Status of the LHC accelerator - PowerPoint PPT Presentation

1 / 68
About This Presentation
Title:

Status of the LHC accelerator

Description:

Collimation system 'Beam commissioning' Commissioning of the beam systems. 18 ... Operation acceptable, collimation must absorb large fraction of beam energy ... – PowerPoint PPT presentation

Number of Views:82
Avg rating:3.0/5.0
Slides: 69
Provided by: Rudi83
Category:

less

Transcript and Presenter's Notes

Title: Status of the LHC accelerator


1
Status of the LHC accelerator
  • Rüdiger Schmidt - CERN
  • KET November 2005
  • Bad Honnef

The LHC injector complex The LHC machine Hardware
commissioning Operation und Machine
Protection Conclusions
On behalf of the CERN staff and the outside
collaborators
2
Interconnection of beam tubes
Cryogenic distribution line
On behalf of the CERN staff and the outside
collaborators
3
The LHC injector complex
4
The CERN accelerator complex injectors and
transfer
Beam 2
5
LHC
4
6
Beam 1
Extraction
7
3
2
SPS
8
TI8
TI2
1
Booster
protons
LINACS
CPS
Ions
High intensity beam from the SPS into LHC at 450
GeV via TI2 and TI8 Transfer lines 2 ? 3
km LHC accelerates from 450 GeV to 7 TeV
LEIR
5
(No Transcript)
6
LHC accelerator
LHC Main Systemsfor hardware commissioniongSupe
rconducting magnetsCryogenicsVacuum
systemPowering
Progress on LHC dashboards http//lhc-new-homepage
.web.cern.ch/lhc-new-homepage/DashBoard/index.asp
7
providing 1232 LHC dipole magnets
  • fabrication of cables
  • fabrication of cold mass
  • cryostating
  • testing at 1.9 K
  • installation in tunnel
  • commissioning
  • operation with beam


8
Superconducting cable Type 1
9
Dipole cold masses
10
Cryodipole overview
11
First cryodipole lowered on 7 March 2005
Only one access point for 15 m long dipoles, 35
tons each
12
Transport in the tunnel with an optical guided
vehicleabout 1600 magnets to be transported for
15 kmat 3 km/hour
13
Cryogenic distribution line
14
Cryogenic distribution line in the LHC tunnel
15
Status summary
  • Magnet production well advanced
  • Installation in progress, more than 100
    cryomagnets have been installed in Sectors 8-1,
    4-5 7-8, this must accelerate (on the critical
    path)
  • Cryogenics
  • large part finished and operational (e.g.
    cryoplants)
  • QRL installed in Sectors 7-8, 8-1 4-5 by end of
    2005, in progress in 3-4 5-6
  • QRL commissioning started
  • Other systems (RF, Beam injection and extraction,
    Beam instrumentation, Collimation, Interlocks,
    Controls)
  • essentially on schedule

16
Hardware commissioning
17
Hardware commissioning Commissioning of the
technical systems
  • Safe commissioning of all technical systems that
    do not require beam
  • 1232 main dipoles 3700 multipole corrector
    magnets
  • 392 main quadrupoles 2500 corrector magnets
  • 26 km cryogenic distribution line
  • 26 km cryogenic magnets
  • 4 vacuum systems, each 27 km long
  • gt 1700 magnet powering circuits with power
    converters (60A 13000 kA)
  • Quench protection and powering interlock systems
  • gt 10000 electronics crates for operation and
    protection

18
Energy stored in magnets at 7 TeV 10 GJoule
Airbus 380 The energy stored in the
LHC magnet system corresponds to the energy of an
A380 at 700 km/hour
19
  • Powering system commissioning startedPower
    converters installed and commissioning on short
    circuits started in tunnel
  • 81 power converters in UA83
  • 156 kA and 1.2 MW dissipated PCs and Cables


