dependable, yet aggressive schedule
    to prove its viability for commercialization.
  • The previous Shuttle mission was delayed a record
    number of times due to mechanical problems and
    poor weather.

4
Background
  • Launch pad refurbishment was required before the
    next mission which was to carry a probe to study
    Halleys comet, the schedule was tight on this
    mission as a similar Russian probe was schedule
    to arrive in the comet vicinity shortly after the
    American probe.

5
Background
  • NASA officials desired to have the Shuttle in
    space with Astronaut/Teacher Christa McAuliffe
    for the State of the Union Address Ronald
    Reagans main topic was to be Education and this
    was to be important to the speech.

6
Solid Rocket Boosters
  • The Solid Rocket Boosters are the primary thrust
    for the Shuttle allowing it to achieve orbit.
  • Each booster is 149 feet long and 12 feet in
    diameter.
  • Each booster weighs 2 million pounds
  • Solid rocket fuel (unlike liquid) cannot be
    turned off once ignited.

7
Solid Rocket Boosters
  • Morton Thiokol received the contract to build the
    SRB in 1974.
  • The SRB design is essentially a scaled version of
    the Titan Missile.
  • The booster is comprised of 7 hollow metal
    cylinders
  • The Solid rocket fuel is cast in the cylinders at
    the M-T plant in Utah and transported to KSC

8
Solid Rocket Boosters
  • The SRB field joints consist of a tang and clevis
    joint held together by 177 clevis pins.
  • Each joint is sealed by 2 O-rings and a heat
    resistant putty is applied to the inner section
    of the joint assembly.
  • To minimize gap and squeeze the O-Rings, shims
    are inserted between the tang and outside leg of
    the clevis.

9
The Event
  • The first launch delay occurred because an
    expected weather front. The launch was scrubbed
    before the front moved into the area.
  • The reason to scrub the launch was to prevent the
    Vice-President from needlessly traveling to KSC
    as he was expected for launch.

10
The Event
  • The weather front stalled and the weather
    conditions were ideal for the scrubbed first
    launch.
  • The second launch was delayed due to a defective
    micro-switch in the hatch locking mechanisms. By
    the time the problem was solved wind conditions
    were too high for launch.

11
The Event
  • The stalled weather system had started moving
    again by the 3rd scheduled launch and was
    expected to bring record low temperatures to the
    area.
  • NASA contacted all shuttle contractors to
    determine if there were concerns with a cold
    weather launch.

12
The night before
  • Alan McDonald (of M-T) was convinced there might
    be cold weather problems with the SRB design and
    contacted 2 project engineers, Robert Ebeling and
    Roger Boisjoly.

13
More background
  • M-T knew of a design problem with the SRB in 1977
    and had initiated a redesign effort in 1985.
  • NASA level I management were briefed on the issue
    in August 1985.
  • Half of all shuttle flights had experienced
    O-Ring erosion in the booster joints.

14
More background
  • Ebeling and Boisjoly had both complained that
    management was not supporting the redesign task
    force.
  • In July 1985 new steel billets had been ordered
    for a redesigned case field joint, these would
    not be ready for months.

15
January 27, 1986
  • Morning temperatures were predicted to be in the
    low 20s.
  • A teleconference was scheduled between
    engineering and management at KSC, Marshall Space
    Flight Center, and M-T Engineers and management
    in Utah.

16
January 27, 1986
  • M-T Roger Boisjoly and Arne Thompson were given a
    very short time to prepare a presentation for the
    conference.
  • They gave a 1 hour long presentation and a
    convincing argument that cold-weather would
    exaggerate problems of joint rotation and delayed
    O-Ring seating.

17
January 27, 1986
  • Previous lowest temperature launch was 53 F on
    January 24, 1985.
  • O-Ring temperature at launch was expected to be
    29 F (ambient temp as expected to be 26 F)
  • M-T VP Bob Lund presented conclusion the 53F was
    lowest temp that data existed for operational
    boosters. The boosters had experienced erosion at
    this temperature.

18
January 27, 1986
  • Because engineers had no low temperature data
    below 53F, they could not prove it was unsafe to
    launch at lower temperatures.
  • Booster specification called for booster
    operation at 31F (later it was found this was for
    booster storage, not launch)

19
January 27, 1986
  • Larry Mulloy (Marshalls SRB Project Manager)
    commented the data was inconclusive and
    challenged the engineers logic.
  • Mulloy called for a decision by Joe Kilminster
    (M-T middle level management) who supported the
    M-T engineers.
  • Several other Marshall managers expressed doubts
    about the recommendation.

20
January 27, 1986
  • The teleconference ended so M-T could review its
    data. Boisjoly and Thompson tried to convince M-T
    senior management to support decision to not
    launch.
  • Senior exec Jerald Mason at M-T told Bob Lund
    Take off your engineering hat and put on your
    management hat

21
January 27, 1986
  • Joe Kilminster wrote a new recommendation
    recommending launch and went back into the
    teleconference.
  • The engineers refused to work on or sign the
    recommendation.
  • Alan McDonald (M-T) was in KSC with NASA, he was
    surprised to see the recommendation to launch.

22
January 27, 1986
  • Alan McDonald refused to sign the launch
    recommendation and appealed to NASA management
    not to launch.
  • NASA management approved the recommendation to
    launch.

23
January 28, 1986
  • Overnight temperature dipped as low as 8F.
  • Safety showers and fire hoses were deployed to
    prevent pipes from freezing, but caused ice to
    form on the platform.
  • The ice inspection team was alarmed, but the
    launch director continued with countdown.

24
January 28, 1986
  • Low temperature launch limits were waived by
    several key personnel during countdown.
  • 8/100 second after ignition engineering cameras
    focused on the right hand booster record 9 smoke
    puffs originating in the booster aft field joint.
  • Oxides from burnt propellant temporarily seal the
    field joint preventing flames from escaping.

25
January 28, 1986
  • 59 seconds into flight telemetry records most
    violent wind shear recorded in a shuttle flight.
  • The glassy oxide film that is sealing the joint
    is shattered by the wind shear, flames burn
    through the external field tank within 2 seconds.

26
January 28, 1986
  • 72 seconds into flight the external fuel tank
    ignites through hole causing an explosion that
    tears the SRB apart and causes extensive damage
    to the shuttle.
  • 100 seconds into flight all telemetry data
    ceases.

27
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com