Title: Folie 1
1Hilti Mining
Project Update March 2009
2Key Application Areas
Mining Australia
OneStep Roadway Development Applications
OneStep Special Applications
Mining Tools
Belt Splicing
Anchor Systems
Distance Measuring
Infrastructure Fixing
Hand Held Drilling
3OneStep Roadway Development Roof Bolts
Mine
Application
- 9000 of 1.8m roof bolts in MG4
Value proposition / Achievements
- Very high performance reliability gt99 good
quality installationsgt98 resin visibility - Highly stable gate roads
- Average bolt installation time reduction of 61s
(44)(78s target overachieved with lt70s) - Productivity gains gt18 (MPOH)
- Highly satisfied operators
- Static Roof Conditions when longwall passed by
Roadway development MG4
HOS installed
4OneStep Roadway Development Roof Bolts
Mine
Application
Bolt Storage
- 10,000 of 2.1m roof bolts to be installed with a
Joy12CM12 Sandvik Drill Rigs
Current Activities
Test Bolts
- Project start April 09
- Miner and Equipment Fitted and compliant to
standards - Value Proposition Targets are to achieve gt 5MPOH
- Geotech evaluation ongoing
- Ergonomic process study ongoing
- Total System Evaluation to commence and be
measured during the project
Roadway development MG4
Miner Fit out
HOS installed
5OneStep Roadway Development Rib Bolts
Mine
Current Activities
- 6,000 bolts installed up to Feb 09
- Bucyrus 30MB3 to commence installing OneSteps in
March 09 - Value Proposition Analysis Ongoing
- Geotech Evaluation Ongoing
- Roof Trials March 09
- Drill Steel Blocking Prevention System
Application
- 20,000 1.5m Bolts to be installed in ribs by a
Sandvik 6-Shooter Bucyrus 30MB3 Miner
Value proposition / Achievements
- Very high performance reliability gt96 good
quality installations100 load test successful - Average bolt installation times around 90s (70s
best installation time) - High quality rib support(zero to minimal rib
movement measured) - Highly satisfied operators
6OneStep Special Applications Longwall Bolt Ups
Mine
Application
- Longwall Face Bolt Up 2.1m bolts
- OneStep method used twice successfully at Twenty
Mile - USA
Sandvik RFB with Hilti system mounted
Current Activities
- Project start Feb 25th 2009
- Sandvik RFB fitted with Hilti System
- Value Proposition Targets are to be safer and
quicker than current method - Total System Evaluation to commence and be
measured during the project
Fletcher Face Bolter with Hilti system
7Special Projects Examples Roadway Repair
Current Activities
Mine
- Pillar Stabilization in Tail Gate - 2.5m bolts
Application
Longwall Bolts
- Longwall Face Bolt Up 1.8m bolts
- Spiling 2.5m bolts
- Pillar Stabilization - 2.5m bolts
Sandvik RFB with Hilti system mounted
Value proposition / Achievements
Longwall Bolts
- Safe bolt installation no injuries(operator in
safe area) - High productivityon all applications
- High quality coal face and rib support
- Highly satisfied operators
Spiling
Rib Repair
8Future Projects 2009
Roadway Development Projects
- QLD 2 Roof and 1 Rib
- NSW 1 Roof and 1 Roof and Rib
Special Application Projects
- QLD 2 Longwall Take offs
- NSW 4 Longwall Take offs
- NSW 2 Roadway Repairs
Mining Tools
- Introduction of Hilti Hand Held Mining Tools