Title: Grid Operations
1Grid Operations
2Purpose Basic Understanding of Grid
Operations/Blackout/Recovery
- Electric Power Grid Structure
- Reliability Councils/ISOs/TSO/RTOs
- GL 2006-02 Information
- Causes of Blackouts
- Blackout Recovery Procedures
- NERC Emergency Declarations
3INTERCONNECTIONSThree major electric system
networks Reliability Councils
4Independent System OperatorsTransmission System
Operators
5Independent System Operators (ISO)Transmission
System Operators (TSO)
- ISO/TSOs rely upon real-time data about the
electric system to buy and sell power, and
arrange transmission service.
- MISO
- Kewaunee
- Point Beach
- Fermi
- Davis-Besse
- Perry
- Duane Arnold
- PJM
- Braidwood
- Byron
- Dresden
- LaSalle
- Quad Cities
- DC Cook
- AmerenIP
- Clinton
- Michigan Electric TC
- Palisades
- NSP System Control Center
- Monticello
- Prairie Island
6GL 2006-02 Grid Reliability and the Impact on
Plant Risk and the Operability of Offsite Power
- GL required information on communications between
plants and ISOs/TSOs - GL also required information regarding Energy
Management Systems (analytical tools to monitor
grid operations) - State Estimator provides a real time ac power
flow model and system snap-shot using known V,
and Amps for sections of grid and calculating V,
Amps, MW, MVARs in other areas and then compares
against telemetered data (every 2 min) - Real Time Contingency Analysis what if study
to determine what problems might result as lines
and transformers are taken out of service (every
5-10 minutes) - First contingency analysis or N-1 refers to
an analysis performed assuming the unexpected
failure or outage of a single component, such as
a generator, a transmission line, or a
transformer (e.g. trip of NPP or largest
generator)
7State Estimator
8Major Causes of Blackouts
- Voltage Collapse results from local reactive
power deficiency - Cascading Thermal Overloads thermal
transmission overloads due to lines sagging into
vegetation. - Dynamic Instability results from systems
inability to dampen normal oscillations after a
disturbance. Generators swing against each
other resulting in large MW and MVAR swings.
9Reactive Power
- Reactive power is a concept to describe the loss
of power in a system arising from the production
of electric and magnetic fields - In power transmission and distribution,
significant effort is made to control the
reactive power flow. This is typically done
automatically by switching inductors or capacitor
banks in and out, by adjusting generator
excitation, and by other means. - A voltage collapse occurs when the system is
trying to serve more load than the voltage can
support
10Power Factor and Reactive Power
- Power Factor Active power/Apparent power
kW/kVA - Active power/ (Active Power Reactive Power)
- kW/(kWkVAr)
- Beer/(Beer Foam)
- The more foam (higher kVAr) indicates low power
factor and vice versa.
11Reactive Power Voltage Support
- Transmission system voltage is needed to transfer
power from generation stations to the load
centers - Reactive power (VARs) is the component of total
power that maintains voltages across the system - Sufficient voltage is maintained by supplying the
transmission system with reactive power from
generating stations and static devices
(capacitors) - Customer loads consume reactive power, as do
heavily loaded transmission lines - Reactive power cannot travel long distances
because it meets considerable resistance over the
transmission lines. - As transmission lines become more heavily loaded,
they consume more of the reactive power needed to
maintain proper transmission voltage - When reactive supply is limited, the increased
loading will cause a voltage drop along the line.
- If reactive supply is not provided at the end of
the line, the voltage begins to rapidly drop. - If the transmission system can no longer transfer
power from distant generation to energy users
system begins to separate.
12Voltage Collapse (V-Q curve)
13Blackout Recovery Procedures
- Establish Generation
- Blackstart units can start and synchronize to the
system without system ac power (compressed air
start, battery powered electric motor, etc ) - hydros can be started quickly
- small Combustion Turbines-jet technology (10
minutes) - large CTs (up to an hour)
- steam units (e.g., coal) (1-20 hours)
- Priorities pre-established
- nuclear plant auxiliary power
- generating unit auxiliary power
- substation power
- natural gas or oil supply facilities
14Blackout Recovery Procedures
- Island isolated area where generation and
load is essentially balanced - Approach to system restoration is pre-planned.
Options - Single island black start unit, identify
transmission paths/loads, expand island - Multiple island black start units, pre-selected
loads, separate restoration process, islands
synchronize - Core island one or a few large core islands
used with multiple control centers involved - Backbone island large island, ties in smaller
areas and avoids synchronizing large islands
15NERC Emergency Declarations
- NERC has established three levels of Energy
Emergency Alerts - Reliability Coordinators will use these terms
when explaining energy emergencies to each other - An Energy Emergency Alert is an emergency
procedure, not a daily operating practice
16NERC ALERT DEFINITIONS
- ALERT 1 All available resources in use.
- All available resources are committed to meet
firm load, firm transactions, and reserve
commitments concern about sustaining Required
Operating Reserves - ALERT 2 Load management procedures in effect.
- No longer able to provide customers expected
energy requirements. - Forsee need to implement procedures including,
but not limited, to - Public appeals to reduce demand.
- Voltage reduction.
- Interruption of non-firm end use loads in
accordance with applicable contracts. - During Alert 2, affected entities have the
following responsibilities - Notifying other Balancing Authorities and market
participants. - Declaration period.
- Sharing information on resource availability.
- ALERT 3 Firm load interruption imminent or in
progress. - Foresee or implementing firm load obligation
interruption. - Continue actions from Alert 2. The emergency is
posted on the NERC website.
17DEFINITIONS
- Black Start Unit. A generating unit with the
ability to go from a shutdown condition to an
operating condition and start delivering power
without assistance from the transmission system. - Blackout (System Shutdown). The disconnection of
the source of electricity from all electrical
loads in a certain geographical area brought on
by insufficient generation, an emergency-forced
outage, or other fault in the generation/transmiss
ion, distribution system serving the area. - Combustion Turbine. A generating unit in which a
combustion turbine engine is the prime mover for
an electrical generator. It is typically used for
peak shaving operation due to quick response
capability. - Emergency Maximum Generation Limit. The most
amount of generation which can be produced by a
unit and still maintain it at a stable level of
operation.
18DEFINITIONS - contd
- Operating Reserve. Reserve capability which can
be converted fully into energy within 30 minutes
from the request of the PJM System Operator. - Reactive Power. The product of voltage and the
out-of-phase component of alternating current.
Reactive power, usually measured in MVAR, is
produced by capacitors and overexcited generators
and absorbed by reactors and other inductive
devices. - Reserves.
- Operating Reserve - Generation available in 30
minutes - Spinning Reserve - Synchronized generation
available in 10 minutes. - Quick-Start Reserve Non-sychronized reserve
available in 10 minutes. - Secondary Reserve Reserve available in 11- 30
minutes - Synchronous Condenser. A synchronous machine
which operates without mechanical load to supply
or absorb reactive power for voltage control
purposes.
19NRR Daily Grid Status Reporthttp//nrr10.nrc.gov/
DEVELOPMENT/GRIDSTATUS/gridstatus_current.ppt
20Important Points
- State Estimator
- Real Time Contingency Analysis
- First contingency analysis
- ISOs/TSOs
- Causes of Blackouts
- Voltage Collapse (lack of reactive power)
- Thermal Overloads (lines or vegetation growth)
- Dynamic Instability (generation/load imbalance)
- NERC Emergency Declarations