Key Performance Indicators V3.0 - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Key Performance Indicators V3.0

Description:

Departmental Costs 3.2 Measurement & Capture The sources of data for this KPI are likely to be your resource plan and business case. A KPI calculator has been ... – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 13
Provided by: AlexH92
Category:

less

Transcript and Presenter's Notes

Title: Key Performance Indicators V3.0


1
Key Performance IndicatorsV3.0
2
Content
  • Introduction
  • 1.1 Background/Overview
  • 1.2 Purpose, Objectives and Deliverables
  • Procurement Turnaround Times
  • 2.1 Definition
  • 2.2 Measurement Capture
  • 2.3 Comparison
  • Departmental Costs
  • 3.1 Definition
  • 3.2 Measurement Capture
  • 3.3 Comparison
  • Supplier Bid Costs
  • 4.1 Definition
  • 4.2 Measurement Capture
  • 4.3 Comparison
  • Resource Capability
  • 5.1 Definition
  • 5.2 Measurement Capture
  • 5.3 Comparison

3
1.1 Background/Overview
Context On the 21 November 2011 the Minister for
the Cabinet Office announced that Government
would Make it 40 per cent faster to do business
with Government and that from January 2012 all
but the most complex procurement processes will
be completed within 120 days. Key Performance
Indicators This KPI pack is intended to give you
guidance on four specific KPIs procurement
turnaround times, departmental costs, supplier
bid costs and resource capability. Why use this
pack? These KPIs are relevant to understanding
the impact of the application of lean on the
procurement process, contributing to continuous
improvement of the lean sourcing process and
demonstrating progress in changing the way the
government does business. Whilst there is no
plan to collect and report this data centrally
the context of Government policy particularly in
reducing procurement turnaround times is likely
to result in you being asked questions from
inside and outside your department about your
performance. Using these KPIs and potentially
feeding them into your departmental performance
measurement and reporting could therefore be
helpful. When using this pack you should apply
your professional judgement to decide whether the
KPI Calculator can usefully be deployed and/or
customised to meet your needs. Related
Documents Visual Management Project Performance
Hub Guidance SOP 2.2 Create a project performance
hub KPI Calculator
4
1.2 Purpose, Objectives Deliverables
Purpose
  • To measure the impact of applying the Lean
    Sourcing standard solution on
  • Procurement turnaround times
  • Departmental costs
  • Supplier bid costs
  • Resource capability

Objectives
  • To understand the impact of the application of
    lean on the procurement process
  • To contribute to continuous improvement of the
    lean sourcing process
  • To demonstrate progress in changing the way the
    government does business

Deliverables
  • Data describing
  • The number of working days from the publication
    of a contract notice to the contract award date
    to enable you to demonstrate a reduction in
    turnaround times and/or the impact of external
    factors (e.g. approvals) on your turnaround
    times.
  • The cost to the department of running the
    procurement based on the above timescale broken
    down by staff costs, consultancy costs, internal
    legal costs, Tsol costs, external legal costs and
    other costs to help you ensure resources are
    deployed effectively.
  • Supplier bid costs to enable you to demonstrate
    progress in changing the way the government does
    business.
  • Whether your team has the required skills and
    expertise to run the procurement and if not, to
    identify what impact this had on the turnaround
    times and costs and to use this as evidence for
    additional resources for future procurements.

5
2. Procurement Turnaround Times
2.1 Definition
  • What is it?
  • The total number of consecutive working days from
    a defined start date to a defined end date
    including the following breakdown as a minimum
  • Working days from contract notice publication
    date to contract award decision date (source
    Tenders Electronic Daily)
  • Note the Minister for the Cabinet Office's
    target of 120 days for all but the most complex
    procurement processes is from contract notice
    publication to contract award decision date
    however the scope of the lean sourcing process is
    wider and to understand the impact of, for
    example, approval processes like the moratorium,
    internal approvals, analysing business needs,
    tender evaluation and so on you might want to
    consider tracking from a defined start date like,
    strategic outline business case approval or
    publication of a PIN through to formal contract
    signature.
  • Why measure it?
  • Departments and suppliers have articulated that
    the current process takes too long and is too
    costly. The lean sourcing process has been
    designed to streamline the process and maximise
    value added activity thus reducing the timescales.

6
2. Procurement Turnaround Times
2.2 Measurement Capture
1
1
2
  • The source of data for this KPI is likely to be
    your project plan.
  • A KPI calculator has been developed for use if
    required.
  • How to use the KPI calculator
  • White cells indicate input cells and grey cells
    indicate cells that will auto calculate.
  • Use your baseline project plan to complete
    planned dates and the final plan to complete
    actual dates.
  • Enter as many of the planned and actual dates as
    possible.
  • The summary table will give you your procurement
    turnaround times in working days.

7
2. Procurement Turnaround Times
2.3 Comparison
  • You can compare the data you have captured for
    procurement turnaround times to a number of
    sources
  • The ambition for completion of all but the most
    complex procurements in 120 working days.
  • Current average baseline performance in 2011
    derived from a survey of Tenders Electronic Daily
    based on the following criteria
  • UK Central Government (including agencies)
  • Contracts awarded between 01/01/2011 03/08/2011
  • Average time taken in working days from
    publication of contract notice to contract award
    decision date per procedure
  • Competitive dialogue 439 days
  • Restricted 202 days
  • Open 111 days
  • An average of your own departmental projects over
    a specific time period, for example average time
    taken per procedure from publication of contract
    notice to contract award decision for
    procurements run during 2011.
  • A baseline project i.e. comparison to a similar
    project that you have run previously where you
    have not used the lean sourcing standard solution.

