Contracts - PowerPoint PPT Presentation

About This Presentation
Title:

Contracts

Description:

Contracts Parts of a Contract Drawings General conditions Boilerplate Establishes right, responsibilities, authority, and obligations. Supplementary ... – PowerPoint PPT presentation

Number of Views:221
Avg rating:3.0/5.0
Slides: 39
Provided by: TheWolf
Category:

less

Transcript and Presenter's Notes

Title: Contracts


1
Contracts
2
Parts of a Contract
  • Drawings
  • General conditions Boilerplate Establishes
    right, responsibilities, authority, and
    obligations.
  • Supplementary conditions Specific to each job,
  • Specifications include all of contract except
    drawings

3
Technical Specifications
  • Qualitative description of items on project
  • Either specs govern over drawings or the
    architect/engineer decides when drawings and
    specs do not agree.
  • Need to be technically accurate and adequate
  • Definite clear stipulations
  • Fair equitable requirements
  • Easy to use during bidding and construction
  • Legally enforceable

4
Design Specifications
  • material and workmanship specifications (method
    and materials)
  • - 2x4 _at_ 16 o.c.

5
Performance Specification
  • spec finished product, let the contractor select
    the material and method.
  • Wall must support a 300 pound/LF vertical load
  • Can incorporate both design and performance specs
    to specify finished product and method and
    materials.
  • Wall must support a 300 pound/LF vertical load
    and be constructed from 8 x 8 x 16 concrete
    block

6
Specifications
  • Closed Spec requires specd item
  • Proprietary Spec - name supplier
  • Open Spec Required for public projects
  • Or Equal AVOID lets engineer spec 1 item and
    then allow for other equal items
  • Or Approved Equal Architect/engineer can decide
    whether a product is equal
  • Reference Spec - References tests, product
    names, part of the technical spec.
  • Standard Spec Standards from one job to the
    next.

7
As Built Drawings
  • Very important
  • Provide the final location of all underground
    utilities, and facilities and all above ground
    facilities.
  • Used as the reference document for future work on
    site
  • Cheshire fair

8
Matter of time
  • Major aspect of contracts - Contracts can specify
    that a job be completed in either XX working days
    or XX calendar days.
  • Working days
  • used when weather delays can be expected - Any
    day except Saturday, Sunday and holidays.
  • Calendar days are used when a definite opening
    date is desired.
  • Dept store must open before thanksgiving

9
How many days
  • Project schedule
  • submitted prior to starting work
  • sets work schedule.
  • Limitation of Operations
  • Times owner does not want contractor operating on
    the site.
  • Liquidated Damages
  • Compensation for financial other losses due to
    late opening. (10,000/day after Nov 20)

10
Types of Delays
  • Delay caused by contractor or contractors agents
    owner can fire contractor
  • Delay caused by owner or owners agents -
    contractor can ask for time extension
  • Delay caused by force majeure or act of God.
    Usually no for either owner or contractor
  • No damage for delay clause protects party from
    liability due to delays caused by that part

11
Exceptions
  • Delay not contemplated Labor strikes, back
    orders on supplies.
  • Active interference action by a 3rd party which
    causes work to slow or stop - environmental
    pickets
  • Delays of unreasonable duration delays by owner
    which are unreasonable in length
  • Fraud or bad faith

12
Exceptions
  • Allow contractor/owner to get time extensions for
    project
  • Extension of Time if running late, get an
    extension of time.
  • Excusable Delay act of God, labor strike,
    flooding, etc.

13
What can Happen
  • Acceleration
  • Actual owner says hire more workers. Owner pays
  • Constructive owner refuses time extension so
    contractor has to hire more help. If owner is
    cause of delay, which leads to falling behind,
    contractor may be able to collect for extra help.

14
What can Happen
  • Suspension of Work
  • gives owner ability to stop work. Owner may
    have financial trouble
  • Termination
  • Default of contractor
  • Convenience of owner
  • Owner may find that the project is too expensive
    and decide to terminate the project.

15
Effect of Delays
  • Delay caused by contractor or contractors agents
    owner can fire contractor
  • Delay caused by owner or owners agents -
    contractor can ask for time extension Delay
    caused by force majeure or act of God. Usually
    no for either owner or contractor

16
Home Office Overhead
  • Operations Maintenance of home office
  • Eichleay Formulae
  • OHproj (Billingsproj)/(Billingstotal)OHTotal
  • For Delay
  • OHdelay (OH/Duration)proj(days of delay)

17
CONTRACT DESCRIPTORS
  • Contract
  • Agreement between two parties that is enforceable
    by law for their mutual benefit.
  • Litigation
  • Court decision, which is binding on both parties
  • Executed
  • When both parties have fully performed in
    accordance with the contract terms, i.e.,
  • Executory
  • When some portion of agreement remains undone,

18
Contracts can be
  • Bilateral
  • Both parties promise something to each other.
    Most construction contracts are bilateral.
  • Unilateral
  • One party promises something while the other
    party exchanges something other than a promise.
    Action may substitute for promise, i.e., Ill
    sell you 100 RR ties for 6 each gt You send me a
    check for 600 you own RR ties. You are in
    control of whether or not contract is formed.

