Title: SGS Industrial Services
1Dealing with the Risk in Onshore and Offshore
Wind Farm Projects
2Introduction to SGS Group
- Founded in 1878 in Rouen, France
- SGS is the global leader in verification,
testing, inspection and certification services - Public listed Swiss company CHF 4,8 bn
revenues in 2008 - Unrivalled geographic network
- 55,000 employees
- More than 1,000 offices and laboratories
- Present in 140 countries
- Complete independence, transparency and integrity
are the core values of the SGS Group
3Our Business Segments
Consumer Testing Services
Government Institution Services
Oil, Gas Chemical Services
Minerals Services
Agricultural Services
Industrial Services
Environmental Services
Automotive Services
Systems and Services Certification
Life Science Services
4The Wind Energy Market SGS Services
- A Global Market
- Elements related to Sustainable Energy Services
- Other SGS elements and services include
- SGS Climate Change Projects and Services
- Other Renewable Energy Sources e.g.
- Solar Energy and Biomass
5Global Wind Power Investment 2006-2010
6 Wind Turbines and Wind Farms Quality Issues
7Main Causes of damages on Wind Turbines and
Foundations
- Poor material quality
- Wrong choice of materials
- Specifications not followed
- Manufacturing faults
- Improper mounting / fastening
- Improper Service and Maintenance
- Unforeseen Loads / Site Specific Loads
- Wear
- Lightening / overvoltage
8SGS Wind Energy Global Network
- SGS Wind Energy Technical Competence Centre
located in Hamburg, Germany - SGS-TÜV Saarland provides testing, inspection and
monitoring services for wind turbines in Germany - SGS Wind Energy Inspection and NDT services
provide from SGS offices in - Germany,Poland, Spain, Denmark, Sweden, Norway,
Portugal, France, Italy, Benelux, UK, Ireland,
Belgium, the Netherlands, Austria, US, China,
Taiwan, Egypt and India - Onshore and Offshore Wind Farm Site Specific
Project Certification including Manufacturing
Survey, NDT and Inspections. Expediting
Management. - Technical Due Diligence for new and existing wind
farms
9PROJECT LIFE CYCLE SERVICES
10Manufacturing- and Installation Survey (1/2)
- Manufacturing Surveys performed as an integrated
part of Project Certification - Approval of Manufacturers based on quality
management system audits and product
Manufacturing Survey Arrangements (MSA) - Verification of Project Quality Plan
- Check that structures are being built and
installed in accordance with Drawings,
Specifications, Certificates, Manuals, Method
Statements etc. Verification of As Built
documentation.
11Manufacturing- and Installation Survey (2/2)
- Check of material certificates, welders
qualifications, NDT, procedures and findings etc. - Assembly survey
- Construction Site Supervision
- Marine verification and warranty survey of load
out, sea transportation and installation
12Commisioning Survey
- Survey includes check procedures for initial
energization of the Wind - Turbine electrical system and for Wind Turbine
testing after installation, to - confirm proper, safe and functional operation of
all devices, controls and - apparatus safe start-up, e.g
- Safe start-up
- Safe shutdown
- Safe emergency shutdown
- Safe shutdown from over-speed or representative
simulation thereof - Functional test of aerodynamic and mechanical
braking systems (shall work independently as
redundancy in the safety system is required) - Functional test of protection system.
- Proper records shall be kept describing testing,
commissioning, control parameters and results.
13Technical Due Diligence of Wind Farms
- An evaluation of assumptions, provisions and
- conclusions compared to the issued certificates
- Wind turbulence intensity including wake aspects
- Extreme gust wind speed and extreme wind
direction change - Wind shear and slope effects
- Mean wind speed, wind speed distribution and wind
rose. - Temperature and air density
- Expected net annual energy production (compared
with actual operation data) and energy losses - B) A review of all technical aspects of the
assumptions and - inputs regarding to their appropriateness
and - completeness.
14Wind Turbines Important Parameters
- Important parameters when selecting the right
turbine. - Cost price
- Service and maintenance Costs
- Track records
- Track records on critical components
- Turbine availability (power warranties)
- Type certificate, Project Certification
- Spare parts and delivery time
- Noise
- Buyer obligations
- Turbine suitability for site (Enviromental
impact) - Reliability
- Turbine delivery !
