Insurance provisions under JCT 1998 and JCT Standard Building Contract 2005 PowerPoint PPT Presentation

presentation player overlay
1 / 24
About This Presentation
Transcript and Presenter's Notes

Title: Insurance provisions under JCT 1998 and JCT Standard Building Contract 2005


1
Insurance provisions under JCT 1998 and JCT
Standard Building Contract 2005
  • Brian Lewis QBE CAR

2
Introduction
  • Most Construction is carried out under a
    standard form of contract with majority of
    commercial work using JCT.
  • A Contractors obligations under a Contract to
    indemnify the Employer or to reinstate any damage
    to the Works and Site Materials are of no effect
    unless the Contractor has adequate funds.
  • It is normally a requirement of a Contract for
    insurance to be taken out to support the
    indemnity requirements of the Contract.

3
Risks in Construction
  • Diverse trades working in close proximity
  • Physical hazards
  • Complicated chains of liability / responsibility
  • Can lead to complex claims

4
Insurance JCT
  • Changes in format but not to the insurance
    provisions which are now included within a
    schedule rather than the body of the contract.
  • Joint Names definition and position of
    sub-contractors clarified
  • JCT 1998 arbitration, whereas 2005 has
    litigation as a default position with arbitration
    as an agreement between parties

5
Indemnity Clauses
  • Clause 20.1 - Requires the Contractor to
    indemnify the Employer for injury on site
  • Clause 20.2 - Requires the Contractor to
    indemnify the employer for liability for injury
    and damage to real and personal property arising
    out of or in the course of or by reason of the
    carrying out of the works ( taking into account
    the minimum stated in the appendix)

6
Clause 21.1.
  • Requirement to insure the Contractors liability
    for death and personal injury to
  • its own direct employees (The minimum
    insurance cover is as stated in the Employers
    Liability (Compulsory Insurance) Act.), and
  • any other person whomsoever arising out of or in
    the course of or caused by the carrying out of
    the Works. (The minimum insurance cover against
    injury and/or death of people other than his own
    employees must comply with the minimum amount of
    cover stated in the Appendix to the Contract.)

7
Clause 21.2
  • Obligation on the Contractor to take out joint
    names insurance

8
Clause Number 22A, 22B or 22C
  • For Damage to the Works and Site Materials, there
    are three options under this heading.
  • Clause 22A is intended for projects involving new
    work where the intention of the parties is that
    the Contractor is to be responsible for the
    insurance. This is to be a Joint Names Policy
    (i.e. the Contractor and the Employer). The
    minimum amount of cover should be the full
    reinstatement value of the Works plus a
    percentage for professional fees. This percentage
    is to be stated in the Appendix to the Contract.

9
  • Clause 22B is also intended for new work but
    where it is the Employer who is responsible for
    obtaining the cover. This is also to be a Joint
    Names Policy (i.e. the Employer and the
    Contractor). The minimum amount of cover should
    be the full reinstatement value of the Works plus
    a percentage for professional fees. This
    percentage is to be stated in the Appendix to the
    Contract.

10
  • Clause 22C is to be used where the work consists
    of refurbishment of, or modifications to, or
    extensions of existing structures. In this
    situation it is the Employer that is responsible
    for the Joint Names All Risk Insurance of the
    Works (under Clause 22C.2). The minimum amount of
    cover should be the full reinstatement value of
    the Works plus a percentage for professional
    fees. This percentage is to be stated in the
    Appendix to the Contract.

11
  • Each of the above insurances are to be All Risk
    insurances. All Risk insurances are defined in
    Clause 22.2 as insurance which provides cover
    against physical loss or damage to work executed
    and Site Materials. However, a long list of
    exceptions are included, and it is apparent that
    All Risk insurance does not in any way cover
    all risks of damage to the Works and Site
    Materials, and the term All Risk insurance is
    therefore a misnomer

12
Clause Number 22C.1
  • Damage to existing structures and their contents
    arising from the Specified Perils (applies to
    contracts involving extensions or refurbishment
    of existing structures).
  • Under Clause 22C.1, the Employer is to take out
    and maintain a Joint Names Policy against damage
    to the existing structures and their contents
    from the Specified Perils. The Specified Perils
    are defined under Clause 1.3 of JCT 98.

13
Clause Number 22D
  • The Employers loss of liquidated damages arising
    from extension of time for loss or damage
    occasioned by any one or more of the Specified
    Perils.
  • Under Clause 25.4.3 of JCT 98, loss or damage
    caused by any of the Specified Perils is a
    Relevant Event which gives a Contractor the right
    to an Extension of Time. In such a circumstance,
    the Employer would not be able to recover
    Liquidated Damages from the Contractor but would
    still incur losses from the delay in completion.

