Title: ARR/Tariff Proposals of APTRANSCO for FY2005-06
1ARR/Tariff Proposals of APTRANSCO for FY2005-06
- Objections/Suggestions
- by
- Er. K.Raghu
- 28.02.2005
2Consideration of Issues Raised During Public
Hearings
- Several important issues are raised during public
hearings- in addition to those raised in the
original petitions - But most of these issues raised during public
hearings are ignored by the Commission- do not
find any mention in the tariff order - Only issues raised in the Original Petitions are
considered - I request the Commission to consider all the
issues raised during the public hearings also.
3- This presentation consists of issues which have
bearing on ARR of APTRANSCO
41.Separation of Trading From APTRANSCO
5Separation of Trading from Transco
- Section 39 of Electricity Act,2003 provides for
separation of Trading function from APTRANSCO (
from 10th June2005) - At present APTRANSCO is in the business of
Trading, because of Power Purchase Agreements it
entered with various Generating Companies. - Separation of Trading means ?Separation of PPAs
from APTransco - Then who should Take the responsibility of these
PPAs? This will have serious repercussions on the
power sector future in the state.
6Separation of Trading from Transco
OPTION-2
PPAs
Tradeco
OPTION-3
OPTION-1
Genco
Discoms
It appears that the Government has already
decided to allocate PPAs to Discoms
(OPTION-1)ignoring other options
7Separation of Trading from Transco
- Difficulties/Disadvantages in allocating PPAs to
Discoms - Difficulties in Allocation
- Factors affecting Allocation
- Power Requirement of Discoms Based on Historical
or Future trends - Evaluation of Generating Stations Availability
or PLFs of Generating stations - Availability of Fuel
- Additional Fuel Allocations
- Balance Life of Generating stations
8Separation of Trading from Transco
- NPV or PV of Fixed Costs/Variable costs
- GVK, Spectrum,MP Plants Fixed Cost payments vary
with time as they are based on capital cost
recovery method. - Other Gas Projects FC Payments are more or less
uniform over project life, as it is based on unit
cost of Electricity - Impact of lifting APM
9Separation of Trading from Transco
- Imbalances It would create imbalances among
Discoms with respect to Power demand and
availability. - Burden of New institutions like Balancing and
Settlement Committee (BSC) - Impact of Open Access
- If surcharge from OA consumer does not fully
compensate for the loss of cross subsidy ( as per
draft guidelines of MOP/Report of Task force on
Power sector investments and Reforms), then
Discoms with better consumer mix would sufferas
their present BST is kept high, taking existing
favourable Consumer mix into consideration.
10Separation of Trading from Transco
- Need For Uniform Retail Supply Tariff
- Uniform RST among discoms can not be done away
with immediately - Allocation of PPAs on Permanent basis among
Discoms would create problems - Against the spirit of Reforms
- Would not result in achieving Multi Buyer Model
(MBM) in its true spirit - Discoms will lose focus on revenue
collections-results in creation of Mini
Electricity Boards
11Separation of Trading from Transco
- Legal Complications- advantage to IPPs and other
Generators if PPAs are in multiple hands - In view of the above I request the Commission to
re-examine the whole issue of separation of
Trading function from Transco.
12Separation of Trading from Transco
- Alternative
- Allocation of PPAs to APGENCO would be a better
option as it avoids all the above disadvantages - Electricity Act,2003 does not prohibit generators
from taking up Trading activity- so not against
spirit of reforms - SLDC can remain with APTRANSCO as trading is
separated from Transco. - Discoms can concentrate on Consumer service and
Revenue collections - Expertise on power trading is already available
with APGENCO
13Separation of Trading from Transco
- Transition to Multi Buyer Model would be
smooth- slowly Discoms can enter into new
agreements with Generators for additional power
requirements - No additional expenditure- only a trading license
is required - Helps in developing rational Merit Order
Procedure. - Eliminates unnecessary friction between
Generators and Discoms - Allows Genco to effectively utilise its resources
in the ABT regime.
