Title: MUO
1L1 L2 Trigger Data Flow
S L I C
L2MUO
MUO
L1MUO
z-vertices (?)
SMT
STT
All objects in physics coordinates
refit tracks
L2CFT
CFT
L1CFT
L2 Global
axial
CPS
L2CPS
stereo (u,v)
L2FPS
1st event-wide trigger decision
FPS
L1FPS
CAL
L1CAL
L2CAL
2DØ Level-2
3Example L2 Crate Calorimeter
MCH1
Optical Signal inputs from L1 4 2 4
MagicBus
M P M - B I T 3
V B D
F I C
F I C
F I C
four MBT channels
to L3
six MBT channels
All Hotlink connections are single channel UTP
cables on Front Pannels MBT (hotlinks) outputs L2
objects to Global MBT receiver
4Example L2 Crate Muon
Coax. (SMB cable) inputs from FE L1 into 14
CICs in dedicated crate
MCH3
MagicBus
double channel UTP cables to SLICs
M P M - B I T 3
V B D
S L I C
S L I C
S L I C
M B T
M B T
S F O
eleven total
pilot
assist.
SCL
eleven MBT channels
to L3
to Global
All Hotlink connections are single channel UTP
cables on Front Pannels MBT (hotlinks) outputs L2
objects to Global MBT receiver
5L2 Crate Locations
6L2 to Test Stand Connections
Patch panels have identical maps
MCH3 Muon
Source Inputs
SCL (Hub) 1 (?)
SCL 6
CAL 10
PSH 12
CTT 16
MUO 18
Global 10
L1 Mask 1
SLIC 14
Total 88
()
Patch Panel
Permanent cabling
MCH2 STT CTT , PS
FCH2 Test Stand
MBT Channels
MCH1 CAL Global
Image Patch Panel
SLIC Channels
Permanent cabling between MCH and T.Stand is
open ended at MCH for minimal noise. Cables are
bundled acc. to table above. Connect as needed
() The only non-hotlink connection in
P.Panel
obs window is 45x45 cm conn.2x3cm
7Status of Installation
- Racks, Crates, Power, Cooling (MCH and FCH)
- Except muon CIC crate (April?)
- Almost all Cabling in place
- building muon pigtails
- some remaining cabling at the test stand
- cabling for L3 readout
- MCH-FCH Window Patch Panel
- not installed yet
- need to build 2nd patch panel for the test stand
- L2 trigger mask to L2HWFW (soon?)
- L1HWFW to L2Global (via FIC) (soon?)
- Monitoring of Alphas by L1 Scalers
- ORCs in April
8Status of L2 Cards
- FIC
- All cards are done
- BIST errors identified last Fall have been fixed
at SACLAY by replacing mismatched signal path
with UTP cable - One modified FIC worked fine in BIST mode
- Cards are currently at UIC to do the wire mods
- MBT
- All cards at UMd testing in progress
- 3 production cards at D0 (3/13/01)
- commissioning of Alpha-MBT communication in
progress - VHDL firmware is 95 done
- Programmed I/O, Broadcast, Monitoring
- SCL handling (April)
9Status of L2 Cards contd
- SLIC
- All cards are here
- Its a software problem now
- Basic operating system done
- CIC
- BIST tests with the two pre-production boards
were completed last week - lt1x10-12 BER with 40 Forward-Central Sci/MDT
channels - of these channels 1 found dead and 2 gave 1x10-9
BER (consistent with L3 BIST testing) - suspect
problems with Mu FE cable/driver - must test the remaining 100 PDT channels with
BIST - board released for production last Monday
(3/12/01) - expected delivery of 18 (tested) boards by
mid-May - needed only by muon system
10Status of L2 Cards contd
- SFO
- two pre-production boards pass all tests
- released for production last week
- expected delivery of 28 tested boards by mid-May
- needed by muon system and for test stand
- Alpha
- 2 pre-productions (1 CDF) worked within 1 week
almost a year ago - 24 production boards delivered on Sep 13, 2000
- zero boards worked within 1 week!
11Alpha Board
1221172 Chipset
13Status of L2 Cards contd
- Alpha contd
- Many production errors are to blame
- broken vias
- small finished sizes
- boards sat 6 months from preprod to final
production - aging of OPC coat decreases solderability
- OPC is reactive and can thin vias
- popcorning of Universe BGA (almost 100 failure)
- recently confirmed by failure analysis
- delamination of the CIA BGA (gt63 failure)
- recently confirmed by failure analysis
- additional concern bad CIA chips - wire bond
cross over - bad quality control
- rotated chips, missing components, no
connectivity to some components, marginal solder
coverage to some R/Cs
14Status of L2 Cards contd
- Alpha contd
- currently we have 9 functional boards (2 pre-prod
7 prod) - total number is limited by the number of bad-CIA
boards - replacing the CIA has been very adventurous BGA
sits in the middle of a 9U board much better
repair yield with Universe BGA - long term reliability has been recently tested
for almost all boards encouraging results,
however, there are concerns with board
lifetime/handling - some Mbus problems (PIO/DMA) make testing of
board difficult - Bob, Stephen, and Drew are currently at D0
debugging these remaining features hopefully all
problems are fixable in firmware
15Status of L2 Cards contd
- Alpha contd
- Assembly of 12 additional boards last shot
- CIA will be socketed due to concerns of bad chips
in hand - buying 5 more sockets to fix for existing Alphas
- 4 weeks lead time PO in progress
- mods to the production layout are completed
(Stephen, UM/CDF) Johnny Green is reviewing the
changes (this week?) - mods include dogbone widths under BGA, wire
mods, L3 cache, re-route R/Cs near the CIA for
socket installation - board vendor has been selected PO is ready
- turnaround time is 5-10 days
- use white-tin plating instead of OPC
- bake BGAs before installation
- expect prototype board gt4 weeks after PCBs with
remaining boards 4 weeks after that - realistically around July for tested boards
- Beta design proceeds full speed ahead (Orsay,
UMd, UVA)
16Online Software Status
- Alpha
- Much of structural software exists in simulation
- Control/data flow for preprocessor and global
- Draft drivers/setup for MBT and event loop
March/April - Some alpha firmware problems?
- SCL_INIT, and DAQ interface
- VME driver, buffer allocation Done
- VBD/L3 readout beginning DONE (3/14)!
- Error logging and beginnings of monitoring
Done - Downloading, release to Worker 95 done
- Admin/Worker control data flow May
- SLIC
- Basic operating system in place
- Code moving to CVS testing download scheme
- VME drivers written March
17Algorithms in Simulator
- Mu L1 seeds DSP Segment Finders,
- Central, Fwd track assembly code April
- CTT
- not tested yet
- PS
- CPS more work needed
- FPS written April?
- Cal
- e Run 1B L1.5
- j merge needs work
- MET L1
- Global
- e(cal,cps), j(cal) (e fps, ctt ready)
- Ht, MET (mass)
- Mu(with ctt) Apr/May?
- STT April?
?
18Time Line
15-Mar 6-11 Alphas Available
? 15-Mar MBT's on Site ? 1-Apr
MBT-Alpha-VBD Data Flow ? Apr L2 Muon
Software Integrated May
2Alpha/MBT/VBD Integration May
Begin Cal/Muon/Global Ind. Integration May
Muon I/O Cards (CIC/SFO's) Jun
Global/Cal/Muon in L3/DAQ Jul Twelve
Additional alphas (repairprod) Jul Start
PS/CTT