Title: Drilling Engineering
1- Drilling Engineering PE 311
- Drill Bit Optimization
2Optimization of Hydraulic Parameters
Introduction
- Significant increases in ROP can be achieved
through the proper choice of bit nozzle. - Most commonly used hydraulic design parameters
are - Bit nozzle velocity
- Bit hydraulic horsepower
- Jet impact force
- Current field practice involves the selection of
the bit nozzle sizes that will cause one of these
parameters to be a Maximum
3Optimization of Hydraulic Parameters
Maximum and Minimum Values - Review
- y f(x)
- The tangent to the curve is
horizontal. - Solve this equation we can get the critical
values (either max or min) x a or x b. - Second derivative
- The function has a minimum value at x b if
f/(b) 0 and f//(b) is a positive number - The function has a maximum value at x a if
f/(a) 0 and f//(a) is a negative number
4Optimization of Hydraulic Parameters
Maximum Nozzle Velocity
- Flow velocity through bit nozzle
- So velocity is directly proportional to the
square root of the pressure drop across the bit - The nozzle velocity is a maximum when the
pressure drop available at the bit is a maximum.
This can be achieved when the pump pressure is a
maximum and the frictional pressure loss in the
drillstring and annulus is a minimum the
frictional pressure loss is a minimum when the
flow rate is a minimum
5Optimization of Hydraulic Parameters
Maximum Nozzle Velocity
- Nozzle velocity may be maximized consistent with
the following two constraints - The annular fluid velocity needs to be high
enough to lift the drill cuttings out of the
hole. This requirement sets the minimum fluid
circulation rate. - The surface pump pressure must stay within the
maximum allowable pressure rating of the pump
and the surface equipment.
6Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- Effectiveness of jet bits could be improved by
increasing the hydraulic power of the pump.
Penetration rate would increase with hydraulic
horsepower until the cuttings were removed as
fast as they were generated. After this level,
there should be no further increase in the
penetration rate. Note that the hydraulic
horsepower developed by the pump is different
from the hydraulic horsepower at the bottom of
the hole. This is due to the friction losses in
the drillstring and in the annulus. Therefore,
the bit horsepower was not necessarily maximized
by operating the pump at the maximum possible
horsepower.
7Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- The Pump Pressure is expended by
- Frictional pressure losses in the surface
equipment, ?ps - Frictional pressure losses in the drillpipe,
?pdp, and drill collars, ?pdc - Pressure losses caused by accelerating the
drilling fluid through the nozzle - Frictional pressure losses in the drill collar
annulus, ?pdca, and drillpipe annulus, ?pdpa - Let
8Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- Hence, the pressure loss at the pump will be sum
of pressure loss at the bit and total frictional
pressure loss to and from the bit - It is well know that the frictional pressure loss
is a function of flow rate and can be expressed
as
9Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- Hence, Dpd can be expressed as
- m is a constant has a value near 1.75, c is a
constant that depends on the mud properties and
wellbore geometry - Pressure drop across the bit
- The bit Hydraulic horsepower
10Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- Bit horsepower is a function of flow rate
- The bit horsepower reaches maximum when
- Or
11Optimization of Hydraulic Parameters
Maximum Bit Hydraulic Horsepower
- Bit hydraulic horsepower is a maximum when
- Since
- The hydraulic horsepower will be maximum at
- Or
12Optimization of Hydraulic Parameters
Maximum Jet Impact Force
- Jet impact force is a function of Dpbit Dppump
Dpf . Note that Dpf is the total pressure loss
in pipes and annuli.
13Optimization of Hydraulic Parameters
Maximum Jet Impact Force
- The impact force is maximized when,
- Solve the above equation yields,
- or
- Since , the jet impact force will be
maximum at
14Optimization of Hydraulic Parameters
Nozzle Size Selection Graphical Analysis
- In general, the hydraulic horsepower is not
optimized at all times . It is usually more
convenient to select a pump liner size that will
be suitable for the entire well rather than
periodically changing the liner size as the well
depth increases to achieve the theoretical
maximum. Thus, in the shallow part of the well,
the flow rate usually is held constant at the
maximum rate that can be achieved with the
convenient liner size. Note that at no time
should the flow rate be allowed to drop below
the required for proper cuttings removal - For a given pump horsepower rating PHP
- E is the overall pump efficiency, pmax is the
maximum allowable pump pressure set by
contractor. This flow rate will be used until the
depth is reached at which Dpd/Dpp at the optimum
value. Then the flow rate will be reduced to the
minimum value which it can still lift the
cuttings.