14Separation of Trading from Transco
- In view of the above I request the commission to
advise the Government to entrust the Trading
function to APGENCO, at least on a temporary
basis, by allocating all the existing PPAs. - If allocation of PPAs to Discoms proves
successful elsewhere in the country, government
may consider the same after evaluating those
experiences.
152. Review of Power Purchase Agreements
16Review of PPAs
- Commission in its Tariff Order for 2003-04
stated that it would consider the review of the
concluded PPAs after the detailed judgement of
the Honble High Court at Mumbai was available. - Maharashtra High court order was submitted to the
Commission during 2004-05 Tariff Hearings. - Commission in its Tariff Order for 2004-05 stated
that At this stage, the Commission does not
consider that any proceedings be initiated for
the above purpose. - However it directed APTRANSCO to renegotiate
with the IPPs to reduce the cost of power
purchase keeping in view the substantial
reduction in interest cost and facility of
swapping etc,.
17Review of PPAs
- Commission in its order did not explain why it
had not considered Mumbai High Courts order on
review of PPAs. - The PPA review taken up by the Government has
many inherent limitations as the Government is
not a party to the Power Purchase Agreement - Its effectiveness depends purely on means out
side legal framework. - I request the Commission to immediately take up
review of all the PPAs without leaving the matter
entirely to the Government or APTRANSCO.
183. Excess Payments to IPPs in Violation of
PPAsi).Spectrumii).GVKiii).BSESiv).NCE
projects
19Stop Excess Payments to IPPs- Violation of PPAs
- The following are a few instances where IPPs are
paid in excess of what is due to them as per the
PPAs. - I request the Commission to immediately stop
excess payments being made to IPPs in violation
of the PPAs. - This does not amount to review of PPAs.
- Excess payments to SPECTRUM
- Incentives
- Presently excess payments are being made to
Spectrum Project (216 MW) at Kakinada towards
incentives. - As per the Govt. Of India notification no. S.O.
251(E) Dt. 30/03/1992 published by MOP in Gazette
of India Extrordinary under P-II sections 3-
subsection (ii)?
20Stop Excess Payments to IPPs- Violation of PPAs
- Full fixed charges shall be recoverable at
generation level of 6000 hours/KW/year. For
Generation above 6000 hours/kw/year, the
additional incentive payable shall not exceed
0.7 of ROE, for each percentage point increase
of PLF above the normative level of 6000
hours/kw/year. - The above GOI notification is included as part of
the PPA and the notification is signed by both
the parties.
21Stop Excess Payments to IPPs- Violation of PPAs
- In line with the above notification an incentive
clause is included in the PPA which states that - the Board ( ie APTRANSCO) shall pay for the
actual generation and notional generation above
the threshold level of a PLF of 68.49 an
incentive in the nature of increased ROE in
accordance with the following formula
22Stop Excess Payments to IPPs- Violation of PPAs
- PLF Level of Incentive
- PLF lt 68.5 0.4 increase in ROE for every 1
increase in PLF above 68.5 - 80.5 lt PLFlt 85.5 0.5 increase in ROE for every
1 increase in PLF above 68.5 - PLFgt85.5 0.6 increase in ROE for every 1
increase in PLF above 68.5 - It also states that the Notional generation above
85 PLF shall not be considered for the purpose
of payment of incentive - Since generation above 85 will not be considered
for notional generation, it would be better to
restrict the purchases from IPP to 85PLF
23Stop Excess Payments to IPPs- Violation of PPAs
- Incentive Payable at 85 PLF
- 0.5 increase in ROE for every 1 increase in
PLF above 68.5 - ?(85-68.5) X 0.5/100 X ROE
- EQITY Rs 117.92 Crore ( As per ARR of
APTRANSCO- Page 69) - ROE allowable as per PPA 16 on Equity ROE
(16/100) X 117.92 Rs 18.86 crores
24Stop Excess Payments to IPPs- Violation of PPAs
- Therefore Incentive Payable to Spectrum at 85
PLF - 16.5 x (0.5/100)x 18.86 crore Rs 1.55 crore
- Whereas APTRANSCO has shown incentive payable to
Spectrum as Rs 9.73 crore - This is Rs 8.18 crore more ( 6.27 times) than
what is required to be paid as per PPA.
