Title:
1 CIS Case HistoryNACE Eastern Area Conference
- Jeffrey L. DidasColonial Pipeline Company2607
Willard RoadRichmond, VA 23294-3639804-672-2718
2INTRODUCTION
- Close - Interval Potential Surveys (CIS or CIPS)
are performed for many reasons. The primary
purpose of a CIS is to ensure that a pipeline is
cathodically protected in its entirety. - CIS is also used as a method to verify pipeline
integrity, evaluate coating condition and follow
up on areas after pipeline rehabilitation.
3CIS GENERAL DISCUSSION
- Close - Interval Potential Surveys have been
utilized for decades. In the early years it
involved hand reels or multiple hand reels of
wire stretched out between test points and bulky
analog meters which remained stationary at the
test points, with a moving reference electrode(s)
traveling along and over the pipeline.
4CIS GENERAL DISCUSSION
- Todays data loggers and wire dispensers provide
a light weight, accurate and fairly simple
method of recording, analyzing and displaying CIS
data.
5CIS GENERAL DISCUSSION
- Motorized or power reels with several miles of
survey wire supplemented the hand reels and
improved the process, which still used a
stationary analog meter and moving the
electrodes. During the 1970s digital meters,
data logging hardware, small diameter survey wire
and wire dispensers evolved into an over the line
surveyor having all the survey equipment with the
surveyor.
6CIS GENERAL DISCUSSION
- Todays data loggers and wire dispensers provide
a light weight, accurate and fairly simple
method of recording, analyzing and displaying CIS
data. - With todays computer technology and what is
known about the technology, the survey interval
has become fairly standard at 1 m (2.5 feet).
7CIS ISSUES GENERAL DISCUSSION
- CIS specification one is required whether for
internal or external use. - CIS contractor or in house personnel proper
training, experience and OQs are required. - CIS data quality and availability data must be
per the specification, be usable and repeatable
and available in a timely manner upon completion
of the CIS.
8CIS ISSUES - GENERAL DISCUSSION
- Pipeline operators have implemented Integrity
Management Plans (IMPs) which gives them a
long term plan to use for evaluating the
pipelines integrity and implementing a
rehabilitation plan - These evaluations use a combination of internal
inspections using ILI, external inspections using
CIS and DCVG, then wrapping all these programs
together using External Corrosion Direct
Assessment (ECDA), Internal Corrosion Direct
Assessment (ICDA) and Stress Corrosion Direct
Assessment (SCCDA).
9CIS ISSUES and ANSWERS - GENERAL DISCUSSION
- When ILI is not practical for the IMP, CIS
becomes extremely valuable as the primary
component for performing the evaluations. - The CIS will determine the areas not meeting a
cathodic protection (CP) criterion. - The areas not meeting these criteria will be
further evaluated using an above ground coating
evaluation survey and normally a depolarized
potential survey.
10CIS GPS Survey In Progress
- Typical Cross Country Pipeline ROW
11CIS GPS Survey In Progress
- Wheres the pipe? They appear to be lost in the
field.
12CIS Technical Issues
- Locating Pipeline
- Interrupter Accuracy and Quality
- Interruption Cycle
- Reference Electrode Calibration
- Crew Quality
- ROW Conditions
- Level of CP and Coating Quality
13Typical CIS Data Plot
14Data Issues
- Repeatability of Data
- Ability to locate Deficiencies GPS Accuracy
- Data integration into database
15CIS DATA ANALYSIS
- The results of the coating evaluation testing
will drive the rehabilitation program and allow
selection of the rehabilitation method - Which method or combination of methods is
determined by the corrosion engineer analyzing
all the data, performing current require testing,
performing coating conductance and / or quality
surveys, running design calculations for CP
systems and determining the most cost effective
methods.
16CIS Case History
- 32 Products Pipeline
- Installed 1961
- Asphalt Enamel Coating
- Recently had a CP Upgrade Performed
- ILI has had Multiple Runs no corrosion issues
- ON/OFF survey with GPS and depth of cover survey
was run - Areas not meeting -850 ON were addressed
17Results
- 30 anomaly locations were selected for recoat
- 45 anomaly locations were selected for new CP or
upgrading existing CP - 100 compliance was achieved after rehabilitation
was completed and follow up survey run
18Location Selected for Recoating
19Area Being Excavated
20Problem Area Identified and Coating Being Removed
21Entire Area That was Examined
22Area Kept Growing
23Some Coating was Actually Sticking to the Pipe
24Found a Problem at the Area of Investigation
25Problem Remediated
26Abrasive Blasting in Progress
27Recoating in Progress
28Coating Inspection
29Coating Inspection
30Recoating Complete
31Follow Up Survey in Progress
32Summary and Conclusions
- Close Interval Potential Survey is a proven tool
to use to evaluate pipelines to ensure it is
cathodically protected or to locate areas that
are not protected. - Using CIS to determine areas of your pipeline
that require coating rehabilitation does work and
works very well.
33Summary and Conclusions
- CIS data alone should not be used in locating
areas that require coating rehabilitation, but a
combination of CIS data, ILI data (when
available), above ground coating surveys and
competent corrosion engineering analysis of the
entire rehabilitation project is required.