Factory Building Symposium on Lean Production
  • January 29, 2007Austin, Texas

2
Palm Harbor HomesAlbemarle, NCAllen Tucker,
Production Manager
  • Clutter to Cash

3
Palm Harbor Albemarle
4
Goal Free Space in the Plant
  • Obsolete and damaged material
  • Unneeded equipment
  • Poor organization of space
  • No system to flush items not needed for
    production from production space

5
Palm Harbors Strategy
  • Form RPI team
  • Designate red tag area
  • Develop red tag process
  • Implement red tag system
  • Departments submit lists
  • Items moved to red tag area
  • Count and value estimates prepared
  • Team meets to examine the items and decide their
    fate
  • Decision is carried out as soon as possible
  • Process repeats weekly
  • Allen Tucker, production manager
  • Tommy Rogers, special projects manager
  • Darrell Story, supervisor of cabinets, doors,
    trim depts.
  • Mark Burke, purchasing manager
  • Deedy Hatley, assistant purchasing manager
  • Doug Eudy, quality assurance manager
  • Dalton McCollum, inventory control supervisor

Lean principle written standard operating
procedures
6
Results
  • Welding, plumbing, ceramic, trim and final areas
    are less cluttered and more organized
  • Recovered 7,603 in obsolete molding
  • Recovered 1,689 from obsolete ceramic tile
  • Recovered 1,760 from obsolete light fixtures
  • Total saved to date 21,282

7
Highlights
  • Using lean to clear space and generate cash
  • Team allows fast action
  • Keeps purchasing and sales on their toes
  • Empowers people
  • Increases involvement in lean
  • Improves teamwork

8
Roof Plastic Application
9
Roof Plastic
Then
  • Small, unstable and awkward work platform
  • No material staging
  • Unsafe rolling procedure

10
Roof Plastic
Now
Now
  • Large stable platform full width of module
  • Material staging on platform
  • Access for supply from fork truck
  • Plastic rolls mounted on spool

Lean principles Five Ss, ergonomics
11
Results
  • Cost 10,000 in materials and 3,000 in labor
  • Safer roof access and application
  • Cycle time reduced
  • Fewer workers required
  • Additional platforms under consideration

12
Going Forward
  • Five S program
  • Red tag system
  • Racks, jigs and fixtures

13
Lean Symposium
14
Factory Building Symposium on Lean Production
  • Manufactured Housing Research Alliance
  • Jordan Dentz
  • (212) 496-0900 x13
  • jdentz_at_research-alliance.org
  • www.mhrahome.org
Write a Comment
User Comments (0)
About PowerShow.com