19
Contracts can be
  • Expressed
  • Terms are clear, concise, explicit and well
    defined.
  • Implied
  • Terms not clearly stated but established thru
    inference and deduction, i.e. Drive to parking
    lot, give attendant 2 and park car
  • An expressed contract can be altered by an
    implied contract if the project described in the
    expressed contract, once signed, is significantly
    changed. Then an implied agreement to do the
    work for hourly rates could become binding.

20
Contracts can be
  • In Joint Agreement
  • individual parties joined into one party in
    legal and liability sense,
  • Several or Separate
  • Each party has a liability that is separate from
    any other party.
  • Joint and Several
  • Binds individuals as a unit each individual
    accepts separate accountability.

21
Contract disputes
  • Usually solved by courts. By using standard
    provisions in contracts it makes it easier for
    the courts to reach a decision.

22
Torts
  • disputes that relate to matters not addressed by
    statutory law or contract obligations.
  • Wrongs committed against others that do not
    involve contracts.
  • Common law interpretation required
  • Can result from a special action or can be caused
    by failure to act
  • Offense against person that does not involve a
    crime or law violation
  • A tort can be a crime

23
To file a tort
  • 1) Establish that one party had a duty to the
    other party breach in performance of duty
  • 2) How damage is direct consequence of (1)
  • Examples slander, libel
  • Standard of care Conduct expected of someone in
    a given capacity.
  • Attractive Nuisance A construction site is an
    attractive nuisance. A tort action of trespass
    could be denied because of this.
  • Contributary Nuisance Offered as a defense to
    avoid liability from an injury. Injury occurred
    due to actions of injured party.

24
Bond Terms
  • Principal
  • Principal debtor is party whose performance is
    guaranteed
  • Surety
  • Company pays if principal does not perform
  • Obligee
  • Party to whom promise of principals performance
    is made

25
Bonds
  • Miller Act (1935)
  • Surety bond required for all federal assistance
    projects.
  • Bid bond
  • Bond that contractor will enter into binding
    contract will provide payment performance
    bonds.
  • Performance bond
  • Payment bond
  • Protects owner if the general contractor does not
    pay the subs or suppliers

26
Elements of a Contract
  • Meeting of Minds
  • Agreement on a basic meaning legal implications
    of the contract.
  • Unreality of Consent
  • cannot agree on basicsgtgtno contract
  • Contract is based on fact.

27
Contract is null and void if
  • Unilateral mistake or mutual error
    (Unintentional)
  • Parties do not have same perception of the
    identity of the subject of the agreement
  • Subject does not exist due to death, destruction,
    etc.
  • Misrepresentation
  • Fraud (intent to deceive)
  • Fraud (deliberate failure to provide relevant
    information vital to the agreement)
  • Duress (forced consent)
  • Error in plans

28
Offer Acceptance
  • Offer
  • one person signifies to another a willingness to
    enter into a binding contract on certain terms.
  • Acceptance
  • creates contract provided it was made in the
    manner time specified in the offer.
  • Counter Offer
  • if acceptance is not definite, unqualified and
    unconditional. Once a counter offer is made, the
    original offer is no longer valid.

29
Consideration
  • Something of value
  • Prime reason for entering a contract. Both
    parties must have consideration or contract is
    void. Consideration does not have to be actual
    benefit, i.e., pay someone not to marry binding
    upon acceptance.

30
Lawful Subject Matter
  • Contracts must have it.
  • Subject matter cannot violate any fundamental
    dictate of common law, or be contrary to public
    policy. Collusion or bid rigging is illegal and
    any contract between two parties for the purpose
    of rigging bids is void.

31
Competent parties
  • Cannot be insane, drunk, or a minor.

32
Estoppel
  • Contract becomes binding in spite of the fact
    that no formal agreement was made between
    parties.
  • Implied agreement, i.e., go to a movie, pay gtgt
    see movie or get a refund.
  • Promissary Estoppel
  • Frequently encountered in construction. Bid by
    phone, which is used in a larger bid package, is
    binding.

33
Assignment of Contracts
  • Transfer rights and responsibilities to a 3rd
    party not originally involved in the contract.
  • Second party cannot be placed in a worse position
    than it would have without the assignment.
    Loans, etc.

34
Real Property
  • Real Property
  • Land and attachments (buildings, permanent
    fixtures on land)
  • Liens
  • Legal claim on property. Party has the right to
    retain property until debt is satisfied.
  • Tax Lien Right of government to retain
    possession of property until taxes are paid.
  • Mechanics Lien Right to place a claim on land
    on which work was performed. Includes all
    craftsmen and suppliers. Needs written contract

35
Real Property
  • Eminent Domain
  • Right of public to take land at fair market value
    when the land will be used to provide a benefit
    (service) to the public.
  • Condemnation exercising the right of eminent
    domain.
  • Zoning

36
Stop Notice
  • Notify owner of non-payment by general
    contractor. Can be placed by supplier, sub,
    worker.

37
Agents
  • Principal is liable for all contracts made by the
    agent.
  • Agents
  • must display complete loyalty good faith,
  • obey instructions,
  • not exceed authority,
  • cannot compete with the principal,
  • profit at principals expense,
  • or do any self dealing.

38
Contingent Liability
  • Injured 3rd party is not or should not be
    affected by a contract between two other parties.
    Therefore, injured worker can sue owner and
    contractor. Engineers can be 3rd parties due
    to inspection.
Write a Comment
User Comments (0)
About PowerShow.com