Title: Consumption-based Planning


1
Consumption-based Planning
2
Material Planning
Material Planning (MRP Procedures)
SAP Terms
Independent Demand (Consumption-based Planning)
MRP-Material Requirements Planning
Reorder point planning
Forecast-based planning
Time-phased planning
SAP Exercise
Manual reorder point
Automatic reorder point
3
Planning Process
Can be automatic
4
Planning Process
  • Planned Order
  • Recommendation by the MRP planning process of
    quantity and timing of production or purchase
    order
  • Production Order
  • Actual order given to shop floor to commence
    production. May be electronic or paper. Can
    include production details (routing, quality
    requirements, drawings, instructions, etc.)

5
Planning Process
  • Purchase Requisition
  • Request to purchasing to create purchase order
  • Purchase Order
  • Request to vendor to supply materials
  • Schedule Line
  • Direct request to vendor for materials, covered
    by scheduling agreement (blanket PO)

6
Reorder Point Processing
Lot Size
Reorder Point
Safety Stock
Time
Replenishment Lead Time
7
Reorder Point Processing
  • When the inventory level for a product that is
    planned using consumption-based planning reaches
    the ROP, an order for the material is NOT created
    automatically
  • Consumption-based planning uses the Material
    Requirements Planning (MRP) planning process to
    create purchase orders
  • The MRP planning process is typically run
    overnight on a daily basis
  • Historically, might have used weekly runs
  • Time until MRP planning run is executed should be
    considered in ROP calculation (daily runs, add 1
    day to lead time)

8
Forward Scheduling forExternal Procurement
9
MRP Planning Process
  • For a company with thousands of materials to
    plan, the computing resources needed to calculate
    material plans can be significant
  • To make sure that
  • Only those calculations that are necessary are
    performed
  • Only on materials that need planning
  • Two filters are used
  • Planning Run Type
  • Planning Horizon

10
Planning Run Types
  • NETCH Net change in the total horizon
  • In the MRP Planning Process, materials are
    planned if there have been any
  • Changes in material stocks (receipts, issues)
  • Addition of purchase requisitions, purchase
    orders, planned orders, dependent requirements
  • Changes in Material Master Data (Lot Size, ROP,
    etc.)

11
Planning Run Types
  • NETPL Net change in the planning horizon
  • Same at NETCH, EXCEPT
  • Changes must occur within the planning horizon
  • Planning horizon keeps MRP planning process from
    making plans for future periods that
  • Do not impact current operations
  • Will be made irrelevant through the dynamics of
    business

12
Planning Run Types
Order/ Requisition
Requirement
Time
13
Plant Parameters Planning Horizon
14
Planning Run Types
  • NETUPL Regenerative Planning
  • Plans all materials for total planning horizon
  • Good idea to run this option regularly (e.g.
    every weekend), even though it is more resource
    intensive
  • Customizing changes dont trigger planning under
    NETCH or NETPL
  • Time passage problem with NETPL

15
NETPL Potential Problem
Planning Horizon
NETPL
Today
Passage of time is not an event Would require
monitoring to detect
Planning Horizon
NETPL
Today
Solution Run NETUPL
16
Planning File
  • A Planning File entry exists for each material
  • Keeps track of changes that would require
    material to be planned under NETCH or NETPL
    options
  • MRP Planning process looks at planning file
    entries for each material to see if it should be
    planned

17
Planning File
Low-level Code
NETCH Indicator
NETPL Indicator
18
Planning Run Options
Planning Run Type NETCH NETPL NETUPL
Create Purchase Req 1 Purchase
Requisitions 2 Purchase Requisitions in
Opening Period 3 Planned Orders
Defined by Schedule Margin Key Usu. does not
impact consumption-based planning
19
Planning Run Options
Create MRP List 1 Yes 2 Depending on
Exception Messages 3 No
Planning mode Determines how system deals
with previous plans (planned order, purchase
requisitions)
Scheduling Determines level of detail in
schedule calculation for production orders
Display results before they are saved Lets
planner make changes before the results are
saved
20
Planning Run Options
  • With consumption-based planning in practice
  • You would not run MRP for a single material, but
    do it as part of a group (MRP Area based on
    storage location)
  • You would have it scheduled to run automatically
  • You would have it either
  • Create purchase requisitions automatically
  • Create schedule lines

21
Net Requirements Calculation
How does safety stock figure into this process?
22
Exercise Material Master Data
MRP Type VB sets consumption-based
planning Reorder point Lot size FX is fixed
lot size Fixed lot size Quantity in an order
23
Exercise Material Master Data
Plnd delivery time Vendor part of lead
time SchedMargin key Sets opening period,
among other things Safety stock Desired
stock level when replenishment order arrives
How does it work in SAP R/3?
24
Exercise Stock/Requirements List
Stock/Requirements List Your one-stop
shopping location for all things material
25
Exercise MRP Planning Run
MRP control parameters Planning run
parameters discussed previously
26
Exercise MRP Planning Run
Planning run results displayed Purchase
requisition created
27
Exercise Purchase Requisition
Can easily create purchase order from S/List
28
Exercise Purchase Order
Purchase order screen is where the requisition is
converted to a purchase order Vendors
selected Price determined
29
Exercise Receive Purchase Order
Goods Receipt Screen In practice, could just
be a bar-code scan Links receipt to purchase
order Tell SAP R/3 system where goods have
been stored
30
Exercise Goods Issue
Goods Issue Screen When goods are issued,
something has to absorb costs (project,
production order, cost center) In this
case, we will charge costs to the warehouse
cost center (P020) What is the downside to
charging to a cost center?