15Impact of Failures on each Component at each
Phase of the Project Life Cycle
16Cost Breakdown of Failure During The Life Time of
a Wind Turbine
- ISET Report Zuverlässigkeit von
Windenergieanlagen 2007 and http//reisi.iset.uni
-kassel.de/ - http//www.eia.doe.gov
17Average Cost of Wind Turbine Components
- Gearbox US270,000
- Set of Rotor Blades US400,000
- Transformer US80,000
- Generator US100,000
- In total per turbine US1,800,000 (replacement
of all major components for the wind turbine size
of 1.669 MW)
- Magazine "Wind Directions - January/February
2007"
18Benefits of SGS Wind Energy Services - 1
- SGS Wind Energy services can minimise the risks
- That stem from environmental, planning,
technical, contractual, commercial, construction,
operational, and energy yield aspects of the
project - SGS Wind Energy Services can help to mitigate the
risks at each phase of the life cycle of a wind
farm - Risk mitigation at each phase can minimise the
potential failures at the consecutive phases - Phases are
- Design verification and site assessment stage
- Site specific design verification stage for wind
turbine and foundation - Manufacturing stage
- Installation stage
- Commissioning stage
- Operations/in-service stage
19Benefits of SGS Wind Energy Services - 2
- SGS input in better project planning, and
verification of site assessment and design can
help to enhance the confidence and interest in
the project for the financial community, which
may facilitate better funding terms - SGS services help to assess the risks, which are
not specifically addressed by the traditional
risk assessment models employed by the financiers - Regular inspections conducted by SGS on
operational wind farms can increase the
availability of the wind turbines - SGS independent technical due diligence services
can - Boost the robustness of the wind farm project
- Attract better financing and insurance deals for
the new wind farm projects - Contribute to higher price when the wind farm is
sold - Improve owners balance sheet when the company is
targeted for acquisition
20Benefits of SGS Wind Energy Services - 3
- SGS services help to manage the wind farm
project risks that may facilitate to - Improve the owners financing capabilities
- Reduce the insurance premiums
- Increase the owners internal rate of return on
investment - Minimise the risk of injuries and fatalities
during the manufacturing, transportation,
installation, commissioning, and operation stages
of the wind farm projects - Improve the owners reputation
- SGSs independent design verification,
inspection, and testing services can overall
improve the financial viability of the wind farm
project by - Mitigating the cost attached to the relevant
risks at each phase of the project - Reducing the maintenance cost, and subsequently
improving the cash flow during the operations
21Conclusion
- Wind farm owner have the burden of additional
cost such as component cost after the expiry of
warranty period - By utilising SGS Wind Energy services throughout
the six project phases, the project owners may
save - Up to 624 days of down time inclusive of
mobilisation time during the life time of each
turbine - Up to US636,000 during the life time of each
wind turbine by minimising the total down time
duration - Combined the cost of brad new grearbox with one
set of blades, the project owner can save up to
US1,300,000 per wind turbine -
22The Report Traffic lights, graph and diagnosis
23The report Overview of all data
24SGS Project(s) Illustration
- Period September- December, 2005
- Project Waardpolder Onshore Wind turbine farm,
the NETHERLANDS - Services Technical Due Diligence of existing
Wind Farm (19 Nedwind N31/3 onshore wind
turbines) - Client ING Bank
- Document Review and Site Inspections
25SGS Project(s) Illustration
- Period September 2005 -
- Project Waardpolder Onshore Wind turbine farm,
the NETHERLANDS - Services Technical Due Diligence of existing
Wind Farm (19 Nedwind N31/3 onshore wind
turbines) - Client ING Bank
- Steel construction coating application Rheden
Steel, Belgium - Document Review and Site Inspections
26SGS Project(s) Illustration
- Period September 2005
- Project Gniezdzewo, Municipality of Puck,
Pomorskie, POLAND - Services Owners Representative for new Wind
Farm Project (11 Gamesa G80 onshore wind
turbines) - Client Polish Energy Partners
- Project Services (Tender Support, Document
Review, QA/QC, Inspections, Project Supervision)
27SGS Project(s) Illustration
- Period December 2005 -
- Project Changkong project in the western part of
Taiwan - Services Inspection of 23 Wind Turbines Vestas
V80 in Denmark and 23 Towers in Taiwan for the
above project - Client Tai Power Corporation Ltd.
- Project Services Inspections
28SGS Project(s) Illustration
- Period Januar 2003 -
- Project Several Onshore Wind Farms in Portugal
- Services Technical Control and Construction
Supervision - Client Enersis Group
- Project Services Inspections
29SGS Project(s) Illustration
- Period November 2005 -
- Project Kriegers Flak Offshore Wind Farm, Baltic
Sea - Services Project Certification for Kriegers
Flak Offshore Wind Farm Project, 600 MW - Client Vattenfall
- Project Certification Services for all Phases
(Tender Support, Document Review, QA/QC,
Manufactruring Survey, Installation, Commisioning
etc)
30SGS Project(s) Illustration
- Period April 2006-
- Project Q7 Offshore Wind Farm 120 MW/60
installations. Inspections performed in the
Netherlands, Belgium, Poland and Denmark - Services Design Verification, QA/QC Management,
Verification of Electrical Systems, Inspections
and NDT of Structural Steel (Primary and
Secondary), Coating and Corrosion Protection
Inspections - Client Van Oord
31SGS Project(s) Illustration
- Period April 2006-December 2006
- Project Elsams Burbo Offshore Wind Farm 100 MW,
UK - Services Coating and Corrosion Protection
Inspections of 25 Offshore Wind Turbine Mono-Pile
Foundations - Client Smulders
32SGS Project(s) Illustration
- Period July 2004 December 2004
- Project Horns Rev, Denmark
- Services Failure analysis of coating problems
on 80 offshore wind turbine foundations. - Main Contractor Elsam Engineering
- Site visits laboratory analysis
33SGS Project(s) Illustration
- Period July 2004 January 2005
- Project Arklow Bank Offshore Wind turbine farm,
Ireland - Services Failure analysis of coating problem on
7 offshore wind turbine foundations - Main Contractor General Electric Wind
- Site visits laboratory analysis (in combination
with US coating lab)
34SGS Project(s) Illustration
- Period May 2006 -
- Services Expediting, Auditing Inspections and
NDT on behalf of Vestas, Nordex Energy and Gamesa
Eolica in China, Spain, Germany, Denmark and
Portugal - Clients Vestas (DK), Gamesa (Spain) and Nordex
Energy (Germany) - Services Expediting Inspections for wind
turbine components and wind farm projects. NDT of
Towers, Machine Frames and Nacelles. Inspection
of Blades.Auditing of wind turbine component
sub-suppliers.
