Title: Construction Project Management
1Construction Project Management
An-Najah National University Faculty of
Engineering Civil Engineering Department
Prepared By Omar Al-Taher Supervised By Dr
Baraq Jumaa
2Graduation project consist of two parts The
first part include preparing a theoretical
research. The second part includes the
application of the principle in construction
project management.
3What is a Project? A project is a temporary
endeavor undertaken to accomplish a unique
product or service with a defined start and end
point and specific objectives .
PMBOK definition
4The Scope Triangle
5What is Project Management?
Project management is the application of
knowledge, skills, tools, and techniques applied
to project activities in order to meet or exceed
stakeholder needs and expectations from a
project.
PMBOK definition
6Project ManagementBody Of Knowledge ( PMBOK)
The PMI has identified nine topic areas to define
the scope of project management knowledge as
follows Project Integration Management Project
Scope Management Project Time Management Project
Cost Management Project Quality
Management Project Human Resource
Management Project Communication
Management Project Risk Management Project
Procurement Management
7Project Phases and Life Cycle
8Project Area
9Project Information
10??????? ???????? ???????
11??????? ???????? ???????
12??????? ???????? ???????
13??????? ???????? ???????
14DESIGN Step
compatibility
Thickness of slabs
15Design Criteria
16Cont.CHECK DESIGN ( Columns )
17Design of Footings Beams
18Design of Slab ( one way Ribbed )
19Cont.
20Cont.
21Cont.
22Work Break Down Structure
23(No Transcript)
24Scheduling by using PrimaveraAssumptions
- Working day 8 hours
- Working days are all days except Fridays and
holidays. - The electrical and mechanical work done by sub
contractor. - All money paid by New Israeli Shekel (NIS) and
the fixed value of Dollar according to local coin
was (14 NIS).
25Scheduling by using Primavera ProgramPrimavera
results show The overall duration of the project
was 523 Calendar Days from 01-Sep-11 to
27-Oct-12, while the total budgeted cost will be
equal 1,069,432 NIS.
26Activity List ( Primavera )
27Cont.
28S-CURVE FOR WE HAVE USING PRIMAVERA
29Results. ( percent of total price )
100 () Description.
18.6 Excavations
25.7 Concrete works
17.5 Stone works
3.4 Plaster.
5.7 Tiles.
3.2 Blocks
25.9 Finishing
30Thank You