15Optimization of Hydraulic Parameters
Nozzle Size Selection Graphical Analysis
- Three intervals
- Interval 1 defined by q qmax .Shallow portion
of the well where the pump is operated at the
maximum allowable pressure - Interval 2 defined by constant ?pf .Intermediate
portion of the well where the flow rate is
reduced gradually to maintain ?pd/pmax at the
proper value for maximum bit hydraulic horsepower
or impact force. - Interval 3 defined by q qmin. Deep portion of
the well where the flow rate has been reduced to
the minimum value that efficiently will lift the
cuttings to the surface.
16Optimization of Hydraulic Parameters
Nozzle Size Selection Graphical Analysis
17Optimization of Hydraulic Parameters
Nozzle Size Selection Graphical Analysis
- Show opt. hydraulic path
- Plot Dpf vs q
- From Plot, determine optimum q and Dpf
- Calculate
- Calculate total nozzle area
- Calculate Nozzle Diameter
18Optimization of Hydraulic Parameters
Example
- Determine the proper pump operating conditions
and bit nozzle sizes for maximum jet impact force
for the next bit run. The bit currently in use
has three 12/32-in nozzles. The driller has
recorded that when the 9.6lbm/gal mud is pumped
at a rate of 485 gal/min, a pump pressure of 2800
psig is observed and when the pump is slowed to a
rate of 247 gal/min, a pump pressure of 900 psig
is observed. The pump is rated at 1,250 hp and
has an efficiency of 0.91. The minimum flow rate
to lift the cuttings is 225 gal/min. The maximum
allowable surface pressure is 3000psig. The mud
density will remain unchanged in the next bit
run.
19Optimization of Hydraulic Parameters
Example
- Pressure drop through the bit
- Total frictional pressure loss inside the
drillstring and in the annulus at different flow
rate
20Optimization of Hydraulic Parameters
Example
- m 1.2, for optimum hydraulics
- Interval 1
- Interval 2
- Interval 3
21Optimization of Hydraulic Parameters
Example
22Optimization of Hydraulic Parameters
Example
- From graph, the optimum point
- The proper total nozzle area is
- The nozzle size
23Optimization of Hydraulic Parameters
Example
24Optimization of Economics
Cost-per-foot Calculation
- The goal of bit selection is to obtain the lowest
cost per foot. The cost per foot can be
calculated by using the equation - Where C is the overall cost per foot, /ft Cb is
the cost of the bit, Cr is the cost of
operating the rig /hr tb is the rotating time
with bit on bottom, hours tt is the round trip
time, including connection time, hours to is the
other time, which is not rotating time or trip
time, hours and DD is the total depth as a given
total time, ft.
25Optimization of Economics
Cost-per-foot Calculation
- Drilling costs tend to increase exponentially
with depth. Thus, when curve fitting drilling
cost data, it is often convenient to assume a
relationship between cost, C and depth, D given
by - C aebD
- Where a, , and b, ft-1, depend primarily on the
well location. - The cost per day of the drilling operations can
be estimated from considerations of rig rental
costs, other equipment rentals, transportation
costs, rig supervision costs, and others. The
time required to drill and complete the well is
estimated on the basis of rig-up time, drilling
time, trip time, casing placement time, formation
evaluation, borehole survey time, completion time
and trouble time.
26Optimization of Economics
Cost-per-foot Calculation
- Example A recommended bit program is being
prepared for a new well using bit performance
records from nearby wells. Drilling performance
records for three bits are shown for a thick
limestone formation at 9000 ft. Determine which
bit gives the lowest drilling cost if the
operating cost of the rig is 400 /hr, the trip
time is 7 hours, and connection time is 1 minute
per connection. Assume that each of the bits was
operated at near the minimum cost per foot
attainable for that bit.