35SGS Project(s) Illustration
- Period February 2008 -
- Services In-service NDT inspections (by
ultrasonic examination) of 160 rotor blades
(potentially up to 1018) globally - Client Gamesa
- Countries currently Japan, Spain and the US
- In addition opportunity for also NDT inspections
in the work shops in manufacturing phase
36SGS Project(s) Illustration
- Period May 2006 -
- Global Frame Agreement
- Services Expediting inspections on behalf of
Nordex Energy - Client Nordex Energy
- Services Expediting Management and Inspections
for wind turbine components and wind farm
projects - Countries currently Germany, Denmark, Sweden,
Austria, Czech, Switzerland, Hungary and China
37Existing and Potential Projects - USA
- Period November 2008 -
- Project Agriwind Wind Farms, USA
- Services Failure Analyses of Wind Turbine Blades
- Client
- John Deere Wind Energy
38Existing and Potential Projects - USA
- Period July 2008 -
- Project MT Home Wind Farm, USA
- Services In-Service inspections, OSHA
compliance, Commissioning Inspection - Client
- John Deere Wind Energy
39Existing and Potential Projects - USA
- Period July 2008 -
- Project Buffalo Bear and Elkhorn Ridge wind
farms, USA - Services Construction supervision, walk-down
inspections and commissioning inspections - Client
- Edison Mission Energy
40Existing and Potential Projects - Europe
- Period October 2008-
- Project Bligh Bank Offshore Wind Farm, wind
turbine - Services Technical Consultancy of the Vestas V90
Wind Turbine, QA/QC Inspections during
manufacturing, installation and commissioning of
wind turbines - Client
- Belwind Offshore Energy
41Existing and Potential Projects - Europe
- Period October 2008-
- Project Bligh Bank Offshore Wind Farm,
sub-structures - Services Consultancy in developing of the QA/QC
manual, QA/QC inspections during manufacturing,
installation and commissioing of sub-structures - Client
- Van Oord
42Existing and Potential Projects - Europe
- Period February 2008-
- Project In-Service Blade Inspections, Globally
- Services In-Service blade-inspections using
UT-application
43Existing and Potential Projects - Europe
- Period November 2008-
- Project Albatros Offshore Wind Farm (80 Tubines)
- Services Project Certification (started with
Phase I) - Client
- Evelop Germany/LCO Nature
44Existing and Potential Projects - Europe
- Period November 2008 -
- Project Cote dAlbatre Offshore wind Farm (21
Turbines) - Services Project Certification (started with
Phase III, Manufacturing Survey of Tripod and
Tower) - Client
- PROKON Nord
45Existing and Potential Projects - Europe
- Period September 2008 -
- Project Gode Wind II Offshore Wind farm (80
Turbines) - Services Project Certification (started with
Phase I) and Development of a Project Fact Book - Client
- Plambeck Neue Energien
46Existing and Potential Projects - Europe
- Period September 2008 -
- Project Borkum West II Offshore wind farm (80
Turbines) - Services Project Certification (started with
phase III) - Client
- PROKON Nord
47Existing and Potential Projects - Europe
- Period September 2008 -
- Project MEG I Offshore wind farm (80 Turbines)
- Services Project Certification (started with
Phase III) - Client
- PROKON Nord
48Existing and Potential Projects - Asia
- Period October 2008 -
- Project Wind Turbine Blade manufacturing survey,
Tianjin, China - Services Manufacturing Survey and Monitoring of
Rotor Blade manufacturer, Process Quality Audit - Client
- REpower
49Existing and Potential Projects - Asia
- Period October 2008 -
- Project Wind Turbine Tower manufacturing survey,
Korea - Services Manufacturing Survey and Monitoring of
tower manufacturer, Process Quality Audit - Client
- REpower
50SGS Industrial Services Global Competence
Centre Renewable Energy Raboisen 28 D- 20095
Hamburg t 49 40 30 101 236 internet
www.sgs.com/wind email wind_at_sgs.com