Title: Tailings Facilities - An Introduction from an Insurance Perspective
1Tailings Facilities - An Introduction from an
InsurancePerspective
- Basic Planning and Design Considerations
2Typical Mine Site Layout
3Procedures in Tailings Production
- Crushing
- Grinding
- Leaching Concentration
Heating - Dewatering
- Tailings Slurry Disposal
4Tailings Grain Size Curves
5Tailings Impoundments - Operating Components
- Tailings Delivery - pumps, pipelines, and bridges
- Tailings Impoundment - retention dams, tailings,
tailings pond, diversion ditches, and seepage
control - Pond Water Return - pump barge, decant conduits,
6Tailings Impoundment Life Cycle
- Planning
- Construction
- Operation
- Closure
7Key Elements in Tailings Impoundment Design
- Siting Studies
- Retention Dam Design
- Water Management
- Tailings Management
- Contamination - Cyanide and Acid Rock Drainage
8Factors Influencing Impoundment Siting
- Location and elevation relative to the mill
- Topography
- Hydrology and catchment area
- Geology
- Groundwater
- Length of tailings and return-water pipelines
Capital and operating costs for the pumps - Embankment layout Embankment fill requirements
Diversion feasibility - Long-term water accumulation Flood-handling
requirements - Availability of natural borrow type and volume
Seepage losses Foundation stability - Rate and direction of seepage movement
Contamination potential -
9Catchment Diversion Planning
Runoff diverted by dyke
Runoff diverted by conduit beneath
tailings(rare) usually have diversion ditches
10A Cross-Valley Downstream Dam
- 200 ft. high downstream dam in a semi-tropical
area - Decant conduit pond discharge through right
abutment - Dam raised by added slices of fill on downstream
slope
11A Cross-Valley Tailings Dam
- Tailings is discharged to storage area upstream
of the dam. - Clearwater pond is retained by the dam
- Dam and decant are raised as the tailings level
rises
12Basic Tailings Dam Section Types
A1
UPSTREAM
A2, A22A1
CENTRELINE
A3, A33A1
DOWNSTREAM
13Upstream Tailings Dams
14Poderosa Tailings Dam Peru, 1998
15INCO R4 - Modified Upstream
16Centreline Construction
17Brenda Centreline Tailings Dam
18L-L Dam - Centreline Construction
19Downstream Tailings Dam
20Downstream Tailings Dam
21Downstream Construction
22Tailings Dam Design Criteria
- Impoundment must be stable under all static and
transient loads must identify failure modes - Design criteria from CDA FOS of 1.5 for long
term FOS of 1.3 for short term - Impoundment must be stable for seismic loading
and must pass design flood
- Transient load design magnitudes are selected
from consequence-based criteria such as CDA - High consequences mean design to MCE and PMF
- Surface and groundwater quality must meet
regional and global water quality standards
23CLASSIFICATION BASIS
24EARTHQUAKE BASED ON CLASSIFICATION
25INFLOW DESIGN FLOOD BASED ON CLASSIFICATION
26REVIEW FREQUENCY BASED ON CLASSIFICATION
27Typical Dam Zonation - Earthfill
28Internal Seepage Control
29Water Balance
- Water accumulates in tailings impoundment from
tailings transport and runoff - Return water to mill for processing circuit
- Design impoundment water handling so that
impoundment is not overtopped - Want a closed system with no loss to environment
without treatment
30Schematic Water Balance
gt
_
Inflows
Outflows
- Precipitation - Surface Water Runoff - Tailings
Process Water
- Evaporation - Reclaim Water To Mill
SPILLWAY DISCHARGE
Seepage Losses
Pond Storage
Storage In Tailings Voids
31Tailings Management
- The rate of rise of a tailings impoundment
depends on mill production and design of tailings
distribution systems within the pond - Must be able to predict storage requirements with
time so that retention dam construction can stay
ahead of rising tailings surface -
32Tailings Volume Balance
33Tailings Deposition Planning
Construct digital terrain model
Run terrain filling model by spigoting from
different locations
34Tailings Discharge Techniques
Spigotting
Open Discharge
35Single Discharge Point
Tailings discharged into middle of pond forming
beach at slopes less than 1
36Water Quality
- Chemical factors affecting water quality are pH,
salinity, and toxicity - Mill effluents that are products of the leaching
process most likely to cause contamination. Acid
leaching causes low pH increasing heavy metal
solubility - Tailings and waste rock with pyrite may result in
low pH due to production of sulphuric acid by
oxidation. This is ARD (Acid Rock Drainage).
Low pH increases heavy metal solubility which are
toxic at low concentrations. - Cyanide used in gold extraction is highly toxic
but is unstable and rapidly degrades with time
37Closure Design
- All tailings impoundments need to be designed
from the outset so that they can be closed
efficiently Designing for Closure - Closure design is driven by water management
considerations - passing floods and water quality
- Low pH water containing heavy metals persist in
perpetuity must treat with lime before release
or prevent ARD by dry and/or wet covers - Cyanide is not a closure issue because of its
instability
38Tailings Design Optimization
- Unlike water retention dams, tailings dams are
constructed and operated simultaneously - Can optimize performance and reduce cost by
monitoring - Monitoring programs key to improvements but
usually neglected - Technology exists to construct safe tailings
impoundments (same failure rate as water
retaining dams)
39Trends in Tailings Impoundment Design
- Tailings dams are becoming some of the highest in
the world Los Leones in Chile is over 200 m
high Antamina is scheduled to be 230 m high - Closure and abandonment of mine sites in North
America is expensive - The ARD problem is not yet satisfactorily solved
so that mine sites can be abandoned with
confidence - Mining companies are acutely aware of tailings
and environmental problems