Title: 3rd Strategy Meet
13rd Strategy Meet
2Action Taken Report (ATR)
3rd S T R A T E G Y M E E T
3Strategic Goals
- To double Reserve Accretion
- To improve Recovery Factor to 40
- To bring in 20 MMTpa equity oil from abroad
- over 2001-20
4To Double Reserve Accretion
- 4 Bmt OOEG Offshore
- Deepwater
- 2 Bmt OOEG onshore
- Frontier Basins
- Growth areas from established 6 Basins
5Deepwater
6Deepwater
- Suggested Approach
- In house expertise development
- Alliance with leading deep-water players
- Long-term strategic relationship
7Deepwater
- Decision
- Formation of Core groups to firm-up time-bound
action plan for expertise development in deep
water exploration.
- Actions Taken
- Deepwater core groups formed for integration of
activities - Plan to bridge gaps in expertise, technology
induction and skill development etc., to be
finalized in July02
Contd
8Deepwater
- Decision
- Charter hiring of rigs for deepwater operations
- Actions Taken
- Charter hiring of 3 deepwater rigs under
finalization. - Up to 1500m 1 rig
- Up to 2500m 1 rig
- Up to 3000m 1 rig
- Discussions held with drilling companies. Pre-bid
conference held. - BEC under finalization.
Contd
9Deepwater
- Decision
- Procurement of one super-deep (gt2500m) drilling
rig - Actions Taken
- Initially 1 super deep drilling rig being hired.
- Acquisition as per success probability.
Contd
10Deepwater
- Decision
- To submit a detailed proposal to MOPNG for
empowering ONGC to formalize Joint Ventures and
Alliances for ED and Drilling - Actions Taken
- Note put up in Feb2002
- Lukewarm response from 17 companies identified
for alliancing for exploration in 5 deepwater
blocks - Other companies short-listed for possible
alliance and modalities for alliance under
finalization. - Discussions with M/S Statoil for drilling
Deepwater wells on turnkey basis.
Contd
11Deepwater
- Decision
- To submit a comprehensive note to MOPNG on
existing CVC guide-lines and proposed deviations
required for taking advantage of the
technological advancements. - Actions Taken
- Comprehensive note submitted in March2002
Contd
12Frontier Basin
13Frontier Basin
- Suggested Approach
- Short Term Focussed exploration
- Medium Term - Prospectivity Assessment for
focussed Exploration - Long Term - Knowledge building for Prospectivity
Assessment
Contd
14Frontier Basin
- Decision
- Physical-inputs and resources for frontier basin
activities to be identified by March2002. - Action Taken
- Physical inputs for knowledge building activities
and resources required in the frontier basins
identified.
Contd
15Frontier Basin
- Decisions
- To submit comprehensive notes to MOPNG
requesting for - Fiscal relaxation required for its activity in
Frontier basins as well as in Tripura - Exploration licenses on nomination basis in
frontier basin - To submit proposal to OIDB for grants/ loans for
exploration in frontier basins - Actions Taken
- Physical plans along with investment requirement
being submitted to EC - On approval, comprehensive proposal to be put up
to - MOPNG for mentioned dispensations
- OIDB for grants/ soft loans for knowledge
building activities
16Established Basins Improving Recovery Factor
17Improvement in Recovery Factor
- Suggested Approach
- To focus on time-bound action plan for 15 major
producing fields including Mumbai High - To initiate actions to improve recovery factor
from other 30 fields - To initiate EOR projects for enhancing oil
recovery - Monetization accelerated development of New
Marginal fields
Contd
18Improvement in Recovery Factor
- Decision
- Continuous monitoring of major fields
- Actions Taken
- Process established for continuous monitoring of
major fields through MDT - Micro detailing for monitoring firmed up through
Project ACCEPT for Assam field - Improved surveillance established at Asset level
- IRS as nodal agency along with IOGPT, KDMIPE
monitoring the major fields on continuous basis - Consultants engaged to suggest proactive approach
Contd
19Improvement in Recovery Factor
- Decision
- To develop the fields optimally keeping in view
the sound Reservoir Management Practices. - Actions Taken
- 19 IOR/ EOR projects underway in 15 major fields
- 12 IOR/EOR under implementation
- 14 IOR Studies programmed
- 11 Feasibility Reports are in process
- 22 EOR studies in progress at IRS
Contd
20Improvement in Recovery Factor
- Decisions
- The proposal for strategic participation with
technology-leaders/ service providers for
best-available technology solutions agreed
in-principle and was desired to be expedited. - ONGC to be operator in all project-based
alliances - Actions Taken
- Special assignment to focus on Strategic
Participation/ Alliances - For strategic Project based Alliance with
technology leaders a comprehensive MOU placed on
ONGC website and correspondences held with
leaders in service sector. Response under
submission to ONGC board.
