- PowerPoint PPT Presentation

About This Presentation
Title:

Description:

CIS Case History NACE Eastern Area Conference Jeffrey L. Didas Colonial Pipeline Company 2607 Willard Road Richmond, VA 23294-3639 804-672-2718 INTRODUCTION Close ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 34
Provided by: jdi82
Learn more at: http://www.wv4c.org
Category:

less

Transcript and Presenter's Notes

Title:


1
 CIS Case HistoryNACE Eastern Area Conference
  • Jeffrey L. DidasColonial Pipeline Company2607
    Willard RoadRichmond, VA 23294-3639804-672-2718

2
INTRODUCTION
  • Close - Interval Potential Surveys (CIS or CIPS)
    are performed for many reasons. The primary
    purpose of a CIS is to ensure that a pipeline is
    cathodically protected in its entirety.
  • CIS is also used as a method to verify pipeline
    integrity, evaluate coating condition and follow
    up on areas after pipeline rehabilitation.

3
CIS GENERAL DISCUSSION
  • Close - Interval Potential Surveys have been
    utilized for decades. In the early years it
    involved hand reels or multiple hand reels of
    wire stretched out between test points and bulky
    analog meters which remained stationary at the
    test points, with a moving reference electrode(s)
    traveling along and over the pipeline.

4
CIS GENERAL DISCUSSION
  • Todays data loggers and wire dispensers provide
    a light weight, accurate and fairly simple
    method of recording, analyzing and displaying CIS
    data.

5
CIS GENERAL DISCUSSION
  • Motorized or power reels with several miles of
    survey wire supplemented the hand reels and
    improved the process, which still used a
    stationary analog meter and moving the
    electrodes. During the 1970s digital meters,
    data logging hardware, small diameter survey wire
    and wire dispensers evolved into an over the line
    surveyor having all the survey equipment with the
    surveyor.

6
CIS GENERAL DISCUSSION
  • Todays data loggers and wire dispensers provide
    a light weight, accurate and fairly simple
    method of recording, analyzing and displaying CIS
    data.
  • With todays computer technology and what is
    known about the technology, the survey interval
    has become fairly standard at 1 m (2.5 feet).

7
CIS ISSUES GENERAL DISCUSSION
  • CIS specification one is required whether for
    internal or external use.
  • CIS contractor or in house personnel proper
    training, experience and OQs are required.
  • CIS data quality and availability data must be
    per the specification, be usable and repeatable
    and available in a timely manner upon completion
    of the CIS.

8
CIS ISSUES - GENERAL DISCUSSION
  • Pipeline operators have implemented Integrity
    Management Plans (IMPs) which gives them a
    long term plan to use for evaluating the
    pipelines integrity and implementing a
    rehabilitation plan
  • These evaluations use a combination of internal
    inspections using ILI, external inspections using
    CIS and DCVG, then wrapping all these programs
    together using External Corrosion Direct
    Assessment (ECDA), Internal Corrosion Direct
    Assessment (ICDA) and Stress Corrosion Direct
    Assessment (SCCDA).

9
CIS ISSUES and ANSWERS - GENERAL DISCUSSION
  • When ILI is not practical for the IMP, CIS
    becomes extremely valuable as the primary
    component for performing the evaluations.
  • The CIS will determine the areas not meeting a
    cathodic protection (CP) criterion.
  • The areas not meeting these criteria will be
    further evaluated using an above ground coating
    evaluation survey and normally a depolarized
    potential survey.

10
CIS GPS Survey In Progress
  • Typical Cross Country Pipeline ROW

11
CIS GPS Survey In Progress
  • Wheres the pipe? They appear to be lost in the
    field.

12
CIS Technical Issues
  • Locating Pipeline
  • Interrupter Accuracy and Quality
  • Interruption Cycle
  • Reference Electrode Calibration
  • Crew Quality
  • ROW Conditions
  • Level of CP and Coating Quality

13
Typical CIS Data Plot
14
Data Issues
  • Repeatability of Data
  • Ability to locate Deficiencies GPS Accuracy
  • Data integration into database

15
CIS DATA ANALYSIS
  • The results of the coating evaluation testing
    will drive the rehabilitation program and allow
    selection of the rehabilitation method
  • Which method or combination of methods is
    determined by the corrosion engineer analyzing
    all the data, performing current require testing,
    performing coating conductance and / or quality
    surveys, running design calculations for CP
    systems and determining the most cost effective
    methods.

16
CIS Case History
  • 32 Products Pipeline
  • Installed 1961
  • Asphalt Enamel Coating
  • Recently had a CP Upgrade Performed
  • ILI has had Multiple Runs no corrosion issues
  • ON/OFF survey with GPS and depth of cover survey
    was run
  • Areas not meeting -850 ON were addressed

17
Results
  • 30 anomaly locations were selected for recoat
  • 45 anomaly locations were selected for new CP or
    upgrading existing CP
  • 100 compliance was achieved after rehabilitation
    was completed and follow up survey run

18
Location Selected for Recoating
19
Area Being Excavated
20
Problem Area Identified and Coating Being Removed
21
Entire Area That was Examined
22
Area Kept Growing
23
Some Coating was Actually Sticking to the Pipe
24
Found a Problem at the Area of Investigation
25
Problem Remediated
26
Abrasive Blasting in Progress
27
Recoating in Progress
28
Coating Inspection
29
Coating Inspection
30
Recoating Complete
31
Follow Up Survey in Progress
32
Summary and Conclusions
  • Close Interval Potential Survey is a proven tool
    to use to evaluate pipelines to ensure it is
    cathodically protected or to locate areas that
    are not protected.
  • Using CIS to determine areas of your pipeline
    that require coating rehabilitation does work and
    works very well.

33
Summary and Conclusions
  • CIS data alone should not be used in locating
    areas that require coating rehabilitation, but a
    combination of CIS data, ILI data (when
    available), above ground coating surveys and
    competent corrosion engineering analysis of the
    entire rehabilitation project is required.
Write a Comment
User Comments (0)
About PowerShow.com