Grid Operations - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Grid Operations

Description:

Grid Operations Purpose: Basic Understanding of Grid Operations/Blackout/Recovery Electric Power Grid Structure Reliability Councils/ISOs/TSO/RTOs GL 2006-02 ... – PowerPoint PPT presentation

Number of Views:386
Avg rating:3.0/5.0
Slides: 21
Provided by: lara124
Category:
Tags: grid | operations | power

less

Transcript and Presenter's Notes

Title: Grid Operations


1
Grid Operations
2
Purpose Basic Understanding of Grid
Operations/Blackout/Recovery
  • Electric Power Grid Structure
  • Reliability Councils/ISOs/TSO/RTOs
  • GL 2006-02 Information
  • Causes of Blackouts
  • Blackout Recovery Procedures
  • NERC Emergency Declarations

3
INTERCONNECTIONSThree major electric system
networks Reliability Councils
4
Independent System OperatorsTransmission System
Operators
5
Independent System Operators (ISO)Transmission
System Operators (TSO)
  • ISO/TSOs rely upon real-time data about the
    electric system to buy and sell power, and
    arrange transmission service.
  • MISO
  • Kewaunee
  • Point Beach
  • Fermi
  • Davis-Besse
  • Perry
  • Duane Arnold
  • PJM
  • Braidwood
  • Byron
  • Dresden
  • LaSalle
  • Quad Cities
  • DC Cook
  • AmerenIP
  • Clinton
  • Michigan Electric TC
  • Palisades
  • NSP System Control Center
  • Monticello
  • Prairie Island

6
GL 2006-02 Grid Reliability and the Impact on
Plant Risk and the Operability of Offsite Power
  • GL required information on communications between
    plants and ISOs/TSOs
  • GL also required information regarding Energy
    Management Systems (analytical tools to monitor
    grid operations)
  • State Estimator provides a real time ac power
    flow model and system snap-shot using known V,
    and Amps for sections of grid and calculating V,
    Amps, MW, MVARs in other areas and then compares
    against telemetered data (every 2 min)
  • Real Time Contingency Analysis what if study
    to determine what problems might result as lines
    and transformers are taken out of service (every
    5-10 minutes)
  • First contingency analysis or N-1 refers to
    an analysis performed assuming the unexpected
    failure or outage of a single component, such as
    a generator, a transmission line, or a
    transformer (e.g. trip of NPP or largest
    generator)

7
State Estimator
8
Major Causes of Blackouts
  • Voltage Collapse results from local reactive
    power deficiency
  • Cascading Thermal Overloads thermal
    transmission overloads due to lines sagging into
    vegetation.
  • Dynamic Instability results from systems
    inability to dampen normal oscillations after a
    disturbance. Generators swing against each
    other resulting in large MW and MVAR swings.

9
Reactive Power
  • Reactive power is a concept to describe the loss
    of power in a system arising from the production
    of electric and magnetic fields
  • In power transmission and distribution,
    significant effort is made to control the
    reactive power flow. This is typically done
    automatically by switching inductors or capacitor
    banks in and out, by adjusting generator
    excitation, and by other means.
  • A voltage collapse occurs when the system is
    trying to serve more load than the voltage can
    support

10
Power Factor and Reactive Power
  • Power Factor Active power/Apparent power
    kW/kVA
  • Active power/ (Active Power Reactive Power)
  • kW/(kWkVAr)
  • Beer/(Beer Foam)
  • The more foam (higher kVAr) indicates low power
    factor and vice versa.

11
Reactive Power Voltage Support
  • Transmission system voltage is needed to transfer
    power from generation stations to the load
    centers
  • Reactive power (VARs) is the component of total
    power that maintains voltages across the system
  • Sufficient voltage is maintained by supplying the
    transmission system with reactive power from
    generating stations and static devices
    (capacitors)
  • Customer loads consume reactive power, as do
    heavily loaded transmission lines
  • Reactive power cannot travel long distances
    because it meets considerable resistance over the
    transmission lines.
  • As transmission lines become more heavily loaded,
    they consume more of the reactive power needed to
    maintain proper transmission voltage
  • When reactive supply is limited, the increased
    loading will cause a voltage drop along the line.
  • If reactive supply is not provided at the end of
    the line, the voltage begins to rapidly drop.
  • If the transmission system can no longer transfer
    power from distant generation to energy users
    system begins to separate.

