Title: PAVEMENT REHABILITATION
1PAVEMENT REHABILITATION RESONANT RUBBLIZING
2 What is Rubblizing?
The Process of Fracturing Pavement of Portland
Cement Concrete into Angular Pieces for Direct
Overlay
3(No Transcript)
4Application of Recycling the Concrete Pavement
(Rubblizing)
Environmentally Friendly Construction
5Reflection Evolution of the Deterioration
PSI
Quality of the Road
Number of Years
6Rehabilition of Concrete Pavement
PSI
Quality of the Road
Number of Years
7Rehabilition of Concrete Pavement
Rubblizing
8Rehabilition of Concrete Pavement
Rubblizing
9Rehabilition of Concrete Pavement
Rubblizing
10Structural Design Correlations
1 to 8
11 DESCRIPTION OF TECHNICAL RUBBLIZING
12Description of Rubblizing Equipment
Computer Controls
Weight
Motor
Resonant Beam
Flotation Tires
Pedestal / Shoe
13Description of Resonant Beam
Weight
Vibration Technology
Frequency 44 Hz Amplitude 1.905 cm
14Description of Resonant Beam
Weight
Vibration Technology
Frequency 44 Hz Amplitude 1.905 cm
15Description of Resonant Beam
Weight
Vibration Technology
Frequency 44 Hz Amplitude 1.905 cm
16Operational Data of Equipment
- Strikes PCC 44 Times per Second.
- 2,000 lbs. of Pressure Per Strike.
- Beam Weighs 4080 kg.
- Beam Raises 1.905 cm Per Strike.
- Machine Speed at Approx. 6-8 km/hr.
- Breaking Area is around 25 cm wide.
- Maximum of 4,000 to 5,000 square meters of
rubblized concrete per day with a crew of two
Resonant Machines.
17 STRUCTURAL DESIGN
18Structural Design Methods
- AASHTO Procedure Design (SN)
- Asphalt Institute Series Manuals (MS) -17
- NAPA Series Information (IS) 117
- Airfield Asphalt Pavement Technology Program -
AAPTP
19Structural Design State Studies
Alabama
- Over 20 Studies from Multiple States support that
rubblizing provides - Long life for surfaces 22 years
- Smooth driving conditions
- Rubblization eliminates reflective cracking and
dramatically reduces surface defects
Michigan
20Structural Design Evaluation
- Pictured is pavement after years of use and
deterioration. - Expert analysis is required to determine the
cause of the failure of the pavement.
- If the damage does not arise from the Subgrade or
SubBase, the pavement is a candidate for
Rubblization. -
- If there is a problem with the Subgrade,
Rubblization will not eliminate the issue.
21Structural Design Drainage
- A Proper Drainage System should be Installed or
Repaired prior to Rubblizing the pavement. - Varying Methods of Drainage can be used depending
on the Site.
22Structural Design Drainage
Shoulder Area
Relief Cut _at_ 9-12 m.
Permeable Zone
5 cm dense-graded
Rubblized PCC
10 cm open-graded
Filter Fabric
57 Stone
Base Course
3 Slope Outlet
Subgrade
23Structural Design Scope
The Modulus of the Rubblized Concrete depends on
the Thickness, Subbase and Subgrade. Typically
Rubblized Concrete is 2.5 Times Stronger than any
Granular Material.
24Coefficient Structure (ai) vs. Modulus (Mr)
AASHTO
Structural Design Coorelations
25 CONSTRUCTION PROCESS
26Rubblizing Process
- Three Stages of Construction
- Rubblizing
- Rolling
- Asphalt Overlay
27Prior to Rubblizing Process
- Repair or Replace the Drainage System
- Remove any Asphalt Overlay Currently in Place
28Resonant Rubblizing
- Breaking area between 15.24 and 30.48 cm Wide
- Ideal Distance Per Run - One Kilometer/ One Lane
Wide - Speed of Resonant Machine 6 to 8 km/hr
29Test Pit Confirm Specification and Debonding
30Wright Patterson
31Rolling
- 10 Ton High Frequency, Low Amplitude Steel Drum
Roller (3 Passes) - Only Equipment Necessary After Rubblization
- Not Recommended to Drive on Prior to Asphalt
Overlay
32Asphalt Layer
- Leveling Course on First Lift with Ability to
Open Traffic - No Primer Required on Rubblized Layer
- Minimum of 12.7 cm of Asphalt Overlay
33Next Day - Open Traffic
34Recommended State Specification
- High Frequency Low Amplitude Resonant Breaker
- Resonant Breaker shall apply 2,000 lbs of
pressure per strike at 44 hertz - Removal of any Existing Asphalt Overlay
- Majority of the Particle Size Less than 15.24
centimeters - Maximum Particle Size of 20.32 centimeters
- 10 Ton High Frequency - Low Amplitude Vibratory
Roller - 3 Passes with Maximum Speed of 1.82 meters/second
- Minimum of 80 Debonding of Existing Steel
Reinforcement - No Traffic on Rubblized Slab Until First Lift is
Placed - Minimum of 12.7 cm of Hot Mix Asphalt Overlay
35Results 22 Year Road