25Stop Excess Payments to IPPs- Violation of PPAs
- APTRANSCO has stated that it has calculated
incentive based on the formula Equity x
(PLF-68.5)x0.005 . - According to Transco this formula is provided in
the PPA of Spectrum. - But the above formula is not provided in the PPA
of SPECTRUM - APTRANSCO has assumed a formula similar to the
one provided in the incentive clause in GVK PPA. - SPECTRUM PPA on incentives only states that at
85 PLF, - Level of incentive 0.5 increase in ROE for
every 1 increase in PLF above 68.5 - Where as formula assumed by the APTRANSCO takes
increase of 0.5 on Equity and not ROE
26Stop Excess Payments to IPPs- Violation of PPAs
- This has resulted in excess payment of incentive
of Rs 8.18crore/Anum ( As per PPA provision it is
only Rs 1.55 cr) - NO SCOPE FOR ANY AMBIGUITY
- In fact there is no scope for ambiguity in the
application of incentive provision as ROE is
clearly defined in the PPA. - Clause 2.5(e) of GOI notification dt 30/3/92
incorporated in the PPA clearly states that
Return On Equity shall be computed on
the paid up and subscribed capital relatable to
the generating unit, and shall be 16 of such
capital.
27Stop Excess Payments to IPPs- Violation of PPAs
- And thus ROE is a single unit, which is equal to
16 of paid up and subscribed capital. In the
present case ROE 16/100 X 117.92 Rs 18.86
crores - Therefore, 0.5 increase in ROE means
- incentive of 0.5/100 x 18.86
- and not 0.5/100 x 117.92
- I request the Commission to restrict the payment
of incentive to Spectrum project to Rs1.55 crore
28Stop Excess Payments to IPPs- Violation of PPAs
- Excess Payments to GVK Project
- Incentives
- Presently excess payments are being made to GVK
Project (220 MW) at Jegurupadu towards
incentives. - As per the Govt. Of India notification no. S.O.
251(E) Dt. 30/03/1992 published by MOP in Gazette
of India Extrordinary under P-II sections 3-
subsection (ii)
29Stop Excess Payments to IPPs- Violation of PPAs
- Section 1.6 of above notification states that
Full fixed charges shall be recoverable at
generation level of 6000 hours/KW/year. For
Generation above 6000 hours/kw/year, the
additional incentive payable shall not exceed
0.7 of ROE, for each percentage point increase
of PLF above the normative level of 6000
hours/kw/year. - The above GOI notification is included as part of
the PPA and the notification is signed by both
the parties.
30Stop Excess Payments to IPPs- Violation of PPAs
- However the same is not reflected in the
Incentive clause incorporated in the Clause
3.10.2 of the PPA. - Clause 3.10.2 states that The Board shall pay for
actual generation and notional generation above
the target level of PLF of 68.49 on incentive
payment according to the following formula - Incentive paymentEquity x (PLF-68.5)x 0.00525
- In the above formula it is mistakenly stated as
Equity which should have been ROE as per the GOI
notification
31Stop Excess Payments to IPPs- Violation of PPAs
- Implicaiton
- As per GOI notification incentive shall not
exceed 0.7xROE 0.7 x16/100 x Equity
0.00112X Equity - Whereas the incentive clause provides for
incentive of 0.00525x equity, which is 4.68 times
the UPPER LIMIT fixed by the GOI
32Stop Excess Payments to IPPs- Violation of PPAs
- There is a contradiction between two provisions
within the same PPA (ie. incentive clause in
GOI notification and clause 3.10.2 of PPA). - APTRANSCO is paying incentives to GVK as per
clause 3.10.2 which is resulting in higher
payments to GVK. This is against the PPA and GOI
notification - APTRANSCO has shown an amount of Rs 21.21 crore
towards incentive for the year 2005-06. It should
have been Rs 3.39 crores. Thus an additional
amount of Rs 17.82 crore is paid to GVK every
year against the PPA provisions.
