Title: Implementation process
1Implementation process of Mahatma Gandhi NREGS
21. Model case record of different schemes
maintenance of Case record by GPs
- At GP level Schemes deals with MGNREGS, TFC, KL
Grant, GP Fund. - MGNREGS
- Maintaining of Case Record in three Stages
- Before Execution
- During Execution
- After Completion
3- A. Before Execution
- The Project is to be approved by Palli Sabha,
Gram Sabha Panchayat Samiti Zillaparisad. - Approved Project List/Action Plan is to be sent
to GP PS and work to be taken up on priority
basis. - The Plan, Estimate Design to be prepared by the
JE with wage component of minimum 60, the
same to be technically sanctioned by the
competent authority.
4- Project Code to be generated at Block Level
NREGAsoft (http//nrega.nic.in). - Example- 2427004011/RC earthen Road 70335
- Financial Sanction will be done at DPC level.
- C1 - is the demand for the work, C2 - is the Job
provided Muster roll to be generated with
computerised number the same will be issued by
the Programme officer. - Case Record is to be opened indicating (Front
Page) - Project Code.
- C/R NoFinancial Year
- Name of the Work..
- Name of the village.
- Name of the GP.
- Name of the PS..
- Heads of A/C.
- Estimated Cost
- Date of Commencement
- Date of Completion..
- Name of BDO, Name of AE, Name of JE, Name of EO,
Name of Gram Sanjojak. - MB no.. Page.
5- Case Record contains
- Copy of Approved Annual Action Plan
- Approved Plan Estimate
- Copy of Financial Section
- Copy of monitoring committee
- Work order of Gram Sanjojaka
- Pre Photograph of Work Side
- Photograph of Transparency pillar
- C1,C2 form and muster roll
6- During Execution
- Work Site will be facilitated with rest shed,
First-aid box ,drinking water supply Creatures
if required. - The Gram sanjojaka will be provided with a bag
containing a copy of Case Record, Stock Register,
Grievance Register, Muster Roll, Diary,
Measurement register,Measuring Tape, Calculator,
First-Aid box , other register forms - Photographs of Working laborers at regular
interval indicating dates. - The muster roll is to be maintain by Gram
Sanjojak Daily _at_90/Day per head. - The daily Measurement will be taken by Gram
Sanjojak in his note book should be signed by
the group leader. - The Measurement will be taken by the JE in every
Seven days which is to be check measured by the
competent authority.
7- During Execution (contd..)
- After passing of bill the payment will be made
through the Post Office/Bank. - the Gram Sanjojaka has to collect the
signature/LTI from the labourer he should
declar the wage amount , name of the Bank/Post
office wage slip given to the labourers. - Interim monitoring committee report is to be
attached. - Online entry of paid muster roll vouchers by
the CP will be done. - Payment amount will be entered in job card
employment register - The most sincere duty of a Gram sanjojaka to
provide regular mesurement, regular payment,
smooth management of work site.
8- C. After Completion
- Final monitoring committee report
- Final photographs of Project.
- Completion certificate of indicating( Date of
Comm, Date of Comp., Mandays generated,
Expenditure incurred) - Hard copy of expenditure report.
- Social Audit.
- Success Story.
9- Six Register of MGNREGA will be maintained
properly at GP level to ascertain the
transparency of MGNREGS. - Application register
- Muster roll received register
- Job Card register
- Employment Register
- Complain register
- Asset register
10SUCCESS STORIES UNDER MGNREGS
RAIN WATER MANAGEMENT PROJECT, PUA(WODC
MGNREGS)
1111
12How do we do that? Infiltration Design network
Yellow Primary guide bond Blue - Secondary
guide bond Red- Runoff water
12
13Convergence of MGNREGS with WODC fund
Project PUA G.P-PUA, Block-Tarva Before Treatment
Project PUA G.P.-PUA, Block-Tarva AFTER
TREATMENT Construction of Secondary guide bonds
Project Cost-53.74 lakh Benefit- i.For
conservation of run off Water. ii.To raise
ground water table . iii. To create addl. Rabi
Summer Crop.
13
14Construction of Primary guide bonds
14
15Farm ponds under NREGS (30 X 30 X 10)Ft.
15
16Secondary Guide bonds
16
17Mango Plantation under NREGS
17
18Men at work under NREGS
18
19(No Transcript)
20Name of the Project- Const.of Farm Pond Name of
the Beneficiary- Deba Podha Village - Brahmani
under Tarva block Est.Cost- 50,000/- Head of
account - MGNREGA It will provided water for
vegetable Cultivation
21Name of Work Farm Pond of Sri Chandra
Mendili Estimated Cost Rs.35,000/-, Name
of Village Dahanipali under Hillund GP of Bmpur
Block
22Improvement of Road from Malpur to
mahanadi Chadeipank GP under Ullunda
Block Cost-5.00 lakhs Benefits-It connects 3 nos
of villages
23MGNREGS PROJECT
Project- Check dam, Sardhapali Cost- 80000/- GP
- Kalapathar Block- SONEPUR Benefit- 1.To
raise ground water 2.Protective irrigation
during dry spell period. 3. for common uses.
24THANKS