Bit Bit cost Rotating time hours Connection time hours Mean penetration rateft/hr
A 800 14.8 0.1 13.8
B 4900 57.7 0.4 12.6
C 4500 95.8 0.5 10.2
27Optimization of Economics
Cost-per-foot Calculation
Bit Bit cost Rotating time hours Connection time hours Mean ROPft/hr Total cost/ft
A 800 14.8 0.1 13.8 46.80768
B 4900 57.7 0.4 12.6 42.55729
C 4500 95.8 0.5 10.2 46.89099
28Optimization of Economics
Run Cycle Speed
- The performance of a bit can also be determined
by using run-cycle speed (RCS). The RCS is
defined as - Where D is the total footage determined by the
particular bit.
29Optimization of Economics
Break-even Analysis
30Optimization of Economics
Break-even Analysis
31Optimization of Economics
Break-even Analysis
32Optimization of Economics
Termination of a Bit Run
- There is almost always some uncertainty about the
best time to terminate a bit run and begin
tripping operations. The use of the tooth-wear
equation and the bearing-wear equation will
provide, at best, a rough estimate of when the
bit will be completely worn. In addition, it is
helpful to monitor the rotary-table torque. In
the case of a roller-cone bit, when the bearings
become badly worn, one or more of the cones
frequently will lock and cause a sudden increase
or large fluctuation in the rotary torque needed
to rotate the bit. With a PDC or fixed-cutter
bit, when cutter elements are heavily worn or
broken, or the bit becomes undergauge, the bit
will exhibit much lower than expected ROP and
cyclic or elevated torque values.
33Optimization of Economics
Termination of a Bit Run
- When the ROP decreases rapidly as bit wear
progresses, it may be advisable to pull the bit
before it is completely worn. If the lithology of
the formation is homogeneous, the total drilling
cost can be reduced by minimizing the cost of
each bit run. In this case, one way to determine
when to terminate the bit run is by keeping a
current running calculation of the cost per foot
for the run, assuming that the bit would be
pulled at the current depth. Even if significant
bit life remains, the bit should be pulled when
the computed cost per foot begins to increase. - However, if the lithology of the formation is not
uniform, this procedure will not always result in
the minimum total cost. In this case, an
effective criterion for determining optimum bit
life can be better established after offset wells
are drilled in the area, thus defining the
lithological variations, and the contribution of
the rock properties can be studied and understood
better.
34Optimization of Economics
Termination of a Bit Run
- Example Determine the optimum bit life for the
bit run described in the table below. The
lithology of the formation is known to be
essentially uniform in this area. The bit cost is
5000. The rig cost is 4000 /hr and the trip
time is 10 hours.
35Optimization of Economics
Termination of a Bit Run
footage, DD ft drilling time, tb to hrs Remarks Drilling Cost, C /ft
0 0 New 0.0
30 2 1766.7
50 4 1220.0
65 6 1061.5
77 8 1000.0
87 10 977.0
96 12 968.8
104 14 971.2
111 16 Torque Increased 982.0
36Optimization of Economics
Termination of a Bit Run
37Optimization of Economics
Termination of a Bit Run
38Optimization of Economics
Termination of a Bit Run
39Optimization of Economics
Termination of a Bit Run
Example Determine the optimum bit life for the
bit run described in the table below. The
lithology of the formation is known to be
essentially uniform in this area. The bit cost is
5000. The rig cost is 4000 /hr and the trip
time is 10 hours.
Footage, DD ft drilling time tb to, hrs Remarks
0 0 New
30 2
50 4
65 6
77 8
87 10
96 12
104 14
111 16 Torque Increased
40Optimization of Economics
Termination of a Bit Run
Solution Cb 5000 USD Cr 4000 /hr Cb/Cr
5000/4000 1.25 hrs Using the equation above
with different dD/dt. te Cb/Cr 1.25 hrs. The
optimal line corresponds to dD/dt 4.2. Time to
change the drill bit is 12 hours and at the depth
of 96 ft.
41Optimization of Economics
Termination of a Bit Run