PICAYUNE STRAND RESTORATION PROJECT PUMP STATIONS PRELIMINARY DESIGN - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

PICAYUNE STRAND RESTORATION PROJECT PUMP STATIONS PRELIMINARY DESIGN

Description:

PICAYUNE STRAND RESTORATION PROJECT. PUMP STATIONS ... Cypress. National. Preserve. Rural Development. Picayune. Strand. Rookery. Bay. National. Estuarine ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 26
Provided by: christ125
Category:

less

Transcript and Presenter's Notes

Title: PICAYUNE STRAND RESTORATION PROJECT PUMP STATIONS PRELIMINARY DESIGN


1
PICAYUNE STRAND RESTORATION PROJECTPUMP STATIONS
PRELIMINARY DESIGN
South Florida Water Management District Water
Resources Advisory Committee Issues
Workshop March 16, 2006

2
Contents
  • Project Overview
  • Introduction to Pump Stations
  • Pump Station Preliminary Design
  • Schedule
  • Issues and concerns
  • Discussion

3
PROJECT OVERVIEW
4
The Missing Piece of the Puzzle
Florida Panther National Wildlife Refuge
Rural Development
  • Restores ecological connectivity between publicly
    owned lands

Big Cypress National Preserve
Picayune Strand State Forrest
Fakahatchee Strand State Preserve
Collier SeminoleState Park
10,000 Islands National Wildlife Refuge
Rookery BayNational EstuarineResearch
Preserve
Everglades National Park
Picayune Strand
5
Hydrologic Restoration Study Area
6
Pre-Development Flowways
7
Recommended Plan
ELEMENTS
MILES
3 Spreader Canals 3 Pump Stations Canal
Plugs 80 of Roads Removed Primary All Weather
Roads Secondary Roads Flood Protection Levees

I-75
810 cfs
Private Lands Levee
1250 cfs
2650 cfs
Management Roads
6L levee
U.S 41
POI N levee
POI SE levee
POI SW levee
8
Design Activities
  • Preliminary Design
  • Pump Stations
  • Road Removal
  • BODR Development
  • Spreader Canals
  • Protection Levees

9
Pump Stations Preliminary Design Overview
  • Based on PIR
  • Three Pump Stations
  • Merritt Canal 810 cfs
  • Miller Canal 1250 cfs
  • Faka Union Canal 2650 cfs

10
Pump Stations
  • Sized for 100 Year Storm Event
  • Merritt 810 cfs
  • Miller 1250 cfs
  • Faka Union 2650 cfs
  • Designed to Meet CERP and SFWMD Standards
  • 155 mph wind load
  • Diesel drives
  • Ten day fuel supply
  • Minimal Reliance on Outside Utilities
  • Diesel engines and generators
  • Remote Control and Operations Capability

11
Faka Union Canal Watershed
12
PSRP Pump Station Sites
13
Hydrologic Design Criteria
  • Match Canal Stage Hydrographs at I-75 For 5-Day,
    100-Year Design Storm Event
  • No Pump Operation Below Minimum Canal Levels at
    I-75
  • Wet Season Dry Season (ft
    NAVD88) (ft NAVD88)
  • Miller Canal 4.9 5.9
  • Faka Union Canal 4.9 5.9
  • Merritt Canal 5.2 8.0

14
Miller Pump StationConceptual Site Plan
15
Faka Union Pump Station Conceptual Site Plan
16
Merritt Pump Station Conceptual Site Plan
17
G-370 Intake Side of Station
18
G-370 Discharge Side of Station
19
Typical Large Pump Station Control Room
20
Preliminary Design Pump Sizing and Configuration
BODR and Preliminary Design




Total
Number
Pump
Proposed
of
Drive
Station
1
Capacity
Pumps
Type
Capacity
(cfs)
per Size






(cfs)

75


2
Motor


Merritt PS

810

220

31
Engine

75


2

Motor

M
iller PS

1,250

220
51






Engine

100


3
Motor

470

Faka Union PS

2,650



51
Engine

Total Number
4


of Pump Sizes
1
The highlighted pump sizes have been installed
previously in District pump stations.



21
Existing Electric Utility Lines
22
Schedule
Initiate Design 12/04 Complete Design 11/06 Start
Construction 1/07 Construction Complete 12/08 Oper
ational Testing 4/09
23
Stakeholder Issues and Concerns(Pump Stations)
  • Capacity and operation of pump stations
    consistent with PIR
  • Hardy Pit is not a storage reservoir on Project
  • Redundant pump capacity included
  • Pump Station operation will mimic existing
    structures

24
Stakeholder Issues and Concerns(other Project
Features)
  • Location and sizing of protection levees is being
    addressed in a separate BODR.
  • Project will not change water quality
  • Working with DOF recreational opportunities
    will be consistent with DOF Land Management Plan
  • Additional modeling is being done to determine if
    there are impacts to Tamiami Trail
  • Pump stations shall be operated in accordance
    with the Permit criteria and Operation Plan
  • All modeling will be completed before Final
    Design
  • Uplands and Wetlands were used as criteria in
    determining Project benefits

25
DISCUSSION
Write a Comment
User Comments (0)
About PowerShow.com