Title: Status of the LHC accelerator
1Status of the LHC accelerator
- Rüdiger Schmidt - CERN
- KET November 2005
- Bad Honnef
The LHC injector complex The LHC machine Hardware
commissioning Operation und Machine
Protection Conclusions
On behalf of the CERN staff and the outside
collaborators
2Interconnection of beam tubes
Cryogenic distribution line
On behalf of the CERN staff and the outside
collaborators
3The LHC injector complex
4The CERN accelerator complex injectors and
transfer
Beam 2
5
LHC
4
6
Beam 1
Extraction
7
3
2
SPS
8
TI8
TI2
1
Booster
protons
LINACS
CPS
Ions
High intensity beam from the SPS into LHC at 450
GeV via TI2 and TI8 Transfer lines 2 ? 3
km LHC accelerates from 450 GeV to 7 TeV
LEIR
5(No Transcript)
6LHC accelerator
LHC Main Systemsfor hardware commissioniongSupe
rconducting magnetsCryogenicsVacuum
systemPowering
Progress on LHC dashboards http//lhc-new-homepage
.web.cern.ch/lhc-new-homepage/DashBoard/index.asp
7providing 1232 LHC dipole magnets
- fabrication of cables
- fabrication of cold mass
- cryostating
- testing at 1.9 K
- installation in tunnel
- commissioning
- operation with beam
8Superconducting cable Type 1
9Dipole cold masses
10Cryodipole overview
11First cryodipole lowered on 7 March 2005
Only one access point for 15 m long dipoles, 35
tons each
12Transport in the tunnel with an optical guided
vehicleabout 1600 magnets to be transported for
15 kmat 3 km/hour
13Cryogenic distribution line
14Cryogenic distribution line in the LHC tunnel
15Status summary
- Magnet production well advanced
- Installation in progress, more than 100
cryomagnets have been installed in Sectors 8-1,
4-5 7-8, this must accelerate (on the critical
path) - Cryogenics
- large part finished and operational (e.g.
cryoplants) - QRL installed in Sectors 7-8, 8-1 4-5 by end of
2005, in progress in 3-4 5-6 - QRL commissioning started
- Other systems (RF, Beam injection and extraction,
Beam instrumentation, Collimation, Interlocks,
Controls) - essentially on schedule
16Hardware commissioning
17Hardware commissioning Commissioning of the
technical systems
- Safe commissioning of all technical systems that
do not require beam - 1232 main dipoles 3700 multipole corrector
magnets - 392 main quadrupoles 2500 corrector magnets
- 26 km cryogenic distribution line
- 26 km cryogenic magnets
- 4 vacuum systems, each 27 km long
- gt 1700 magnet powering circuits with power
converters (60A 13000 kA) - Quench protection and powering interlock systems
- gt 10000 electronics crates for operation and
protection
18Energy stored in magnets at 7 TeV 10 GJoule
Airbus 380 The energy stored in the
LHC magnet system corresponds to the energy of an
A380 at 700 km/hour
19- Powering system commissioning startedPower
converters installed and commissioning on short
circuits started in tunnel - 81 power converters in UA83
- 156 kA and 1.2 MW dissipated PCs and Cables
Cryogenic system Cryoplant commissioning well
advancedTunnel cryogenics commissioning started
20Power converter commissioning, F.Bordry, 11-2005
21Location UA83 (Beginning) Equipt
type LHC2-4-6-8kA SP1 TC 46 conf.
90 Date 2005-10-13 11h00
F.Bordry, 11-2005
22Cryogenic system
surface
tunnel
23Cool down of the cryogenic distribution line
24Operation and machine protection
25Beam commissioning Commissioning of the beam
systems
- Safe commissioning of all systems that require
beam - Injection system
- Extraction (beam dumping) system
- Beam monitoring
- 4000 beam loss monitors and 1000 beam position
monitors - Many other monitors (beam current, beam size, .)
- RF system
- Beam interlock system
- Collimation system
26Energy stored in one beam at 7 TeV 362 MJoule
- Kugelstossen
- The energy of one shot (5 kg) at 800 km/hour
corresponds to - the energy stored in one bunch at 7 TeV.
- There are 2808 bunches.
- Factor 200 compared to HERA, TEVATRON and SPS.
27SPS experiment Beam damage at 450 GeV
- Controlled SPS experiment
- 8?1012 protons clear damage
- beam size sx/y 1.1mm/0.6mm
- above damage limit
- 2?1012 protons
- below damage limit
25 cm
6 cm
0.1 of the full LHC beams
V.Kain et al
28Protection and Beam Energy
- A small (lt10-3) fraction of beam can cause damage
- Very efficient protection systems throughout the
cycle are required - A tiny (lt10-7) fraction of beam can quench a
magnet - Very efficient beam cleaning is required
- Sophisticated beam cleaning with about 40
collimators per beam, each with two jaws, in
total about 80 collimators and beam absorbers
(first phase of LHC)
29The LHC Phase 1 Collimator
Vacuum tank with two jaws installed
Designed for maximum robustness Advanced Carbon
Composite material for the jaws with water
cooling!