Cryogenic system Cryoplant commissioning well
advancedTunnel cryogenics commissioning started
20
Power converter commissioning, F.Bordry, 11-2005
21
Location UA83 (Beginning) Equipt
type LHC2-4-6-8kA SP1 TC 46 conf.
90 Date 2005-10-13 11h00
F.Bordry, 11-2005
22
Cryogenic system
surface
tunnel
23
Cool down of the cryogenic distribution line
24
Operation and machine protection
25
Beam commissioning Commissioning of the beam
systems
  • Safe commissioning of all systems that require
    beam
  • Injection system
  • Extraction (beam dumping) system
  • Beam monitoring
  • 4000 beam loss monitors and 1000 beam position
    monitors
  • Many other monitors (beam current, beam size, .)
  • RF system
  • Beam interlock system
  • Collimation system

26
Energy stored in one beam at 7 TeV 362 MJoule
  • Kugelstossen
  • The energy of one shot (5 kg) at 800 km/hour
    corresponds to
  • the energy stored in one bunch at 7 TeV.
  • There are 2808 bunches.
  • Factor 200 compared to HERA, TEVATRON and SPS.


27
SPS experiment Beam damage at 450 GeV
  • Controlled SPS experiment
  • 8?1012 protons clear damage
  • beam size sx/y 1.1mm/0.6mm
  • above damage limit
  • 2?1012 protons
  • below damage limit

25 cm
6 cm
0.1 of the full LHC beams
V.Kain et al
28
Protection and Beam Energy
  • A small (lt10-3) fraction of beam can cause damage
  • Very efficient protection systems throughout the
    cycle are required
  • A tiny (lt10-7) fraction of beam can quench a
    magnet
  • Very efficient beam cleaning is required
  • Sophisticated beam cleaning with about 40
    collimators per beam, each with two jaws, in
    total about 80 collimators and beam absorbers
    (first phase of LHC)


29
The LHC Phase 1 Collimator
Vacuum tank with two jaws installed
Designed for maximum robustness Advanced Carbon
Composite material for the jaws with water
cooling!
R.Assmann et al
30
(No Transcript)
31
Proton luminosity running Parameters
HSM -gt 4 l (MHiggs 140-155 GeV and 190-450
GeV) can be discovered with 4 fb-1 Some
supersymmetry can be discovered at more modest
luminosities 1 fb-1 Potential for
b-physics right from startup
(300 hours _at_ ltLgt of 1033 cm-2 s-1 1 fb-1)
  • Machine parameters
  • Bunch intensity
  • Distance between two bunches (number of bunches)
  • Beta function (beam size) at interaction point
  • Experiments
  • Will make use of any beam for detector
    commissioning
  • Minimize event pileup early on (go to 25 ns as
    soon as possible)
  • (My guess..) Operate safely has priority

- From Chamonix XIV -
32
Proposal for early proton running
  • Pilot physics run with few bunches
  • No parasitic bunch crossings
  • Machine de-bugging no crossing angle
  • 43 bunches, unsqueezed, reduced intensity
  • Push performance (156 bunches, partial
    squeeze in 1 and 5, push
    intensity)
  • 75 ns operation
  • Establish multi-bunch operation
  • Relaxed machine parameters (squeeze and crossing
    angle)
  • Push squeeze and crossing angle
  • 25 ns operation (Phase I collimators partial
    beam dump)
  • Needs scrubbing for higher intensities ( ib gt 3 -
    4 1010 )
  • 25 ns operation
  • Push towards nominal performance

R.Bailey
33
Conclusions
34
Recalling LHC status and challenges
  • Concentrating on short term goals, get one sector
    installed and commissioned.
  • The more global situation will be reviewed with a
    view to giving in April 2006 a more precise date
    for the completion of the machine
  • Hardware commissioning with help of many external
    institutes


Fabrication of equipment
Installation
LHC hardware commissioning
LHC Beam commissioning
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
2005
2004
2006
2007
35
Conclusions
  • The LHC is a global project with the world-wide
    high-energy physics community devoted to its
    progress and results
  • As a project, it is much more complex and
    diversified than the SPS or LEP or any other
    large accelerator project constructed to date

Machine Advisory Committee, chaired by Prof. M.
Tigner, March 2002
  • We recognize that the planned schedule is very
    aggressive, given the complexity and potential
    for damage involved in the initial phases of
    operation.
  • It will be important to understand the
    performance of the machine protection system, the
    collimation system and the orbit feedback system
    as well as cycle repeatability and adequate
    beta-beat control before proceeding to run with
    significant stored beam energy. Pressure to take
    shortcuts must be resisted.

