Title: PICAYUNE STRAND RESTORATION PROJECT PUMP STATIONS PRELIMINARY DESIGN
1PICAYUNE STRAND RESTORATION PROJECTPUMP STATIONS
PRELIMINARY DESIGN
South Florida Water Management District Water
Resources Advisory Committee Issues
Workshop March 16, 2006
2Contents
- Project Overview
- Introduction to Pump Stations
- Pump Station Preliminary Design
- Schedule
- Issues and concerns
- Discussion
3PROJECT OVERVIEW
4The Missing Piece of the Puzzle
Florida Panther National Wildlife Refuge
Rural Development
- Restores ecological connectivity between publicly
owned lands
Big Cypress National Preserve
Picayune Strand State Forrest
Fakahatchee Strand State Preserve
Collier SeminoleState Park
10,000 Islands National Wildlife Refuge
Rookery BayNational EstuarineResearch
Preserve
Everglades National Park
Picayune Strand
5Hydrologic Restoration Study Area
6Pre-Development Flowways
7Recommended Plan
ELEMENTS
MILES
3 Spreader Canals 3 Pump Stations Canal
Plugs 80 of Roads Removed Primary All Weather
Roads Secondary Roads Flood Protection Levees
I-75
810 cfs
Private Lands Levee
1250 cfs
2650 cfs
Management Roads
6L levee
U.S 41
POI N levee
POI SE levee
POI SW levee
8Design Activities
- Preliminary Design
- Pump Stations
- Road Removal
-
- BODR Development
- Spreader Canals
- Protection Levees
9Pump Stations Preliminary Design Overview
- Based on PIR
- Three Pump Stations
- Merritt Canal 810 cfs
- Miller Canal 1250 cfs
- Faka Union Canal 2650 cfs
10Pump Stations
- Sized for 100 Year Storm Event
- Merritt 810 cfs
- Miller 1250 cfs
- Faka Union 2650 cfs
- Designed to Meet CERP and SFWMD Standards
- 155 mph wind load
- Diesel drives
- Ten day fuel supply
- Minimal Reliance on Outside Utilities
- Diesel engines and generators
- Remote Control and Operations Capability
11Faka Union Canal Watershed
12PSRP Pump Station Sites
13Hydrologic Design Criteria
- Match Canal Stage Hydrographs at I-75 For 5-Day,
100-Year Design Storm Event - No Pump Operation Below Minimum Canal Levels at
I-75 - Wet Season Dry Season (ft
NAVD88) (ft NAVD88) - Miller Canal 4.9 5.9
- Faka Union Canal 4.9 5.9
- Merritt Canal 5.2 8.0
14Miller Pump StationConceptual Site Plan
15Faka Union Pump Station Conceptual Site Plan
16Merritt Pump Station Conceptual Site Plan
17G-370 Intake Side of Station
18G-370 Discharge Side of Station
19Typical Large Pump Station Control Room
20Preliminary Design Pump Sizing and Configuration
BODR and Preliminary Design
Total
Number
Pump
Proposed
of
Drive
Station
1
Capacity
Pumps
Type
Capacity
(cfs)
per Size
(cfs)
75
2
Motor
Merritt PS
810
220
31
Engine
75
2
Motor
M
iller PS
1,250
220
51
Engine
100
3
Motor
470
Faka Union PS
2,650
51
Engine
Total Number
4
of Pump Sizes
1
The highlighted pump sizes have been installed
previously in District pump stations.
21Existing Electric Utility Lines
22Schedule
Initiate Design 12/04 Complete Design 11/06 Start
Construction 1/07 Construction Complete 12/08 Oper
ational Testing 4/09
23Stakeholder Issues and Concerns(Pump Stations)
- Capacity and operation of pump stations
consistent with PIR - Hardy Pit is not a storage reservoir on Project
- Redundant pump capacity included
- Pump Station operation will mimic existing
structures
24Stakeholder Issues and Concerns(other Project
Features)
- Location and sizing of protection levees is being
addressed in a separate BODR. - Project will not change water quality
- Working with DOF recreational opportunities
will be consistent with DOF Land Management Plan - Additional modeling is being done to determine if
there are impacts to Tamiami Trail - Pump stations shall be operated in accordance
with the Permit criteria and Operation Plan - All modeling will be completed before Final
Design - Uplands and Wetlands were used as criteria in
determining Project benefits
25DISCUSSION