Overview of the - PowerPoint PPT Presentation

1 / 67
About This Presentation
Title:

Overview of the

Description:

Overview of the – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 68
Provided by: ITER4
Category:

less

Transcript and Presenter's Notes

Title: Overview of the


1
Overview of the ITER Plasma Facing
Components Presented by M. Merola with thanks
to R. Pitts, A. Martin, C. Lowry, M. Pick, J.
Palmer, A. Kukushkin, A. Loarte, R. Mitteau And
the ITER Domestic Agencies
2
Outline
Divertor First Wall and Blanket
3
Status of PFCs Divertor
4
Divertor System
Main Functions
  • Divertor system main functions
  • Exhaust the major part of the plasma thermal
    power (including alpha power)
  • Minimize the helium and impurities content in
    the plasma

5
Divertor System
Overall Layout and Ports
54
Cassettes in a circular array held in position by
two concentric radial rails .
6
Divertor System
Overall Layout and Ports
Nine equally
spaced divertor level ports, arranged at
40 degrees of each other RH Ports, Diagnostic
Ports Cryopump Ports
7
Divertor System
Overall Layout and Ports
Diagnostic
Port 10
RH Port 8
Cryopump Port 12
Cryopump Port 6
RH Port 14
Cryopump Port 4
Diagnostic
Port 16
RH Port 2
Cryopump Port 18
8
Divertor System
Outer Toroidal Rail
Central Cassette Rail
Support Pad
Support Pad
Central
Cassette Rail permanently installed in
Diagnostic and Cryopump Ports removable on RH
Ports
9
Divertor System
Outer Toroidal Rail
10
Divertor System
Diagnostics
Diagnostic Equipment located inside three RH
Ports and two Diagnostic Ports 16 in total
11
ITER Party Responsibilities
Divertor System
Diagnostics
Baseline 2006

Twenty different systems delivered by six Parties
12
Divertor System
Diagnostics
  • Diagnostic Integration Criteria
  • 1) Preserve overall functionality of the divertor
    system, while fulfilling the
  • requirements of each specific system.
  • 2) Avoid as much as possible creating divertor
    cassette variants, to minimize
  • manufacturing costs and maximize the flexibility
    in the management of spare
  • Partsgt integrate as many diagnostic interfaces
    into the standard cassette
  • design as possible
  • Standard PFCs Standard Cassette Body (CB )
    45
  • PFCs Variant to integrate Langmuir Probes Stand
    CB 5
  • PFCs Variant to integrate Thermocouples
    Stand CB 3
  • Standard PFCs CB Variant to integrate Neutron
    Camera 1

13
Divertor System
14
Divertor System
Cassette body
The divertor CB is reusable to minimise activated
waste it provides neutron shielding, routes the
water coolant and supports the different PFCs
15
Divertor System
16
Divertor System
Vertical Targets
The inner and outer vertical targets (VTs), are
the PFCs that, in their lower part, intercept the
magnetic field lines, and therefore remove the
heat load coming from plasma via conduction,
convection and radiation.
Inner VT
Outer VT
17
Divertor System
18
Dome
Divertor System
The inner and outer neutral Particle Reflector
Plates protect the CB from plasma radiation,
allow transient movements of the strike points
and provide improved operational flexibility of
the divertor in terms of magnetic configuration.
The Umbrella, which is located below the
separatrix, baffles neutrals, particularly helium.
Large conductance between the two divertor
channels increases the neutral densities at the
outer target and enhance radiation losses
19
Materials Choice
Divertor System
In the current ITER baseline CFC at the strike
points, W on the baffles through the H and D
phases All-W from the start of DT operations
  • Rationale
  • Carbon easier to learn with
  • Lack of melting makes it easier to test ELM and
    disruption mitigation strategies
  • T-retention expected to be too high in DT phase
    with CFC targets
  • But (limited) DT operations with CFC target still
    in place not excluded