Machine Advisory Committee, chaired by Prof. M.
Tigner, June 2005
36
Acknowledgement
  • The LHC accelerator is being realised by CERN in
    collaboration with institutes from many countries
    over a period of more than 20 years
  • Main contribution come from the USA, Russia,
    India, Canada, special contributions from France
    and Switzerland
  • Industry plays a major role in the construction
    of the LHC
  • Thanks for the material from
  • R.Assmann, R.Bailey, F.Bordry, L.Evans,
    B.Goddard, M.Gyr

37
Is everything always going smoothly? Not really.
  • I am convinced that for a project such as the
    LHC, considering the
  • complexity
  • uniqueness
  • novelty
  • difficulties will always be encountered.
  • However, it is important that such difficulties
    are identified, addressed, and mastered.
  • This is required
    to make a project success

38
Conclusions
39
LHC hardware commissioning
  • Qualification for operation of the individual
    systems of a sector (vacuum, cryogenics, quench
    protection, interlocks, powering, etc.)
  • Each (sub-)sector will be commissioned as a whole
    up to the powering to nominal current of all the
    electrical circuits.
  • Validation and specific studies will be
    carried-out on the first commissioned sector.

40
Some references
  • Accelerator physics
  • Proceedings of CERN ACCELERATOR SCHOOL (CAS),
    http//schools.web.cern.ch/Schools/CAS/CAS_Proceed
    ings.html
  • In particular 5th General CERN Accelerator
    School, CERN 94-01, 26 January 1994, 2
    Volumes, edited by S.Turner
  • Superconducting magnets / cryogenics
  • Superconducting Accelerator Magnets, K.H.Mess,
    P.Schmüser, S.Wolff, World Scientific 1996
  • Superconducting Magnets, M.Wilson, Oxford Press
  • Superconducting Magnets for Accelerators and
    Detectors, L.Rossi, CERN-AT-2003-002-MAS (2003)
  • LHC
  • Technological challenges for the LHC, CERN
    Academic Training, 5 Lectures, March 2003 (CERN
    WEB site)
  • Beam Physics at LHC, L.Evans, CERN-LHC Project
    Report 635, 2003
  • Status of LHC, R.Schmidt, CERN-LHC Project Report
    569, 2003
  • ...collimation system.., R.Assmann et al.,
    CERN-LHC Project Report 640, 2003
  • LHC Design Report 2003

41
Reserve Slides
42
Regular arc Magnets
1232 main dipoles 3700 multipole corrector
magnets 392 main quadrupoles 2500 corrector
magnets 26 km cryogenic distribution line 26 km
cryogenic magnets 4 vacuum systems, each 27 km
long 1800 magnet powering circuits with power
converters (60A 13000 kA) gt 10000 electronics
crates for operation and protection
43
Regular arc Cryogenics
44
Regular arc Vacuum
45
Regular arc Electronics
46
Commissioning of the technical systems Hardware
commissioning
  • Definition of the procedures, their sequencing,
    the refinement of the time required for the
    commissioning
  • Identification of the conditions required to
    start, those required during the commissioning
    and the conditions which determine the end of the
    commissioning
  • Commissioning and qualification of the individual
    systems (vacuum, cryogenics, interlocks, magnet
    protection, powering, etc).
  • Following-up work of the assemblers and the teams
    checking their systems, to ensure that conditions
    for hardware commissioning are present
    (infrastructure, assembly, safety)
  • Coordinating and carrying-out hardware
    commissioning in the time frame allocated by the
    General Construction and Installation Schedule
  • Carrying-out validation and specific studies