12
Voltage Collapse (V-Q curve)
13
Blackout Recovery Procedures
  • Establish Generation
  • Blackstart units can start and synchronize to the
    system without system ac power (compressed air
    start, battery powered electric motor, etc )
  • hydros can be started quickly
  • small Combustion Turbines-jet technology (10
    minutes)
  • large CTs (up to an hour)
  • steam units (e.g., coal) (1-20 hours)
  • Priorities pre-established
  • nuclear plant auxiliary power
  • generating unit auxiliary power
  • substation power
  • natural gas or oil supply facilities

14
Blackout Recovery Procedures
  • Island isolated area where generation and
    load is essentially balanced
  • Approach to system restoration is pre-planned.
    Options
  • Single island black start unit, identify
    transmission paths/loads, expand island
  • Multiple island black start units, pre-selected
    loads, separate restoration process, islands
    synchronize
  • Core island one or a few large core islands
    used with multiple control centers involved
  • Backbone island large island, ties in smaller
    areas and avoids synchronizing large islands

15
NERC Emergency Declarations
  • NERC has established three levels of Energy
    Emergency Alerts
  • Reliability Coordinators will use these terms
    when explaining energy emergencies to each other
  • An Energy Emergency Alert is an emergency
    procedure, not a daily operating practice

16
NERC ALERT DEFINITIONS
  • ALERT 1 All available resources in use.
  • All available resources are committed to meet
    firm load, firm transactions, and reserve
    commitments concern about sustaining Required
    Operating Reserves
  • ALERT 2 Load management procedures in effect.
  • No longer able to provide customers expected
    energy requirements.
  • Forsee need to implement procedures including,
    but not limited, to
  • Public appeals to reduce demand.
  • Voltage reduction.
  • Interruption of non-firm end use loads in
    accordance with applicable contracts.
  • During Alert 2, affected entities have the
    following responsibilities
  • Notifying other Balancing Authorities and market
    participants.
  • Declaration period.
  • Sharing information on resource availability.
  • ALERT 3 Firm load interruption imminent or in
    progress.
  • Foresee or implementing firm load obligation
    interruption.
  • Continue actions from Alert 2. The emergency is
    posted on the NERC website.

17
DEFINITIONS
  • Black Start Unit. A generating unit with the
    ability to go from a shutdown condition to an
    operating condition and start delivering power
    without assistance from the transmission system.
  • Blackout (System Shutdown). The disconnection of
    the source of electricity from all electrical
    loads in a certain geographical area brought on
    by insufficient generation, an emergency-forced
    outage, or other fault in the generation/transmiss
    ion, distribution system serving the area.
  • Combustion Turbine. A generating unit in which a
    combustion turbine engine is the prime mover for
    an electrical generator. It is typically used for
    peak shaving operation due to quick response
    capability.
  • Emergency Maximum Generation Limit. The most
    amount of generation which can be produced by a
    unit and still maintain it at a stable level of
    operation.

18
DEFINITIONS - contd
  • Operating Reserve. Reserve capability which can
    be converted fully into energy within 30 minutes
    from the request of the PJM System Operator.
  • Reactive Power. The product of voltage and the
    out-of-phase component of alternating current.
    Reactive power, usually measured in MVAR, is
    produced by capacitors and overexcited generators
    and absorbed by reactors and other inductive
    devices.
  • Reserves.
  • Operating Reserve - Generation available in 30
    minutes
  • Spinning Reserve - Synchronized generation
    available in 10 minutes.
  • Quick-Start Reserve Non-sychronized reserve
    available in 10 minutes.
  • Secondary Reserve Reserve available in 11- 30
    minutes
  • Synchronous Condenser. A synchronous machine
    which operates without mechanical load to supply
    or absorb reactive power for voltage control
    purposes.

19
NRR Daily Grid Status Reporthttp//nrr10.nrc.gov/
DEVELOPMENT/GRIDSTATUS/gridstatus_current.ppt
20
Important Points
  • State Estimator
  • Real Time Contingency Analysis
  • First contingency analysis
  • ISOs/TSOs
  • Causes of Blackouts
  • Voltage Collapse (lack of reactive power)
  • Thermal Overloads (lines or vegetation growth)
  • Dynamic Instability (generation/load imbalance)
  • NERC Emergency Declarations
Write a Comment
User Comments (0)
About PowerShow.com