W reflector plates
20
CFC W Transition Point
Divertor System
  • W-CFC interface moved down 10 cm
  • During H D phases strike points can be placed
    on the W part
  • Modelling demonstrates that a 7.5 MA plasma
    equilibrium can be established in H-mode on the W
    part of the vertical target
  • Heat loads will not exceed the 5 MWm-2 for which
    the W monoblocks are qualified
  • At least 2 power e-folding lengths on vert.
    target portion (lp 1.0 cm scaled with 1/Ip from
    0.5 cm _at_15 MA)

Reasonable compromise between easier start with
CFC and gaining experience with W as soon as
possible in preparation for DT (with W).
21
Flexibility built-in in the Design
Divertor System
1
2
3
  • 1. Radial width of IVT increased2. Position of
    inner dome multi-link3. Position of dome cooling
    pipes
  • All modified to maximise flexibility

IVT can be shifted back and forth by ?5? if
required in future designs
22
Alignment of PFCs
Divertor System
The PFCs shall be angled to avoid exposing the
leading edges of the armour to the Scrape-Off
Layer (SOL), otherwise the near normal incidence
of the SOL on these edges would cause large
amounts of carbon to be evaporated (or tungsten
melted) with the inherent risk of poisoning of
the plasma and/or inducing a critical heat flux
event in the water coolant. A nominal step in
the toroidal direction between adjacent targets
of 3 mm is taken as a requirement
23
Divertor System
Supporting analysis
  • Divertor is being subject to final rigorous
    analysis
  • Time averaged and transient loads (plasma fluxes
    and radiation (specified by physics) updated and
    being used for final thermal analysis
  • Detailed electromagnetic FE modelling (VDE
    forces)
  • Hydraulic analysis of whole cassette (cooling
    water pressure drops, draining and dry)

Example for predicted transient heat loads(loads
in red permissible up to 10 s, in yellow up to 2
s)
24
Design Values
Divertor System
  • The PFCs of the first divertor set shall
    withstand 3000 equivalent pulses of 400 s
    duration at nominal parameters, including 300
    slow transients
  • During normal operational conditions
  • vertical target has a design surface heat flux up
    to 10 MW/m2 (strike point region) and 5 MW/m2
    (baffle region)
  • Under slow transient thermal loading conditions
  • lower divertor vertical target geometry has a
    design surface heat flux up to 20 MW/m2 for
    sub-pulses of less than 10 s
  • The dome shall sustain heat fluxes of up to 5
    MW/m2
  • The umbrella and the particle reflector plates
    shall sustain local heat flux up to 10 MW/m2,
    which can be transiently swept across the surface
    (about 2 s) as the plasma is returned to its
    correct position

25
Power Handling
Comparisons
HIGH HEAT FLUX COMPONENTS FOSSILE FIRED BOILER WALL (ABB) FISSION REACTOR (PWR) CORE ITER DIVERTOR
DESIGN 12/15 mm ID/OD
HEAT FLUX average MW/m2 - maximum MW/m2 0.2 0.3 0.7 1.5 3 5 10 20
Max heat load MJ/m2 Lifetime years Nr. of full load cycles Neutron damage dpa Materials - 25 8000 - Ferritic-Martens. steel - 4 10 10 Zircaloy - 4 10 5-8 3000 - 16000 0.2 CuCrZr CFC/W
Coolant - pressure MPa - temperature C - velocity m/s - leak rate g/s Water-Steam 28 280-600 3 lt50 Water 15 285-325 5 lt50(SG) Water 4 100 150 9 11 lt10-7
26
Divertor RH
Replacements
  • The divertor shall be designed for relatively
    frequent (3 times during the 20 years of ITER
    operation) fully remote assembly and disassembly
  • 6 months is the maximum (that is, the target)
    period that shall be allocated for cassette
    refurbishment/replacement (from divertor port
    primary closure plate opening to its closure).
    2-month allowance for machine shutdown and
    start-up time should be added to this period.
  • The replacement time of a single faulty cassette
    will depend on its toroidal position and, on the
    average, shall not exceed 2 months
  • Two sets of divertor cassettes shall be procured
    to allow the off-line refurbishment

27
Maintenance Strategy
Divertor RH
  • Main feature
  • Four divertor sets ? Three divertor
    replacements

2
1
3
4
PFCs new CBs new (set 2)
PFCs new CBs set 1 5 diagn cass new
PFCs new CBs new (set 1)
PFCs new CBs set 2 5 diagn cass new
28
RH Equipments
Divertor RH
  • Divertor RH equipment is comprised of
  • Two main types of cassette mover
  • Cassette Multifunctionl Mover (CMM)
  • Cassette Toroidal Mover (CTM)
  • Each are to be equipped with a dexterous
    manipulator arm and RH tooling.

