MUO - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

MUO

Description:

Cypress Hotlink. SLIC. MBT. ALPHA. Hotlink. Hotlink. SFO. Nebraska/MIS. MSU-UIC UM/CDF. Saclay ... All Hotlink connections are single channel UTP cables on ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 19
Provided by: mac7
Category:
Tags: muo | cypress

less

Transcript and Presenter's Notes

Title: MUO


1
L1 L2 Trigger Data Flow
S L I C
L2MUO
MUO
L1MUO
z-vertices (?)
SMT
STT
All objects in physics coordinates
refit tracks
L2CFT
CFT
L1CFT
L2 Global
axial
CPS
L2CPS
stereo (u,v)
L2FPS
1st event-wide trigger decision
FPS
L1FPS
CAL
L1CAL
L2CAL
2
DØ Level-2
3
Example L2 Crate Calorimeter
MCH1
Optical Signal inputs from L1 4 2 4
MagicBus
M P M - B I T 3
V B D
F I C
F I C
F I C
four MBT channels
to L3
six MBT channels
All Hotlink connections are single channel UTP
cables on Front Pannels MBT (hotlinks) outputs L2
objects to Global MBT receiver
4
Example L2 Crate Muon
Coax. (SMB cable) inputs from FE L1 into 14
CICs in dedicated crate
MCH3
MagicBus
double channel UTP cables to SLICs
M P M - B I T 3
V B D
S L I C
S L I C
S L I C
M B T
M B T
S F O
eleven total

pilot
assist.
SCL
eleven MBT channels
to L3
to Global
All Hotlink connections are single channel UTP
cables on Front Pannels MBT (hotlinks) outputs L2
objects to Global MBT receiver
5
L2 Crate Locations
6
L2 to Test Stand Connections
Patch panels have identical maps
MCH3 Muon
Source Inputs
SCL (Hub) 1 (?)
SCL 6
CAL 10
PSH 12
CTT 16
MUO 18
Global 10
L1 Mask 1
SLIC 14
Total 88
()
Patch Panel
Permanent cabling
MCH2 STT CTT , PS
FCH2 Test Stand
MBT Channels
MCH1 CAL Global
Image Patch Panel
SLIC Channels
Permanent cabling between MCH and T.Stand is
open ended at MCH for minimal noise. Cables are
bundled acc. to table above. Connect as needed
() The only non-hotlink connection in
P.Panel
obs window is 45x45 cm conn.2x3cm
7
Status of Installation
  • Racks, Crates, Power, Cooling (MCH and FCH)
  • Except muon CIC crate (April?)
  • Almost all Cabling in place
  • building muon pigtails
  • some remaining cabling at the test stand
  • cabling for L3 readout
  • MCH-FCH Window Patch Panel
  • not installed yet
  • need to build 2nd patch panel for the test stand
  • L2 trigger mask to L2HWFW (soon?)
  • L1HWFW to L2Global (via FIC) (soon?)
  • Monitoring of Alphas by L1 Scalers
  • ORCs in April

8
Status of L2 Cards
  • FIC
  • All cards are done
  • BIST errors identified last Fall have been fixed
    at SACLAY by replacing mismatched signal path
    with UTP cable
  • One modified FIC worked fine in BIST mode
  • Cards are currently at UIC to do the wire mods
  • MBT
  • All cards at UMd testing in progress
  • 3 production cards at D0 (3/13/01)
  • commissioning of Alpha-MBT communication in
    progress
  • VHDL firmware is 95 done
  • Programmed I/O, Broadcast, Monitoring
  • SCL handling (April)

9
Status of L2 Cards contd
  • SLIC
  • All cards are here
  • Its a software problem now
  • Basic operating system done
  • CIC
  • BIST tests with the two pre-production boards
    were completed last week
  • lt1x10-12 BER with 40 Forward-Central Sci/MDT
    channels
  • of these channels 1 found dead and 2 gave 1x10-9
    BER (consistent with L3 BIST testing) - suspect
    problems with Mu FE cable/driver
  • must test the remaining 100 PDT channels with
    BIST
  • board released for production last Monday
    (3/12/01)
  • expected delivery of 18 (tested) boards by
    mid-May
  • needed only by muon system

10
Status of L2 Cards contd
  • SFO
  • two pre-production boards pass all tests
  • released for production last week
  • expected delivery of 28 tested boards by mid-May
  • needed by muon system and for test stand
  • Alpha
  • 2 pre-productions (1 CDF) worked within 1 week
    almost a year ago
  • 24 production boards delivered on Sep 13, 2000
  • zero boards worked within 1 week!