Contd
21Improvement in Recovery Factor
- Decisions
- Monetization accelerated development of New
Marginal Fields
- Action Taken
- Special group formed for development of New
Marginal fields - FR ready for Accelerated development of Vasai
East, D-1 G-1 - Dockets for new marginal fields under
preparation - Strategic options and action plan being submitted
in 3rd Strategy Meet.
22Equity oil
23Equity Oil Gas
To bring in 20 MMTpa equity oil from abroad by
2020
Suggested Approach To focus on countries -
Indonesia, Russia, Iran, Iraq, Oman, Sudan,
Libya, Kazakhstan, Nepal, Algeria, Venezuela
Contd
24Equity Oil Gas
- Available equity
- Vietnam Gas Project to go on stream by end 2002
- Sakhalin-1 project progressing on schedule oil
to flow from 2005, Gas from 2007 - Available block under exploration
- 20 equity taken in an offshore Gas exploration
block in Myanmar
Contd
25Equity Oil Gas
- Decision
- To explore the possibility to develop matrix
indicating political risk in the countries of
interest and should cover these risks through
International banks - Actions Taken
- Government of india has Bilateral Investment
Protection Agreements (BIPA) with 44 countries. - OVL refrains from investing in nations which are
not covered under BIPA - Internally OVL takes sufficient risk mitigation
through the rate of return , turn around time and
strong partner approach - Additional safe guard through the insurance
covers and guarantees is also being exercised
wherever it is felt necessary
26Focussing Responsibilty Accountability
27Corporate Rejuvenation Campaign
- Background
- CRC formulated from lessons learnt through Pilots
of Organisational Transformation Project (OTP)
launched in 1997. - CRC implementation decided in 1st Strategy Meet,
July 2001 - Launched with the blessings of Honble Minister
(PNG) on 20.8.2001
Contd
28Corporate Rejuvenation Campaign
- Status
- CRC roll-out complete Assets, Basins, Services
etc., in place - Each business unit has developed methodology to
function as Virtual Corporates
Contd
29Corporate Rejuvenation Campaign
- Decision
- To obtain suggestions on CRC implementation from
E-0 officers and above level officers. To be put
in next EC meeting for corrective actions, if any - Actions Taken
- Continued interaction - feedbacks received
- Continued Corrective actions
Contd
30Corporate Rejuvenation Campaign
- Decision
- Existing gaps in CRC to be plugged
- Actions Taken
- Necessary modifications in PAR, Cadre
development, Promotion policy etc., under
consideration for alignment as per CRC - Special groups formed for critical areas of
operation - Gas Flaring, Corporate IE, CMT, Fire Services etc.
Contd
31Corporate Rejuvenation Campaign
- Decision
- Collectives to be shown existing distortions in
the organogram due to past promotion policy - Actions Taken
- Distorted organogram posted on web for wider
appreciation - Modular course being developed for
under-qualified employees in consultation with
ISM, Dhanbad
Contd
32Corporate Rejuvenation Campaign
- Decision
- ONGC to submit a proposal on VRS bringing out
constraints and dispensations required from the
Govt. - Actions Taken
- Proposal for VRS submitted to the Govt.
33Empowerment
34Empowerment
- Background
- Board approved modifications in BDP-1994 giving
enhanced powers to the - Committee of the Board
- Committees of CMD functional Directors
- CMD
- Functional Directors.
- This became effective from 1st August2001.
- Powers below Board level was enhanced w.e.f 1st
January2002
Contd
35Empowerment
- Decision
- To carry out a quick assessment of the impact of
empowerment on overall functioning of the
organization once the transition is completed.
- Actions Taken
- Quick assessment carried out
- HR BDP approved by Board in May2002
Contd
36Empowerment
- Decision
- To give suitable powers to the location managers
to carry time bound activities.