29
Divertor RH
Divertor Test Platform 2
CMM with Second Cassette End-Effector
  • Objective
  • To demonstrate in-vessel cassette handling and
    divertor maintenance.
  • Details
  • To be located in Tampere (Finland) and hosted by
    the TEKES fusion Association.
  • Comprises a 27o mock-up of the ITER divertor
    region with one radial access port.
  • To initially include
  • CMM prototype
  • Second cassette mock-up
  • Later extensions to include
  • Cassette Toroidal Mover (CTM)
  • prototype
  • standard central cassettes
  • divertor cooling pipes

DTP2
 
TECHNICAL RESEARCH CENTRE OF FINLAND
30
Divertor Remote Handling
DRP
Divertor Refurbishment Platform
Objective To demonstrate and refine hot-cell
cassette maintenance operations. Details Located
in Brasimone (Italy) and hosted by the ENEA
fusion Association. Comprises a remote work cell
equipped with light dexterous manipulators,
robotic tool / component transporters and
component refurbishment tooling. Visual feedback
via video link (no direct viewing) in keeping
with the ITER hot-cell concept.
 
31
Divertor Remote Handling
Main Challenges
  • Characteristics
  • Very tight cassette-VV clearance often 25mm
  • Almost blind operations (for radial transport)
  • ITER will be dark !
  • There must be a heavy reliance on virtual
    techniques and extremely good correlation of
    virtual models with as-built data.

At 5m, 25mm 0.3 on the lift axis joint angle.
25mm
Hinge
Selected resolvers have a fundamental accuracy of
30 arc-seconds.
x
5m
32
Thermo-Hydraulics
Coolant Flow Path
Divertor coolant design parameters Inlet
temperature 100 C Inlet water pressure
4.2 MPa Total pressure drop lt 1.4 MPa CHF
margin gt 1.4 Total flow rate
lt 1000 kg/s
33
Experiments
Thermo-Hydraulics
Pressure drop vs.flow rate have been measured on
Outer and Inner Vertical target and Dome (ENEA
Brasimone)
Hydraulic testing of DOME
Hydraulic testing of IVT
34
Experiments
Thermo-Hydraulics
35
Overall Divertor Pressure Drop (MPa)
Inner VT 0.51
Outer VT 0.32
Dome 0.73
Cassette 0.002
TOTAL 1.56
  • Total pressure drop 1. 56 lt 1.6 MPa
  • Total flow rate 934 lt 1000 kg/s

36
Critical Heat Flux
Critical heat flux tests on monoblocks
37
Terminology Flat Tile and Monoblock
HHF Technologies
38
HHF Technologies
FT
M
M
FT
39
HHF Technologies
Thermal expansion at 300 C
40
HHF Technologies
Monoblocks
CFC or W
CuCrZr tube
AMC (CFC) Brazing (CFC) Casting
HIPing Brazing Hot Radial Pressing
Cu interlayer
41
HHF Technologies
Flat Tiles
Armour to heat sink joints
Cu casting Brazing
Tungsten
Pure copper interlayer
HIPing Hot Radial Pressing Brazing EB welding
CuCrZr
42
Vertical TargetMedium-Scale Prototype
Test results
  • W macrobrush
  • 15 MW/m2 x 1000 cycles
  • CFC monoblock
  • 20 MW/m2 x 2000 cycles
  • CHF test gt 30 MW/m2

43
Vertical TargetFull-Scale Prototype
  • W monoblocks
  • 10 MW/m2 x 1000 cycles
  • CFC monoblock
  • 10 MW/m2 x 1000 cycles
  • 20 MW/m2 x 1000 cycles
  • 23 MW/m2 x 1000 cycles

44
  • Brazing using TiCuNi and CuNiMn alloys
  • 15 MW/m2 x 3000 cycles 20 MW/m2 x 1000 cycles

