EPOXY-COATED REBARS IN CONRETE CONSTRUCTION - PowerPoint PPT Presentation

About This Presentation
Title:

EPOXY-COATED REBARS IN CONRETE CONSTRUCTION

Description:

EPOXY-COATED REBARS IN CONRETE CONSTRUCTION Ahmad S. Al-Gahtani Department of Civil Engineering King Fahd University of Petroleum & Minerals Background ... – PowerPoint PPT presentation

Number of Views:384
Avg rating:3.0/5.0
Slides: 48
Provided by: Hna4
Category:

less

Transcript and Presenter's Notes

Title: EPOXY-COATED REBARS IN CONRETE CONSTRUCTION


1
EPOXY-COATED REBARS IN CONRETE CONSTRUCTION
  • Ahmad S. Al-Gahtani
  • Department of Civil Engineering
  • King Fahd University of Petroleum Minerals

2
Epoxy coating procedure
3
Background
  • Deterioration of bridge decks in the 1960s
  • Research by U.S FHWA
  • First bridge in 1973 in Philadelphia
  • By 1977, 17 states adopted the use of FBECR
  • Early studies showed FBECR is effective in
    reducing corrosion by many folds (11-41 times)
    compared to black steel(FHWA 1977-81)

4
Florida Experience
  • Florida long key bridges constructed in 1979
  • In 1986 substructures showed signs of corrosions
    in major five bridges
  • Corrosion was in tidal/splash zone (0.6-2.4 m
    above water mark)

5
Florida Investigation
  • Disbondment of coating
  • Water blisters under the coating
  • Corrosion initiated at damages/imperfections
  • Corrosion aggravated by
  • - Fabrication bending
  • - Exposure to salt air in construction yard
  • - Coating defects/damages
  • In 1992 Florida D.O.T. discontinued
  • use of FBECR.

6
(No Transcript)
7
Performance of ECR in Pennsylvania (I)
  • 11 bridges with ECR (ages 6 to 10 years) and 11
    bridges (comparable ages) with plain rebar
    subjected to deicing salt service. Initial
    stages of corrosion observed in the plain bar
    bridges but not in the ECR structures. Chloride
    0.7 Kg/m3. 1987

8
Performance of ECR in Pennsylvania (II)
  • Investigation of epoxy coated rebar and other
    protection systems of 21 bridge decks ( ages 10
    years) in deicing salt , Chloride 7 kg/m3 Both
    ECR rebar provided the most effective
    protection performance, some rebars being in
    excellent condition despite high chloride
    contents .

9
Performance of ECR in Canada (C-SHRP)
  • 19 ECR structures (3 to 16 years old) The ECR
    bars showed varying degrees of corrosion damage,
    with concrete damage and/or significant corrosion
    on bars at cracks and in low cover areas with
    high chloride. Many uncorroded after up to 16
    years service when no significant chloride had
    reached the bars. About 50 of bars showed
    reduced coating adhesion, (1992).

10
Performance of ECR in Canada (Ontario)
  • Ontario MOT, during 1989-1995, evaluated ECR in
    numerous structures in deicing salt service.
    Initially found little deterioration of ECR
    except for damage in a barrier wall ? 10 years
    old. By 1992 multiple instances of ECR corrosion
    were observed. Coating disbondment was observed.
    ECR was viewed as providing an improvement over
    plain steel, but the suitability for 75-year
    durability was questioned 16.

11
Performance of ECR in New York Bridge Decks
(1992)
  • DOT examined 14 of 7-12 year old "worst-case"
    bridges with deck surface distress ed in deicing
    salt service. Rebars from cores, 65 had
    negligible corrosion, 30 had corrosion at ribs
    only and 5 showed more pronounced corrosion. No
    undercoating was observed surrounding corroded
    areas. Chloride ?2 Kg/m3 the incidence of
    corrosion was not observed to be correlated with
    chloride level. Long-term corrosion performance
    could not be quantified yet.

12
Performance of epoxy coated in Virginia (1993)
  • Transportation Research Council investigated the
    condition of ECR in two test bridges built in
    1977 and in deicing salt service for 13 years.
    Chloride ?2 Kg/m3) . ECR bars were of early
    types, with many flaws and holidays. However,
    coating disbondment or signs of severe rusting
    were not observed. It was concluded that the
    combination of adequate depth of cover and ECR
    provided excellent protection.

13
Performance of ECR in a Coastal Georgia Bridge
(1993)
  • Georgia DOT examined ECR in the substructure of
    a 9-year old marine bridge (seawater tidal and
    splash service). Coating disbondment was
    observed at several of the ECR samples extracted.
    Severe corrosion of ECR was observed at an area
    of poor concrete consolidation. It was concluded
    that ECR provided questionable added corrosion
    protection, and recommended that epoxy coating
    not be used in continually wet marine
    substructure.

14
Performance of ECR in West Virginia Bridges
(1994)
  • DOT investigated 14 bridge decks (?13 years old)
    in deicing salt service using ECR and plain bar.
    ECR bridges exhibited little or no distress
    while plain bar bridges showed 2-17 deck
    delamination. Chloride ?1.5 to 3 Kg/m3. It was
    concluded that use of ECR resulted in dramatic
    reduction of delamination in bridge decks.

15
Performance of ECR in Coastal North Carolina
Bridges (1993-1995)
  • DOT examined the ECR in the substructure of
    three marine bridges (splash-tidal seawater
    service), ? 8 years old. Chloride 1-2 Kg/m.
    No significant corrosion of ECR or coating
    disbondment was observed. It was concluded that
    epoxy coating in the selected bridges was
    providing adequate corrosion protection at time
    of the survey.

