08:00 Meeting - PowerPoint PPT Presentation

1 / 2
About This Presentation
Title:

08:00 Meeting

Description:

08:00 Meeting Mon. June 28 Fri. June 25 Thurs. June 24 Wed. June 23 Tue. June 22 Mon. June 21 Fri. June 18 8a-4p 8a-4p Mech. Team Build/install protective cage – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 3
Provided by: Larr47
Category:
Tags: meeting | taking | test

less

Transcript and Presenter's Notes

Title: 08:00 Meeting


1
0800 Meeting
Fri. June 18 Mon. June 21 Tue. June 22 Wed. June 23 Thurs. June 24 Fri. June 25 Mon. June 28
8a-4p Mech. Team Fasten TEM to Mini-CAL TEM-TKR flex cable mates Setup for Single Bay LPT Gary Setup for Van Der Graaff test Elec.Team, Online Single Bay LPT 8a-4p Gary, Mech.Team Repair Van Der Graaff CAL pedestal noise calibration Reset CAL thresholds 8a-4p Gary, Mech.Team Repair Van Der Graaff Mech. Team, QA Transport EM2 TEM/TPS and EGSE to bld 33 Inspection of EM2 TEM/TPS Setup for EM2 TEM/TPS bench test Elec.Team, Online EM2 TEM/TPS safe-to-mate test Mech. Team Swap-in EM2 TEM/TPS Elec.Team, Online Single Bay LPT CAL pedestal noise calibration Set CAL thresholds Test runs 8a-4p Gary, Mech. Team Setup for Van De Graaff Test Test Runs Elec.Team, Online Setup for Van De Graaff data taking Collect test data Offline Van De Graaff data analysis (test runs) 8a-4p Gary, Mech. Team Van De Graaff operations Elec.Team Van De Graaff data taking Offline Van De Graaff data analysis 8a-4p Mech. Team Build/install protective cage Elec.Team Single Bay LPT Mech. Team Ship Mini-Tower assembly to bld 84 ELX lab 8a-4p
4p-8p Gary, Mech.Team Repair Van Der Graaff 4p-8p 4p-8p Offline Cosmic Ray data analysis (test runs) 4p-8p Offline Van De Graaff data analysis (test runs) 4p-8p Offline Van De Graaff data analysis 4p-8p Elec.Team Post-ship Single Bay LPT 4p-8p
2
Action Items
  1. Repair Van De Graaff Gary Godfrey, Reggie
    Rogers
  2. Transportation of EM2 TEM/PSU and EGSE to bld 33
    Eliazar Ortiz
  3. Mechanical inspection of EM2 TEM/PSU connectors
    and standoff holes Eliazar Ortiz, Joe Cullinan,
    Tom Borden, Jerry Clinton
  4. Setup for EM2 TEM/PSU bench tests Eliazar Ortiz
  5. Proof test of Mini-Tower assembly lift fixture
    Dave Kiehl
  6. Build Mini-Tower assembly cart/cage Tom Nieland
  7. EM2 TEM/PSU Safe-to-mate Test Brian Horwitz
  8. Swap-in EM2 TEM/PSU Eliazar Ortiz
  9. Setup for Single Bay LPT Eliazar Ortiz
  10. Execute Single Bay LPT (w/ EM2 TEM/PSU) Brian
    Horwitz, John Canfield, Jim Panetta, Lester
    Miller
  11. CAL pedestal and noise calibration (compare w/
    EM1) Brian Horwitz
  12. Execute CAL CPT Brian Horwitz, John Canfield
  13. Execute TKR CPT Brian Horwitz, John Canfield
  14. Setup operator workstations in room 102 John
    Canfield
  15. Operator training (Gary, Tune, Larry, Brian,
    John) for data taking Online, Offline
  16. Check Cosmic Ray test data Xin Chen
Write a Comment
User Comments (0)
About PowerShow.com