45
Other mockups
Type 2
Type 1
Type 3
Type 4
46
HHF test at 20 MW/m2 (19-25 MW/m2) of the type-4
mockup
  • Test facility JEBIS
  • Flow rate approx. 70 L/min ( 10m/s) at 4 MPa

47
600 mm
  • W-Cu by casting
  • Cu-CuCrZr by CuInSnNi (STEMET 1108) brazing
  • 18.5 MW/m2 x 1000 cycles

48
The mock-up has survived 1000 thermal cycles at
5 MW/m2 500 thermal cycles at 6
MW/m2 500 thermal cycles at 7 MW/m2 No
overheating, no visible detachments After
testing the mock-up was destructively examined
49
Divertor Qualification Prototypes
A qualification is needed for the critical
procurement packages shared by multi-Parties,
including the divertor
50
Divertor Qualification Prototypes
Design Value (Incident heat flux) Test results (Absorbed heat flux) Test results (Absorbed heat flux) Test results (Absorbed heat flux)
CFC 300 cycles at 20 MW/m2 1000 cycles 10 MW/m2 987 cycles gt20 MW/m2 1000 cycles 10 MW/m2 1000 cycles 20 MW/m2 N/A
W 1000 cycles at 5 MW/m2 1000 cycles 3 MW/m2 1000 cycles 5 MW/m2 1000 cycles 3 MW/m2 1000 cycles 5 MW/m2 1000 cycles 3 MW/m2 1000 cycles 5 MW/m2 348 cycles 10 MW/m2
51
Vertical Targets
Plasma-Facing Components
W monoblock
5 MW / m2
XM-19
316L(N)-IG
10 MW / m2
20 MW / m2 10 sec
XM-19
52
Vertical Targets
Plasma-Facing Components
53
Dome
Plasma-Facing Components
W Flat Tiles
5 MW / m2
316L(N)
XM-19
316L pipes
54
Acceptance Criteria
Plasma-Facing Components
Manufacturing of more than 100 mock-ups with
artificial defects
High heat flux test of mock-ups with artificial
defects
Non-destructive and destructive examinations of
mock-ups
Final definition of the divertor acceptance
criteria
55
Acceptance Criteria
Plasma-Facing Components
SamplesThere are 112 samples split in two
batches - 56 HIPing Technology ? Plansee-
56Hot Radial Pressing Technology ? Ansaldo
RicercheEach batch of 56 samples includes -
28 CFC monoblocks 26 short 2 high- 14
W monoblocks- 14 W flat tiles
CFC monoblock (Ansaldo)
W monoblock (Ansaldo)
CFC monoblock (Plansee)
W flat tile (Plansee)
56
Status of PFCs First Wall and Blanket
57
Caveat Divertor design and plans for
procurement are far more advanced than for the
first wall. It is not possible at this time to
give more than outline indications of FW design
progress
58
Functions
FW Blanket
  • To limit the neutron fluence to the Vacuum
    Vessel and Coils
  • To be remotely installed, repaired and exchanged
  • Simple and reliable attachments
  • Minimise number of operations
  • To exhaust incident plasma exhaust power
  • Active cooling technology
  • Plasma compatible materials

59
Procurement Sharing
FW Blanket
Procurement sharing
  • Almost all Parties involved in first wall and
    blanket procurement
  • Makes the problem harder from a design and
    organizational point of view
  • ? Simplification of the procurement scheme shall
    be urgently attempted !

60
Power Handling Capability
FW Blanket
2001 Requirements
2008 Requirements
Power flux and disruption halo current following
field lines Interactions deep into the scrape-off
layer
0.5 MWm-2 Surface flux Disruption halo current
defined as surface current density
No particular shaping requirements Medium heat
flux technology
Attention to shaping required Higher heat flux
technology required
61
Thermal Load Specifications
FW Blanket
  • First wall power loadings broken down into
    several categories
  • Limiter start-up and ramp-down
  • Steady state (inter-ELM) heat fluxes
  • ELM transient heat fluxes
  • Plasma movement onto wall in response to
    confinement transients
  • All reported in detailed thermal load
    specification document recently agreed into ITER
    Baseline (PCR-093)
  • Derived from extrapolation of results from
    present machines all expressed in terms of
    midplane parallel heat fluxes