8
3. Departmental Costs
3.1 Definition
  • What is it?
  • The total cost of staff deployed on the
    procurement during a defined timescale. This
    should include
  • Commercial staff
  • Programme management staff
  • Subject matter experts used for evaluation,
    requirement drafting etc
  • Admin staff
  • Staff costs should be calculated using annual
    capitation rates and daily rates (annual
    capitation / number of working days) .
  • The total cost of legal advice for the
    procurement project, this should include
  • In house legal costs
  • Tsol legal costs
  • External legal costs
  • The total cost of external consultancy for the
    procurement project, this should include
  • Consultancy
  • Interim staff substitution
  • Temporary staff (e.g. used to back fill subject
    matter experts)
  • Other costs associated with running the
    procurement including

9
3. Departmental Costs
  • Why measure it?
  • To provide internal and external assurance that
    the lean sourcing process costs less to run than
    existing practices and that internal and external
    resources are deployed effectively.

3.2 Measurement Capture
1
1
1
2
4
3
5
4
  • The sources of data for this KPI are likely to be
    your resource plan and business case.
  • A KPI calculator has been developed for use if
    required.
  • How to use the KPI calculator
  • White cells indicate input cells and grey cells
    indicate cells that will auto calculate.
  • For staff costs insert team members (either by
    name or anonymous reference number), grades (e.g.
    SCS, Grade 7) and an annual capitation rate
    (source finance).
  • The calculator will identify a daily rate based
    on the number of working days in the year (e.g.
    251 for 2011, 252 for 2012, 253 for 2013).
  • Enter the planned number of working days for the
    team member. So if they are full time enter 251,
    or allocated to the team 50 would be 125.5, or
    evaluating for four weeks would be 20 and so on.
  • This will give you a cost per team member and a
    total cost.
  • Do the same for actual days worked by the team
    member.

10
3. Departmental Costs
6
7
6
6
  1. For legal, consultancy and other costs enter your
    planned and actual.
  • The summary table will then give you planned and
    actual totals for
  • your departmental costs.

3.3 Comparison
  • The cost baseline should be your budget for the
    project
  • Staff costs this may be articulated in the form
    of headcount resource allocated to the
    procurement.
  • Legal costs budget
  • Consultancy budget
  • Venue hire
  • TS
  • This will enable you to identify actual cost
    versus budget at the end of the procurement
    exercise see summary table above (7).

11
4. Supplier Bid Costs
4.1 Definition
  • What is it?
  • Supplier bid costs are the costs incurred by
    suppliers to develop a bid and to participate in
    the procurement process.
  • Suppliers should be asked to articulate their bid
    costs as
  • The total cost of participating in the
    procurement exercise.
  • Why measure it?
  • Suppliers have articulated that the current
    process takes too long and is too costly
    therefore you may wish to capture feedback at the
    end of the process to understand whether
    suppliers have realised a benefit from the
    implementation of the lean sourcing standard
    solution and to collect anecdotal evidence of
    progress in changing the way the government does
    business.

4.2 Measurement Capture
  • You should indicate to suppliers your intention
    of capturing feedback from them on the cost of
    participating in the procurement.
  • As suppliers are deselected or deselect
    themselves and you conduct a feedback debrief
    session ask them to write to you and identify the
    following
  • Cost of participating in this specific exercise
  • Either average cost of bidding for similar
    government contracts or the cost of bidding for a
    specific similar government contract
  • Either average cost of bidding for similar
    private sector contracts or the cost of bidding
    for a specific similar private sector contract
  • In practice there is no way you can verify this
    data therefore you should view it as useful
    indication rather than a robust data source.

4.3 Comparison
  • There is no robust baseline data on supplier bid
    costs and therefore you should ask suppliers to
    provide a comparison.

12
5. Resource Capability
5.1 Definition
  • What is it?
  • Resource capability is the measure of whether
    your team has the required skills and expertise
    to run the procurement.
  • Why measure it?
  • A key aspect of the lean sourcing standard
    solution is mobilisation being able to get the
    right skills and capability in the right numbers
    to manage the procurement process. This also
    requires departments to reduce reliance on
    external consultants.
  • You will be able to identify whether you had the
    necessary skills and expertise and if not, to a)
    identify what impact this had on the turnaround
    times and costs and b) use this as evidence for
    additional resources for future procurements.

5.2 Measurement Capture
  • Use the skills matrix in the standard document
    library.
  • Refer to the Performance Hub visual management
    pack section 3.3 which details how to use the
    skills matrix to identify skills and capability
    required versus skills and capability available.
  • In addition refer to SOP 2.3 Complete team skills
    assurance.
  • Refer to Departmental Costs KPI to track the use
    of external resources planned versus actual.
  • Unplanned use of external resources in
    particular consultants may indicate capability
    shortfalls within the team that need to be
    addressed.

5.3 Comparison
  • You will be able to compare the skills and
    expertise you needed to the skills and expertise
    you were allocated.
Write a Comment
User Comments (0)
About PowerShow.com