11
Alpha Board
12
21172 Chipset
13
Status of L2 Cards contd
  • Alpha contd
  • Many production errors are to blame
  • broken vias
  • small finished sizes
  • boards sat 6 months from preprod to final
    production
  • aging of OPC coat decreases solderability
  • OPC is reactive and can thin vias
  • popcorning of Universe BGA (almost 100 failure)
  • recently confirmed by failure analysis
  • delamination of the CIA BGA (gt63 failure)
  • recently confirmed by failure analysis
  • additional concern bad CIA chips - wire bond
    cross over
  • bad quality control
  • rotated chips, missing components, no
    connectivity to some components, marginal solder
    coverage to some R/Cs

14
Status of L2 Cards contd
  • Alpha contd
  • currently we have 9 functional boards (2 pre-prod
    7 prod)
  • total number is limited by the number of bad-CIA
    boards
  • replacing the CIA has been very adventurous BGA
    sits in the middle of a 9U board much better
    repair yield with Universe BGA
  • long term reliability has been recently tested
    for almost all boards encouraging results,
    however, there are concerns with board
    lifetime/handling
  • some Mbus problems (PIO/DMA) make testing of
    board difficult
  • Bob, Stephen, and Drew are currently at D0
    debugging these remaining features hopefully all
    problems are fixable in firmware

15
Status of L2 Cards contd
  • Alpha contd
  • Assembly of 12 additional boards last shot
  • CIA will be socketed due to concerns of bad chips
    in hand
  • buying 5 more sockets to fix for existing Alphas
  • 4 weeks lead time PO in progress
  • mods to the production layout are completed
    (Stephen, UM/CDF) Johnny Green is reviewing the
    changes (this week?)
  • mods include dogbone widths under BGA, wire
    mods, L3 cache, re-route R/Cs near the CIA for
    socket installation
  • board vendor has been selected PO is ready
  • turnaround time is 5-10 days
  • use white-tin plating instead of OPC
  • bake BGAs before installation
  • expect prototype board gt4 weeks after PCBs with
    remaining boards 4 weeks after that
  • realistically around July for tested boards
  • Beta design proceeds full speed ahead (Orsay,
    UMd, UVA)

16
Online Software Status
  • Alpha
  • Much of structural software exists in simulation
  • Control/data flow for preprocessor and global
  • Draft drivers/setup for MBT and event loop
    March/April
  • Some alpha firmware problems?
  • SCL_INIT, and DAQ interface
  • VME driver, buffer allocation Done
  • VBD/L3 readout beginning DONE (3/14)!
  • Error logging and beginnings of monitoring
    Done
  • Downloading, release to Worker 95 done
  • Admin/Worker control data flow May
  • SLIC
  • Basic operating system in place
  • Code moving to CVS testing download scheme
  • VME drivers written March

17
Algorithms in Simulator
  • Mu L1 seeds DSP Segment Finders,
  • Central, Fwd track assembly code April
  • CTT
  • not tested yet
  • PS
  • CPS more work needed
  • FPS written April?
  • Cal
  • e Run 1B L1.5
  • j merge needs work
  • MET L1
  • Global
  • e(cal,cps), j(cal) (e fps, ctt ready)
  • Ht, MET (mass)
  • Mu(with ctt) Apr/May?
  • STT April?

?
18
Time Line
15-Mar 6-11 Alphas Available
? 15-Mar MBT's on Site ? 1-Apr
MBT-Alpha-VBD Data Flow ? Apr L2 Muon
Software Integrated May
2Alpha/MBT/VBD Integration May
Begin Cal/Muon/Global Ind. Integration May
Muon I/O Cards (CIC/SFO's) Jun
Global/Cal/Muon in L3/DAQ Jul Twelve
Additional alphas (repairprod) Jul Start
PS/CTT
Write a Comment
User Comments (0)
About PowerShow.com