62
Old Baseline Design
FW Blanket
First wall panel
First Wall leg welded at back of shield module
Vacuum vessel
Shield module
Central support leg to allow for thermal expansion
Key to react radial moment
Flexible cartridge to allow for differential
expansion
4 individual First Wall Panels to reduce induced
currents
  • Number of issues identified by 2007 design
    review
  • Very small (30 mm) access holes for cutting and
    re-welding of hydraulic connectors ? PFC
    changeout extremely difficult (if not impossible)
    in-vessel
  • FW panels toroidally flat on LFS and top, faceted
    on HFS ? no leading edge protection (not required
    on LFS due to favourable plasma curvature)
  • Relied on less than 2 mm possible misalignment
    between adjacent panels

63
New Design Concept
FW Blanket
  • Design driver minimise changes to VV interface
  • VV is long lead item manufacture must start as
    early as possible

Shield block semi-permanent item leave
interfaces to VV as fixed as possible
Single FW panel removable in-vessel Reduces RH
operations, better power handling Horizontal
fingers reduce halo loads and eddy
currents Toroidal shaping to protect leading
edges
Poloidal Shaping Allow good access for RH Shadow
leading edges
64
New Design Concept
FW Blanket
Complexity arises on LFS due to numerous
asymmetries set by diagnostic ports, heating
systems, test blanket modules, ripple ? maintain
identical FW panels but radially advance poloidal
bands in between ports
Parallel power flux reduced drastically as more
limiters used But start-up and higher potential
heat fluxes near 2nd X-point may impose variable
cooling technology at different locations
3.0 MW/m2
1.5 MW/m2
Poloidal strips of 9 blanket modules advanced by
5 mm to protect port region
65
Shaping Calculations
FW Blanket
  • Considerable efforts now being expended on FW
    panel shape optimisation
  • Semi-analytic work (P. C. Stangeby see PSI
    Conf. 2008)
  • Sophisticated numerical field line tracing (R.
    Mitteau)
  • Preliminary benchmark of the two methods has been
    successful
  • Only toroidal shaping required on LFS to protect
    central hole (curvature of VV provides
    self-shielding for poloidal edges)
  • Toroidal poloidal shaping required on HFS
  • Design study for upper dump region underway

Port
R. Mitteau
66
Technology
FW Blanket
Chen et al., IAEA 2008
Geometry Max Heat Flux(MWm-2) Tsurf _at_ at max Heat Flux Overageing of Cu (400C) Fatigue life (3x105 cycles)
SS tube (1mm) in Cu 1.8 (8kgs-1) 700C 1.3 MWm-2 1 MWm-2
SS tube (0.5mm) in Cu 1.8 (8kgs-1) 590C 2 MWm-2 2 MWm-2
Cu tube in Cu 1.8 (8kgs-1)3 (12kgs-1) 530C(700C _at_ 2.8 MWm-2) 2.5 MWm-2 3.0 MWm-2
Hypervapotron 8.0 (8kgs-1) 700C _at_ 4.5 MWm-2 8 MWm-2
67
Conclusions
  • Divertor Design is completed
  • Extensive integration work carried out on the
    interfacing systems
  • Extensive RD has been carried out by EU, JA, RF
    DAs
  • All concerned DAs have demonstrated the technical
    capability to manufacture divertor components
    with adequate heat flux performance
  • Divertor design process has progressed over the
    years with constant consideration for the
    maintenance process and close interaction with RH
    equipment / process developers. However, RH
    remains a challenge.
  • First Wall and Shield Blanket design has been
    modified with respect to the 2001 baseline
  • A First Wall shape is being developed which both
    shadows leading edges, and provides for a
    generous RH access aperture
  • Different design solutions may be required
    depending from the toroidal and poloidal position
    of the modules
  • High heat flux technology is required in some
    regions, but removes the need for start-up
    limiters
  • The complex procurement sharing adds a further
    challenge
Write a Comment
User Comments (0)
About PowerShow.com