Title: Inspection and Testing
1Inspection and Testing
Approved for Public Release
2Introduction
- All materials and services supplied to Electric
Boat must be inspected and tested in accordance
with Purchase Order invoked specifications,
drawings, standard clauses, etc. - Determine if supplier or government have
additional or more stringent requirements.
Approved for Public Release
3Introduction (continued)
- Purchase order imposes inspection systems via
EB2678 and Standard Clauses (60-5, 60-19, 60-58)
for MIL-I-45208, MIL-Q-9858, or ISO9000 series - Accordingly, suppliers must establish and
maintain a compliant inspection system - System must also address subtier suppliers
- Be aware of Supplemental Technical Requirements
(60-58 STRs) for ISO9000
Approved for Public Release
4Introduction (continued)
- Inspection and Testing that result in OQE must be
performed by a suppliers organization
independent of production, i.e., the Quality
Control Department.
Approved for Public Release
5 3 Basic Types of Inspection
- Receiving Inspection verifies acceptability of
materials, services, and associated documentation
at receipt.
Approved for Public Release
6 3 Basic Types of Inspection
- In-Process Inspection performed at manufacturing
stages deemed necessary to verify - internal compliance with requirements as
production progresses, statistical process
control charting, non-accessible assembly, etc. - as required by the purchase order, drawing, or
specifications to be an EB or Government
Hold/Witness Point (SC37-8 series).
Approved for Public Release
7 3 Basic Types of Inspection
- Final Inspection shall verify that the product is
dimensionally acceptable, properly assembled, and
the documentation is satisfactory in accordance
with the purchase order.
Approved for Public Release
8Requirements
- Inspection and Testing must be accomplished using
clear, complete, and current procedures and
instructions - Inspection and Testing shall be performed in
appropriate environmental conditions with respect
to temperature, humidity, noise, vibration, etc. -
Approved for Public Release
9Requirements (continued)
- Instruction needs to specify
- Source of the inspection or test criteria
- drawing, specification, standard clause, etc.
- Gaging or tooling required to ensure proper
accuracy of measurements - Provision for recording the actual results as
objective quality evidence for reference
Approved for Public Release
10Requirements (continued)
- When required by a standard clause (10, 60, 76
series), drawing, or specification, procedures
shall be approved by Electric Boat on a Vendor
Procedure Approval Request (VPAR), prior to
performance of the testing.
Approved for Public Release
11Requirements (continued)
- Examples of Testing Procedures requiring Electric
Boat approval - NDT Procedures
- Noise Testing Procedures
- Shock Testing Procedures
- Vibration Procedures
Approved for Public Release
12Requirements (continued)
- Examples of Testing Procedures requiring Electric
Boat approval (continued) - Forging test specimen location drawings
- Production Procedures (when specified by the
Purchase Order or Procurement Specification) - Qualification and First Article Procedures (when
specified by the Purchase Order or Procurement
Specification)
Approved for Public Release
13Electrical Testing
- Dielectric Voltage Withstand Test
- Dielectric Voltage can be a Destructive test.
- Voltage Level and time should be considered.
- Example Operating Voltage is 440VAC
- Test at 2 X 440 1000VAC 1880VAC
Approved for Public Release
14Electrical Testing
- Insulation Resistance
- An Insulation Resistance test is normally done
with DC and is usually performed at a lower
voltage level such as five (500VDC) hundred
volts. An IR test measures the quality of the
insulation system and provides a measure in ohms
or megohms. It is sometimes used before a HiPot
Test as both a predictor of a failure condition
and to provide a quantitative value of the
insulation system. - Often performed before, during and after Hydro on
Electrical Hull Penetrators.
Approved for Public Release
15Electrical Testing
- Continuity
- Determines if there is an uninterrupted
electrical connection between two points. - Resistance or DC Resistance
- Measured in ohms
- The opposition to current flow
- Report actual results EX gt 1 Ohm
Approved for Public Release
16Documentation
- Inspection and test results shall be documented,
preferably on a company form with letterhead. - Inspection and test results must clearly
indicate - the type and number of inspections or tests
performed - the results of the inspection or test
- the signature/date of personnel performing the
test - additional requirements of the applicable SC76-9
series
Approved for Public Release
17Documentation (continued)
- When required by the Purchase Order, generally a
Standard Clause, the Inspection and Test Reports
shall be provided to Electric Boat. - Inspection and Test Reports shall not contain any
qualifying statements, such as to the best of
our knowledge, while in our possession,
approximately, etc.
Approved for Public Release
18Documentation (continued)
- All instruments, gages, and tools used to perform
official inspections and tests must be calibrated
in accordance with a documented calibration
program. - Actual instruments, gages, and tools used to
perform official inspections and tests should be
identified and listed in the inspection or test
report - provides additional objective quality evidence
- traceability if gage out of calibration
Approved for Public Release
19Documentation (continued)
- Inspection Records and Test Reports shall be
traceable back to the product being tested or
inspected and the applicable procedures or
instruction being used. - Corrections of errors on Inspection Records or
Test Reports shall be in accordance with the
requirements of Electric Boat Specification 2678.
Approved for Public Release
20Suggestion
- Initiate a method and procedure defining type and
accuracy of gages to be used for dimensional
inspection of particular attribute tolerance
ranges - Gage for /-.020 tolerance different than
/-.0005 tolerance as is a 50psig test different
than a 500psig test - 10 rule
Approved for Public Release
21Suggestion
- To better ensure that the integrity and caliber
of the inspection system and the personnel are
being maintained - Implement an overcheck program that periodically
confirms inspector results - Implement a refresher training and qualification
program for inspectors (similar to NDT, welding,
etc.)