16
Performance of ECR in California (1995)
  • 4 bridges, 7 to 10 years old in deicing salt
    service. Preliminary findings revealed ECR
    corrosion in 8 of 32 cores examined chloride ?10
    Kg/m3. Some bars were showing no corrosion with
    6 Kg/m3 chloride. Coating disbondment was
    observed at some of the bars. The concrete was
    often dry for extended time periods. The bridges
    examined were not showing severe distress.

17
Performance of ECR in Indiana (1995)
  • Investigations by Purdue University of 5 bridges
    in deicing salt service. Preliminary findings
    showed no corrosion or disbondment ,Chloride ?2.5
    Kgm3 . Corrosion of ECR was seen at one bridge
    at bends in the bar and chloride ?3 Kg/m3.

18
Performance of ECR in Kansas (1995)
  • DOT investigated Bridges in deicing salt
    service made in 1995 24 . Preliminary findings
    show chloride levels at rebar depth less than 0.5
    Kg/3 and good ECR condition.

19
Performance of ECR in Minnesota (1995)
  • DOT in 1994 investigated 10 bridges in deicing
    salt service. Cores taken from cracked
    concrete showed only one core with ECR
    corrosion. Satisfaction with ECR performance was
    reported, indicating that bridge overlays and
    good concreting were also factors in the observed
    performance.

20
Code Amendments
  • Upgrade in specification,
  • -Min. thickness 130m 175 m
  • - Number of holidays 6/m 3/m
  • - Damages 2 1
  • - Improvement of adhesion, handling
  • and storage procedures
  • - Plant certification program

21
Sales in USA
22
Use of FBECR in the Gulf
  • Early 1980s used in some projects in U.A.E.
  • By mid 1980s set up of coating plants in U.A.E.
    (now 5 plants)
  • Early 1990s 3 plants established in Eastern
    Province of S.A.
  • 1996/97 New plant in State of Qatar.
  • Total 9 plants

23
Sales in Saudi Arabia
Tones
Time (Year)
24
Research Experience
  • CE-KFUPM
  • Specimens prisms 120 X 120 X 305 mm four
    bars with 25mm cover
  • Reinforcements Mild steel, galvanized steel,
    FBECR and stainless steel
  • Contamination 2.4, 4.8 and 19.2 kg/m3 of
    chloride
  • Exposure Natural exposure site, Dhahran
    (above ground)

25
Specimens at exposure site
26
Performance Criteria
  • onset and propagation of cracks
  • weight loss in rebar
  • bar condition (rust and pitting)

27
Results (after 7 years exposure)
Black Steel
FBECR
Crack category 1 - No crack 4 - Wide 2 - Fine 5
- Heavy 3 - Medium 6 - Spalling
28
Retrieved bars
29
RI-KFUPM Study
  • Specimens prisms 62.5 X 100 X 305 mm
  • 62.5 X 202 X 305 mm
  • with 25 mm cover
  • Reinforcements FBECR straight bars
  • J-bend bars
  • Exposure 5 sodium chloride solution,
  • in room temp.
  • (Accelerated lab. testing)

30
Results
  • Coating disbondment
  • Corrosion at coating cracks
  • Corrosion started at deformation patterns
  • Corrosion proceeded underneath coating

31
Corrosion underneath coating
32
U.A.E. Study
  • Dubai Municipality, 1991
  • Specimens 150 X 150 X 360 mm with
    10 mm and 30 mm cover
  • Reinforcements FBECR and black steel
  • Exposure -Below ground
  • -Tidal zone
  • -Above ground

33
Results after 3 years
  • FBECR generally in good conditions
  • Some adhesion loss of coating for below and tidal
    specimens
  • Specimens collected from construction sites were
    far from satisfactory w.r.t. ASTM standards

34
Local Construction Practices
  • Improper Cut and Bend at job sites
  • Improper storage at sites
  • No repair for damages
  • Mix of coated and uncoated rebars
  • Unskilled laborers (damages, scratches bending,
    cutting, )

35
Cut and Bend at job sites
36
Storage at sites
37
Coating damages
38
Mix of rebars
39
(No Transcript)
40
Ineffective patching
41
Sharp edge and seem in rebar
42
Gulf Environment Conditions
  • Favorable Corrosion Conditions
  • - High temp. with salt laden humidity
  • - High level of contamination of
  • construction materials

Temp.
R.H.
Cl-
43
CONCLUDING REMARKS
  • Good quality FBECR would provide satisfactory
    protection if constructed with good quality
    concrete.
  • Moisture and temperature of the exposure
    conditions are key factors for the disbondment of
    coating.
  • Epoxy-coating powders shall be handled without
    exposure to high temperature (above 30C).

44
CONCLUDING REMARKS
  • Long storage time for reinforcement and time
    between cleaning and coating should be minimized.
  • Storage time at the construction site should be
    limited.
  • Repair of damaged coating by touch-up should be
    done immediately.
  • Plant fabrication is highly preferable.

45
CONCLUDING REMARKS
  • Bending at site should be carried by proper
    equipment and tools.
  • Mix of uncoated and coated reinforcement should
    be avoided.
  • Construction interruption should be minimized.
  • Manufacturers of rebars should produce more
    suitable product for coating.

46
THANKS
47
Initiation-Propagation Model
Write a Comment
User Comments (0)
About PowerShow.com