14
  • In situations where the Employer cannot avoid
    liability for delay and the risk of delay from
    the Specified Perils is significant, insurance
    may be his best course of action.
  • Clause 22D insurance is designed for this type of
    situation. It applies only if it is indicated in
    the Appendix to the Contract that insurance under
    that clause may be required. The maximum period
    of delay to be insured against is also to be
    stated there

15
Clause Number 30.3
  • Loss or damage to off-site materials or goods
    from the Specified Perils.
  • Under Clause 30.3, the value of off-site
    materials that are on the list of materials
    annexed to the Contract Bills and intended for
    the Contract may be included in interim
    certificates. A pre-condition for such inclusion
    is that such materials are insured for their full
    value against damage or loss from the Specified
    Perils. The Specified Perils are defined under
    Clause 1.3 of JCT 98.

16
Clause 21.2.1.
  • Injury or damage to property due to collapse,
    subsidence, vibrations, weakening or removal of
    support or lowering of groundwater attributable
    to the carrying out of the Works.
  • The Contractor is only responsible for damage to
    property due to negligence, breach of statutory
    duty, omissions or default on the part of the
    Contractor or of whom the Contractor is
    responsible in law.

17
  • Sometimes damage can occur without any fault on
    the part of the Contractor, and Clause 21.2.1
    envisages that a prudent Employer may wish to
    insure against this type of liability.
  • If that is the case, it should be indicated in
    the Appendix to the Contract that Clause 21.2.1
    insurance may be required, and the amount of
    cover required, per occurrence or series of
    occurrences arising from the same event, must
    also be stated.
  • The insurance must be in the joint names of the
    Contractor and the Employer and must be placed
    with insurers approved by the Employer

18
21.2.1 Insurance
  • Cover is normally arranged with the Contractor's
    Public Liability insurer rather than in isolation
    and covers injury or damage to any property,
    caused by collapse, subsidence, heave, vibration,
    weakening or removal of support or lowering of
    ground water and arising from the carrying out of
    the works.

19
21.2.1 Insurance
  • The usual exclusions for these policies include
    but are not limited to
  • Damage to the works and materials something
    that should be covered by the Contract Works
    insurance.
  • Losses arising from the contractors negligence -
    something that should be covered by the
    Contractor's Public Liability insurance.
  • Losses due to errors and omissions in the
    designing of the works - something that should be
    covered by the Architect's Professional Indemnity
    insurance

20
Conclusions
  • From the above summary it is apparent that the
    insurance provisions remain much the same
  • JCT 2005 has been re-scheduled with the intention
    of making it more user friendly, but the
    substance of the contract (particularly in
    respect of the insurance provisions) remains very
    much as JCT 98.
  • Although the JCT insurance clauses may still
    appear cumbersome or wordy to some, it is
    obviously very difficult to cover all aspects of
    the insurance provisions in a few words.

21
Other Issues for Insurers
  • Suitability of insurance Carried
  • (Limits / Who with / Security / Evidence)
  • BFSC control / evidence that insurances are
    checked?
  • Site security / contractors care of their own
    property?

22
Comparison of Insurance provisions from JCT 98
to JCT 2005.
  • JCT 98 Clause number 21.1.1.1 / JCT 2005 Clause
    number 6.4.1 - Effectively the same insurance
    liability under JCT 2005 as existed under JCT
    98.
  • JCT 98 Clause number 21.2.1 / JCT 2005 Clause
    number 6.5.1 - Effectively the same insurance
    liability under JCT 2005 as existed under JCT
    98.
  • JCT 98 Clause number 22A, 22B or 22C / JCT 2005
    Clause number Clause 7.6, Schedule 3 Options A.
    B or C. - Effectively the same insurance
    liability under JCT 2005 as existed under JCT
    98.

23
  • JCT 98 Clause number 22C.1 / JCT 2005 Clause
    number Clause 6.7, Schedule 3 Option C Clause
    C.1 - Effectively the same insurance liability
    under JCT 2005 as existed under JCT 98.
  • JCT 98 Clause number 22D / JCT 2005 Clause
    number N/A - The option of insurance for the
    Employers loss of Liquidated Damages in the
    event of delays caused by loss or damage
    occasioned by any of the Specified Perils, does
    not appear in JCT 2005.

24
  • JCT 98 Clause number 30.3 / JCT 2005 Clause
    number 4.17.2.2 - Effectively the same insurance
    liability under JCT 2005 as existed under JCT
    98.
  • JCT 98 Clause number N/A / JCT 2005 Clause
    number 6.11 - Where there is a Contractors
    Designed Portion, the Contractor shall forthwith
    after the Contract has been entered into take out
    a Professional Indemnity insurance policy with a
    limit of indemnity of the type and in an amount
    not less than that stated in the Contract
    Particulars.
Write a Comment
User Comments (0)
About PowerShow.com