- Actions Taken
- Delegation gaps identified
- Comprehensive agenda for revision of BDP to give
suitable powers to operational managers under
submission to Board
37Operational Efficiency
38Focus Areas
- Non-flowing wells
- Gas flaring
- Exploratory drilling backlog
- Technology
- OOR Schemes
- Infocom
- Offshore Services
- Process Simplification
39Non-flowing wells
- Goal
- Number of non-flowing wells to be reduced to 15
in onland 5 in offshore by 31.3.2003 - Suggested Approach
- Proactive workover operations
- Augmentation of Resources
Contd
40Non-flowing wells
- Decision
- An agenda to be put up to Executive Committee to
review the decision of reducing non- flowing
wells.
- Action Taken
- Action plan to reduce the number of non-flowing
wells discussed in EC
Contd
41Non-flowing wells
- Decisions
- IRS and IOGPT in consultation with Assets
Basins to review categorization of non-flowing
wells and bring a paper to EC - Sick wells to be reviewed on priority to make
achievable progress.
- Actions Taken
- MDT from IRS, IOGPT Assets constituted for
Categorization of non-flowing wells submitted
report - Sick wells being reviewed on continuous basis
Contd
42Non-flowing wells
- Decision
- To float tenders for charter-hire of 30
Work-over rigs (25 for onshore and 5 for
offshore) for 3 years - Actions Taken
- Onshore
- 22 onshore workover rigs of different capacity
planned to be charter hired during 2002-03 - Approval accorded to augment 7 workover rigs as
per existing contracts on immediate basis - Tender for charter-hiring of 4 additional rigs
under process - Offshore
- Charter hiring of 4 additional Cantilever J/Up
rigs under process
43Gas Flaring
- Goal
- To minimise Gas Flaring
- Suggested Approach
- Focus on assets where consumer base exists
- Creation of necessary infrastructure on
fast-track
Contd
44Gas Flaring
- Decision
- To minimize gas flaring.
- Actions Taken
- Focused group for Gas Flaring Control
- Required infrastructure identified
- Compressor procurement in process
- Time-bound action plan to achieve Zero Gas Flaring
45Exploratory drilling Backlog
- Goal
- To remove backlog in exploratory wells
- Suggested Approach
- Activity driven resource mobilization
Contd
46Exploration drilling Backlog
- Decision
- To initiate time-bound plan for
procurement/up-gradation of the state-of- the-art
Drilling Rigs - Actions Taken
- MOU with BHEL signed on 15.4.2002. Initially
contract awarded to BHEL for upgradation of 12
onshore rigs - Proposal submitted for acquisition of 3 offshore
jack up rigs
47Technology
- Goal
- Technology for efficiency
- Suggested Approach
- Adoption of best-in-class technology
- Monetization of idle Assets with technology
- Strategic participation with technology leaders
Contd
48Technology
- Decision
- Employing state-of-the-art and cost-effective
technologies. - Action Taken
- Technology needs worked out in various areas of
operation
Contd
49Technology
- Decision
- Improving operational efficiency using
best-in-class equipment and facilities and
continuous up-gradation of skills - Action Taken
- Technology induction plan through alliances
discussed in Board in May2002. MOU under
finalization.
Contd
50Technology - Seismic
- Decisions
- Procurement of additional state-of-the-art
Seismic Survey vessel - State-of the-art data acquisition, supported with
high computing capability for GG activities - Actions Taken
- Under Procurement
- 1- Vessel for offshore Seismic survey
- 10 - Seismic Data Acquisition system
- Upgradation of facilities at GEOPIC under process
- Virtual Reality Centre (Third Eye) to be
commissioned in July 2002 at Mumbai
51Technology - Drilling
- Decision
- ONGC to leverage state-of the-art technology like
Premium Bits, use of Drilling fluid technology
etc., for improving overall efficiency. - Actions Taken
- Premium bits under use in all major fields 42
to 64 - Efforts being made to augment drilling fluid
technology - Discussions with industry leaders
52Technology - Drilling
- Decision
- To put in place a process to ensure quality
cementation - Actions Taken
- IDT has developed light weight and ultra heavy
weight cement slurry for Mumbai high Cachar
project respectively - Project specific cementation technology worked out
53Technology - GTL
- Decision
- To send a delegation to Sasol for firming up GTL
technology induction for utilization of Tripura
Gas. - Actions Taken
- Sasol not interested to license on arms-length
basis - Desires participation in profitable ventures
- Conditions for participation
- Uncommitted gas reserve 20 TCF gas over 30
years - Gas price US0.50 per MMBTU
- Capacity 100,000 bpd
- Project benchmark for Sasol
- ICB being floated to invite prospective partners
for setting up GTL project
54OOR Scheme
- Goal
- Improved management of the existing Assets
- Suggested Approach
- Close Monitoring
- De-bottlenecking revamping of facilities
Contd
55OOR Scheme
- Decision
- To work-out time-bound action plan for SCADA
implementation. - Actions Taken
- Offshore SCADA system scheduled to be upgraded by
June2004 under project PROMISE - Onshore SCADA system (GGS/ CTF level) planned
under Project PROMISE by June2003
Contd
56OOR Scheme
- Decision
- De-bottlenecking revamping of facilities
- Actions Taken
- Assets identified the facilities requiring
de-bottlenecking. Structured approach being
adopted to revamp the facilities. - Recommendations of the consultant M/S Mckinsey
under project ACCEPT being implemented in Assam
Asset. - De-bottlenecking revamping of facilities
defined as KPA in Performance Contract signed
with Assets and Basins - Compliance of internal safety audits and third
party audit ensures phased de-bottlenecking and
revamping of facilities.