R.Assmann et al
30(No Transcript)
31Proton luminosity running Parameters
HSM -gt 4 l (MHiggs 140-155 GeV and 190-450
GeV) can be discovered with 4 fb-1 Some
supersymmetry can be discovered at more modest
luminosities 1 fb-1 Potential for
b-physics right from startup
(300 hours _at_ ltLgt of 1033 cm-2 s-1 1 fb-1)
- Machine parameters
- Bunch intensity
- Distance between two bunches (number of bunches)
- Beta function (beam size) at interaction point
- Experiments
- Will make use of any beam for detector
commissioning - Minimize event pileup early on (go to 25 ns as
soon as possible) - (My guess..) Operate safely has priority
- From Chamonix XIV -
32Proposal for early proton running
- Pilot physics run with few bunches
- No parasitic bunch crossings
- Machine de-bugging no crossing angle
- 43 bunches, unsqueezed, reduced intensity
- Push performance (156 bunches, partial
squeeze in 1 and 5, push
intensity) - 75 ns operation
- Establish multi-bunch operation
- Relaxed machine parameters (squeeze and crossing
angle) - Push squeeze and crossing angle
- 25 ns operation (Phase I collimators partial
beam dump) - Needs scrubbing for higher intensities ( ib gt 3 -
4 1010 ) - 25 ns operation
- Push towards nominal performance
R.Bailey
33Conclusions
34Recalling LHC status and challenges
- Concentrating on short term goals, get one sector
installed and commissioned. - The more global situation will be reviewed with a
view to giving in April 2006 a more precise date
for the completion of the machine - Hardware commissioning with help of many external
institutes
Fabrication of equipment
Installation
LHC hardware commissioning
LHC Beam commissioning
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
2005
2004
2006
2007
35Conclusions
- The LHC is a global project with the world-wide
high-energy physics community devoted to its
progress and results - As a project, it is much more complex and
diversified than the SPS or LEP or any other
large accelerator project constructed to date
Machine Advisory Committee, chaired by Prof. M.
Tigner, March 2002
- We recognize that the planned schedule is very
aggressive, given the complexity and potential
for damage involved in the initial phases of
operation. - It will be important to understand the
performance of the machine protection system, the
collimation system and the orbit feedback system
as well as cycle repeatability and adequate
beta-beat control before proceeding to run with
significant stored beam energy. Pressure to take
shortcuts must be resisted.
Machine Advisory Committee, chaired by Prof. M.
Tigner, June 2005
36Acknowledgement
- The LHC accelerator is being realised by CERN in
collaboration with institutes from many countries
over a period of more than 20 years - Main contribution come from the USA, Russia,
India, Canada, special contributions from France
and Switzerland - Industry plays a major role in the construction
of the LHC - Thanks for the material from
- R.Assmann, R.Bailey, F.Bordry, L.Evans,
B.Goddard, M.Gyr
37Is everything always going smoothly? Not really.
- I am convinced that for a project such as the
LHC, considering the - complexity
- uniqueness
- novelty
- difficulties will always be encountered.
- However, it is important that such difficulties
are identified, addressed, and mastered. - This is required
to make a project success
38Conclusions
39LHC hardware commissioning
- Qualification for operation of the individual
systems of a sector (vacuum, cryogenics, quench
protection, interlocks, powering, etc.) - Each (sub-)sector will be commissioned as a whole
up to the powering to nominal current of all the
electrical circuits. - Validation and specific studies will be
carried-out on the first commissioned sector.
