Allen Park Presbyterian Church
  • Facility Study 2007-08

2
Facility Study 2007-08 History
  • Doug Pretty introduces Bill McCarthy, McCarthy
    Smith, to Pastor Doug Blaikie.
  • Doug Pretty and Bill McCarthy met with members of
    Building Committee in July 2007 to explain what
    and how a Facility Study could be accomplished.

3
Facility Study 2007-08 History
  • August 2007 - Building Committee hires architects
    Wilkie Zanley and construction manager McCarthy
    Smith to conduct Facility Study which will lead
    to conceptual drawings, estimated costs and
    schedule.

4
Facility Study 2007-08 History
  • Summer/Fall 2007 Onsite investigating,
    discussions with city conducted by Wilkie
    Zanley.
  • Preliminary concepts presented in September 2007
    to Building Committee. Committee directs team to
    further study additions option.

5
Facility Study 2007-08 History
  • McCarthy Smith prepares cost estimates and
    schedule options.
  • Team presents report to Building Committee on
    December 19, 2007.

6
Building Committee Concerns
  • Fellowship Hall (Old Building)
  • Barrier-free access to lower and main levels
  • Multi-purpose space, air-conditioned
  • Church services in summer
  • Social/fellowship activities
  • Youth group activities
  • Additional columbarium space and inventory
  • Develop shower space for annual outreach programs
  • Develop designated storage areas
  • Upgrade electrical service to facilities

7
Building Committee Concerns
  • Main Church (New Building)
  • Barrier-free restroom facilities

8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Scenarios to Consider
  • Scenario 1
  • Construct barrier-free addition and associated
    site work
  • Construct columbarium addition and associated
    basement storage
  • Barrier-free restrooms (Main Church)

1,300,000
Alternate for Development of Office Area 30,000
19
Options to Consider
  • Scenario 2
  • Construct the multi-use addition at a later time.

1,300,000
Alternate for shower room facilities 20,000
Cost is based on 2008 construction dollars.
Average price escalation per year is 4-5.
20
Options to Consider
  • Scenario 3
  • Construct both scenarios at the same
    time.(Represents a cost savings achieved
    through less redundant general condition and
    supervision costs.)

2,500,000
21
Schedule
  • Project Review and Approvals
  • Present to session committee 1/16/08
  • Present to congregation at annual meeting
    1/20/08
  • Congregation to vote on project 2/10/08?

22
Schedule
  • Design
  • Design Phase
  • Review and approval(5-1/2 months) 2/11/08
    - 7/30/08

23
Schedule
  • Bid/Award
  • Bid/Award Phase(1 month) 8/1/08 - 8/29/08

24
Schedule
  • Construction
  • Scenario 1
  • Barrier-free entrance addition
  • Columbarium addition
  • Assorted interior remodeling(6 months)
  • Barrier-free restrooms (main church)
  • 9/15/08 - 3/27/09

25
Schedule
  • Construction
  • Scenario 2
  • Multi-use addition(8 months) TBD

26
Schedule
  • Construction
  • Scenario 3
  • Additions, entrance multi-purpose
  • Columbarium addition
  • Interior remodeling 9/15/08 - 5/30/09

27
AcknowledgementsAllen Park Presbyterian Church
Building Committee
  • Ken Lieber, Co-chair
  • John Dam
  • Shirley Slatka
  • Jim Kinard
  • Fern Brandt
  • Doug Blakie, Pastor
  • John Wilkie
  • Bill McCarthy
  • Jim Bebe, Co-chair
  • Barry Davis
  • Kelly Ellis
  • Larry Templin
  • Melody Jones, Associate Pastor
  • Dave Zanley
  • Steve Banchero

Wilkie-Zanley, Architects
McCarthy Smith, Construction Managers
28
Allen Park Presbyterian Church
  • Facility Study 2007-08
Write a Comment
User Comments (0)
About PowerShow.com