57Infocom
- Goal
- Integrated IT solutions for efficiency
- Projects under implementation
- Project ICE
- Project PROMISE
- Project EPINET
Contd
58Infocom
- Present Status
- Approval accorded to award contract on nomination
basis to M/S SAP India for implementation - 30 Projects identified under Project PROMISE
under various stages of implementation. - First phase of Project EPINET implemented
59Optimization of Offshore Services
Goal To improve and optimise offshore
services Suggested Approach Outsourcing of
offshore services through Joint Venture (JV)
Contd
60Optimization of Offshore Services
- Decisions
- To select JV partner (s)
- To prepare Feasibility Report
- MOPNG, Ministry of Shipping Surface Transport
and Ministry of Defence to be informed about the
ONGCs need and policy regarding formation of JV
for Floating Services. - Actions Taken
- Core team discussed JV formation with
- SCI, GE Shipping, SEMAC, HSL, MDL, CSL, ICICI
- Consultant being appointed for preparing
Feasibility Report. - Action in Hand
61Process Simplification
- Goal
- To Streamline tender and contract processes
procedures for expeditious resource mobilization - Suggested Approach
- To carry out Changes aiming at
- reduction in number of tenders
- selection of quality bidders
- transparent bidding process
Contd
62Process Simplification
- Decisions
- Position specific empowerment from top to grass
root level, with an in-built system of reviews at
appropriate level. - Tender information to be put on the web-site for
transparency and appropriate publicity. - Organization of proactive pre-bid conferences.
- Actions Taken
- Proposed revision in material procurement
provisions in BDP submitted for consideration - Web-site ongctendersonline.com launched. Tender
information being put on web. - Pre-bid conferences being organized on regular
basis
Contd
63Process Simplification
- Decisions
- Annual Maintenance Contract (AMC) on life-cycle
concept basis be in-place - Payment within 15 days, LD levied strictly as per
the contract - Post contract issues should be appropriately
addressed at the Directors level - Actions Taken
- AMC on life-cycle concept being incorporated as
standard clause in BEC. - Instructions issued to make payment within 15
days and imposition of LD as per contract. Agenda
under consideration of Executive Purchase
Committee (EPC) for further clarifications - Circular issued specifying authority dealing with
post contract issues.
Contd
64Process Simplification
- Decisions
- Sampling/ Bonding of Chemicals to be streamlined
- Charter-hiring of the Vessels on long-term basis
- ONGC to put up a proposal to MOPNG for entering
into long-term contracts, wherever felt necessary - Actions Taken
- Agenda related to streamline sampling/ bonding of
chemicals under consideration of Executive
Purchase Committee (EPC) - BEC approved by EPC for hiring of vessels for 3
years term. Tender being invited - DGSD is proposed to be appointed as consultant
for suggesting modalities for long-term contract.
Based on suggested approach proposal shall be
submitted to MOPNG
Contd
65Process Simplification
- Decision
- Effective vendor rating systems be evolved.
Termination or Holiday in case of defaulting
vendors. - Action Taken
- Vendor rating system established
66Other issues
67Direct Marketing
- Decision
- To prepare a comprehensive paper for direct
marketing of hydrocarbon produced from isolated
fields and in the other areas where GAIL is not
in a position to provide marketing support to
ONGC. - Actions Taken
- Comprehensive note put up to MOPNG in Feb2002
- Issue discussed by Gas Linkage Committee(GLC) on
22.5.2002 - GLC formed a committee to review guidelines for
allocation of such gas.