40Some references
- Accelerator physics
- Proceedings of CERN ACCELERATOR SCHOOL (CAS),
http//schools.web.cern.ch/Schools/CAS/CAS_Proceed
ings.html - In particular 5th General CERN Accelerator
School, CERN 94-01, 26 January 1994, 2
Volumes, edited by S.Turner - Superconducting magnets / cryogenics
- Superconducting Accelerator Magnets, K.H.Mess,
P.Schmüser, S.Wolff, World Scientific 1996 - Superconducting Magnets, M.Wilson, Oxford Press
- Superconducting Magnets for Accelerators and
Detectors, L.Rossi, CERN-AT-2003-002-MAS (2003) - LHC
- Technological challenges for the LHC, CERN
Academic Training, 5 Lectures, March 2003 (CERN
WEB site) - Beam Physics at LHC, L.Evans, CERN-LHC Project
Report 635, 2003 - Status of LHC, R.Schmidt, CERN-LHC Project Report
569, 2003 - ...collimation system.., R.Assmann et al.,
CERN-LHC Project Report 640, 2003 - LHC Design Report 2003
41Reserve Slides
42Regular arc Magnets
1232 main dipoles 3700 multipole corrector
magnets 392 main quadrupoles 2500 corrector
magnets 26 km cryogenic distribution line 26 km
cryogenic magnets 4 vacuum systems, each 27 km
long 1800 magnet powering circuits with power
converters (60A 13000 kA) gt 10000 electronics
crates for operation and protection
43Regular arc Cryogenics
44Regular arc Vacuum
45Regular arc Electronics
46Commissioning of the technical systems Hardware
commissioning
- Definition of the procedures, their sequencing,
the refinement of the time required for the
commissioning - Identification of the conditions required to
start, those required during the commissioning
and the conditions which determine the end of the
commissioning - Commissioning and qualification of the individual
systems (vacuum, cryogenics, interlocks, magnet
protection, powering, etc). - Following-up work of the assemblers and the teams
checking their systems, to ensure that conditions
for hardware commissioning are present
(infrastructure, assembly, safety) - Coordinating and carrying-out hardware
commissioning in the time frame allocated by the
General Construction and Installation Schedule - Carrying-out validation and specific studies
47LHC magnetic cycle
energy ramp
coast
coast
7 TeV
start of the ramp
injection phase
preparation and access
450 GeV
L.Bottura
48LHC magnetic cycle - beam injection
beam dump
energy ramp
coast
coast
7 TeV
start of the ramp
injection phase 12 batches from the SPS (every 20
sec) one batch 216 / 288 bunches
450 GeV
L.Bottura
49Beam lifetime with nominal intensity at 7 TeV
Failures will be a part of the regular operation
and MUST be anticipated
50End of data taking in normal operation Beam Dump
- Luminosity lifetime estimated to be approximately
10 h (after 10 hours only 1/3 of initial
luminosity) - Beam current somewhat reduced - but not much
- Energy per beam still about 200-300 MJ
- Beams are extracted into beam dump blocks
- The only component that can stand a loss of the
full beam is the beam dump block - all other
components would be damaged - At 7 TeV, fast beam loss with an intensity of
about 5 of one single nominal bunch could
damage superconducting coils - In case of failure beam must go into beam dump
block
51Schematic layout of beam dump system in IR6
Septum magnet deflecting the extracted beam
Beam 1
H-V kicker for painting the beam
Q5L
Beam Dump Block
Q4L
about 700 m
Fast kicker magnet
Q4R
about 500 m
Q5R
Beam 2
52Dumping the LHC beam
beam absorber (graphite)
about 8 m
about 35 cm
concrete shielding
53Full LHC beam deflected into copper target
Copper target
2808 bunches
2 m
Energy density GeV/cm3 on target axis
Target length cm
N.Tahir (GSI) et al.
54Operational margin of a superconducting magnet
Applied Magnetic Field T
Applied magnetic field T
This is about 1000 times more critical than for
TEVATRON, HERA, RHIC
Bc critical field
Tc critical temperature
9 K
Temperature K
55 56.0 mm
- 3? 1.3 mm
Beam /- 3 sigma
Beam in vacuum chamber with beam screen at 7 TeV
56Dipole magnets for the LHC
1232 Dipolmagnets Length about 15 m Magnetic
Field 8.3 T Two beam tubes with an opening of 56
mm
57(No Transcript)
58(No Transcript)
59SECTOR 8-1
ELECTRICAL QUALITY ASSURANCE
COOLDOWN
POWERING TESTS
60LHC Layout eight arcs (sectors) eight long
straight section (about 700 m long)
Beam dump blocks
IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (warm)
IR7 Betatron Cleaning (warm)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
61Global requirements on the machine
- Highest energy proton collisions for ATLAS / CMS
- Nominal luminosity 1034 cm-2 s-1 in points 1 and
5 - Highest energy proton collisions for LHCb
- Nominal luminosity 5 1032 cm-2 s-1 in point 8
- Proton collisions _at_ various energies for ALICE
- Nominal luminosity 1030 cm-2 s-1 in point 2
- Ion collisions _at_ various energies for ALICE
- Nominal luminosity 1027 cm-2 s-1 in point 2
- ATLAS and CMS will also take data
- Proton collisions _at_ various energies for TOTEM
Proton luminosity running
Dedicated operation
Dedicated operation
62TI 8 Beam spot at end of line
63Transfer on jacks
64Preparation of interconnect
65Repair of QRL modules at CERN
66Repair of special QRL elements at CERN
http//lhc.web.cern.ch/lhc/LHCnews/repairs20and2
0cooldown_E.pdf
67Livingston type plot Energy stored magnets and
beam
6856.0 mm
Collimators at 7 TeV, squeezedoptics
1 mm
R.Assmanns EURO
/- 8 sigma 4.0 mm
Example Setting of collimators at 7 TeV - with
luminosity optics Beam must always touch
collimators first !