47
LHC magnetic cycle
energy ramp
coast
coast
7 TeV
start of the ramp
injection phase
preparation and access
450 GeV
L.Bottura
48
LHC magnetic cycle - beam injection
beam dump
energy ramp
coast
coast
7 TeV
start of the ramp
injection phase 12 batches from the SPS (every 20
sec) one batch 216 / 288 bunches
450 GeV
L.Bottura
49
Beam lifetime with nominal intensity at 7 TeV
Failures will be a part of the regular operation
and MUST be anticipated
50
End of data taking in normal operation Beam Dump
  • Luminosity lifetime estimated to be approximately
    10 h (after 10 hours only 1/3 of initial
    luminosity)
  • Beam current somewhat reduced - but not much
  • Energy per beam still about 200-300 MJ
  • Beams are extracted into beam dump blocks
  • The only component that can stand a loss of the
    full beam is the beam dump block - all other
    components would be damaged
  • At 7 TeV, fast beam loss with an intensity of
    about 5 of one single nominal bunch could
    damage superconducting coils
  • In case of failure beam must go into beam dump
    block

51
Schematic layout of beam dump system in IR6
Septum magnet deflecting the extracted beam
Beam 1
H-V kicker for painting the beam
Q5L
Beam Dump Block
Q4L
about 700 m
Fast kicker magnet
Q4R
about 500 m
Q5R
Beam 2
52
Dumping the LHC beam
beam absorber (graphite)
about 8 m
about 35 cm
concrete shielding
53
Full LHC beam deflected into copper target
Copper target
2808 bunches
2 m
Energy density GeV/cm3 on target axis
Target length cm
N.Tahir (GSI) et al.
54
Operational margin of a superconducting magnet
Applied Magnetic Field T
Applied magnetic field T
This is about 1000 times more critical than for
TEVATRON, HERA, RHIC
Bc critical field

Tc critical temperature
9 K
Temperature K
55
56.0 mm
- 3? 1.3 mm
Beam /- 3 sigma
Beam in vacuum chamber with beam screen at 7 TeV
56
Dipole magnets for the LHC
1232 Dipolmagnets Length about 15 m Magnetic
Field 8.3 T Two beam tubes with an opening of 56
mm
57
(No Transcript)
58
(No Transcript)
59
SECTOR 8-1
ELECTRICAL QUALITY ASSURANCE
COOLDOWN
POWERING TESTS
60
LHC Layout eight arcs (sectors) eight long
straight section (about 700 m long)
Beam dump blocks
IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (warm)
IR7 Betatron Cleaning (warm)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
61
Global requirements on the machine
  • Highest energy proton collisions for ATLAS / CMS
  • Nominal luminosity 1034 cm-2 s-1 in points 1 and
    5
  • Highest energy proton collisions for LHCb
  • Nominal luminosity 5 1032 cm-2 s-1 in point 8
  • Proton collisions _at_ various energies for ALICE
  • Nominal luminosity 1030 cm-2 s-1 in point 2
  • Ion collisions _at_ various energies for ALICE
  • Nominal luminosity 1027 cm-2 s-1 in point 2
  • ATLAS and CMS will also take data
  • Proton collisions _at_ various energies for TOTEM

Proton luminosity running
Dedicated operation
Dedicated operation
62
TI 8 Beam spot at end of line
63
Transfer on jacks
64
Preparation of interconnect
65
Repair of QRL modules at CERN
66
Repair of special QRL elements at CERN
http//lhc.web.cern.ch/lhc/LHCnews/repairs20and2
0cooldown_E.pdf
67
Livingston type plot Energy stored magnets and
beam
68
56.0 mm
Collimators at 7 TeV, squeezedoptics
1 mm
R.Assmanns EURO
/- 8 sigma 4.0 mm
Example Setting of collimators at 7 TeV - with
luminosity optics Beam must always touch
collimators first !
Write a Comment
User Comments (0)
About PowerShow.com