68Indian Flag Vessels
- Decision
- The issues related to Indian Flag Vessels
including payment in foreign currency was
discussed and it was decided that a note be
submitted to the MOPNG - Action Taken
- Action in Hand
69Refinery products
- Decision
- To put up details regarding non-upliftment of
products from Tatipaka Refinery to the Additional
Secretary (MOPNG) for taking up the matter in
the sales meeting with refineries, scheduled for
18th Feb. 2002. - Action Taken
- Comprehensive note put up to MOPNG in Feb2002
70Price Purchase Preference
- Decision
- A proposal to be submitted to MOPNG to review
the instructions regarding Price Purchase
preference to the PSUs. - Actions Taken
- Comprehensive note submitted in Feb2002
- As per decision of the Board on 16.5.2002
comprehensive agenda under submission to Govt. - Notification issued by the Govt. in June2002
restoring Purchase Preference.
71ILiTes
- Decisions
- To form disaster Management team at National
level - Indian Life Saver Teams (ILiTes) - Issue of tax exemption be examined for creating
ILiTes and modalities to flag the name of ONGC
with disaster management team be finalized. - Actions Taken
- Consultant appointed
- Action in hand
72Project Saraswati
- Decision
- A proposal for exploitation of aquifers in areas
covering the ancient Saraswati River be brought
to the EC. - Actions Taken
- Proposed approach paper discussed in EC on
25.4.2002 - Process of identifying agencies/institutions for
engagement of consultant being finalized
73Dry wells
- Decision
- Option to hand over existing dry wells which
cant be put on use to the Ground Water Boards be
examined. - Actions Taken
- Feasibility w.r.t double casing, well
availability with ONGC, cost water requirement
in the area to be studied
74Jatar Committee Report
75Jatar Committee Report
- Background
- G-345 Well in Gandhar got fire on 30.10.2001 due
to theft attempt - Expert Committee constituted by MOPNG under the
Chairmanship of Maj.Gen (Retd.) S C N Jatar to
enquire the accident - Interim report was submitted by the Committee in
January2002 - Findings of the report discussed in the 2nd
Strategy Meet, Feb 1-3, 2002.
Contd
76Jatar Committee Report
- Decisions
- Promotion of the under-qualified people to E-4
level and designating them as Engineers be
re-looked. - 14 days on/off pattern be reviewed with one rule
applicable to all work centers of ONGC. However,
a distinction be made between onshore and
offshore operations. - Actions in hand
Contd
77Jatar Committee Report
- Decision
- A comprehensive review of Crisis Management Team
in terms of reporting, equipment, efficiency,
audit, training in a time bound manner - Actions Taken
- Review of CMT carried out
- RCMT at different locations established
- CMT equipment identified and sourcing planned
- To get services at the time of crisis - Rate
contract being finalized with a reputed company - Training exposure to CMT Operational crew
- Floating Crisis Management Facility at Mumbai
Contd
78Jatar Committee Report
- Decision
- All the well sites be fenced. However, if the
present design of fencing is inadequate a review
be made. - Head-Performance Management and Benchmarking be
asked to study measurement and accounting
practices. - Actions in Hand
793rd Strategy Meet Agenda Items
80Agenda 3rd Strategy Meet
12.7.2002
- Action Taken Report (ATR)
- Monetization - Service Contract for Marginal
Fields - Monetization Farm-out of Deep-water nomination
Blocks - Monetization Departmental Projects
- FPSO/ EPS
- Gas Business Marketing Issues
- Gas Business Under recoveries
- Onshore Production
- Value Addition Oil Gas
Contd
81Agenda 3rd Strategy Meet
13.7.2002
- OOR Non-Flowing Wells
- OOR Gas Compression
- Security Manning Policy
- Offshore Production
- Financials Negative Revenues
- Financials Outstandings
- Financials Cash-flow projections
- HRD Transfer Promotion Policy Approach
- Community Development Policy
Contd
82Agenda 3rd Strategy Meet
14.7.2002
- PY-3 Case Study
- Environmental Protection
- SHE Crisis Management Team (CMT)
- SHE Learning from Safety Audits
83Thank you