33Stop Excess Payments to IPPs- Violation of PPAs
- Since, GVK has also agreed to abide by the GOI
notification, which clearly limits the incentives
to 0.7 of ROE, the incentive payment to GVK
shall be limited to the same - I request the Commission to restrict the payment
of incentive to GVK project to Rs 3.39 crore,
instead of Rs21.21 crore as shown by APTRANSCO.
34Stop Excess Payments to IPPs- Violation of PPAs
- Excess payments towards ROE
- At present APTRANSCO is making payments to both
GVK and Spectrum projects towards ROE - which is equal to 16 of Equity, paid in twelve
monthly installments - Monthly installments paid to these projects is
1/12 of (16 of ROE) - This is resulting in ROE of over 17.2 of equity
per anum considering the interest benefits to the
IPPs. - But section 1.5 of the GOI notification dated
30/3/1992 incorporated in the PPA and signed by
Private parties clearly states that the above
amount of 16 of ROE shall be for the entire
year.
35Stop Excess Payments to IPPs- Violation of PPAs
- The notification also states that, if payments
are made on monthly basis, necessary adjustments
shall be made on actuals at the end of the year. - It can be seen that APTRANSCO is not making any
adjustments towards the end of the year, leading
to excessive payments to IPPs, in violation of
the PPAs. - Total Equity of GVK and Spectrum projects is
244.8117.92 Rs 364.72 crore - Thus additional payment made to these projects
1.2/100 x 364.72 Rs 4.37 crore/Anum - This is clear violation of the PPA provisions
- Hence I request the Commission to direct the
Transco to make necessary adjustments towards the
end of the Year to adjust the excess ROE paid to
these IPPs.
36Stop Excess Payments to IPPs- Violation of PPAs
- Recover the Excess payments made to GVK and
Spectrum Projects - Huge amounts are already paid to GVK and Spectrum
projects towards incentives and ROE in violation
of the provisions of the PPA - Excess payments already made every year
- Towards incentive17.82(GVK)8.49(Spectrum)Rs26.3
1 cr - Towards ROE
Rs 4.37 cr - Total excess payments Rs30.38 cr
- Total amount to be recovered from these two
projects - 30.38 x 8 years of operation Rs 243.04 crore
- Interest also must be recovered
- Hence, I request the Commission to direct
APTRANSCO to recover the amounts from GVK and
Spectrum, which are paid in violation of the
provisions of the Agreements
37Stop Excess Payments to IPPs- Violation of PPAs
- COMMISSION TO IDENTIFY ALL SUCH VIOLATIONS
- The above excess payments made to the IPPs is due
to violation of PPA provisions and reduction of
these costs can not be treated as review of PPAs - There is every likelihood of many more such
violations, whose elimination would reduce the
cost on APTRANSCO and eventually on the consumer.
38Stop Excess Payments to IPPs- Violation of PPAs
- For ex
- Failure on the part of IPPs to achieve ramp up
rate of 4 MW/Minute would allow APTRANSCO to
impose penalty of double the shortfall of such
shortfall in energy. - As per GOI notification incorporated in the PPAs,
all Components of Fixed Cost ( not just ROE )
shall be calculated on annual basis and may be
recovered in monthly installments and due
adjustments shall be made towards the end of the
year - I request the Commission to identify all such
violations immediately and reduce the payments to
IPPs and pass on the benefits to the Consumers.
39Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
- BSES is one of the Short Gestation Project
approved by the GoAP, accordingly PPA was signed
on 31.3.1997 with APTRANSCO - Amendment Agreement submitted to the Commission
in December 2001 for its consent. - Construction of 220MW BSES project at Samarlakota
was completed before the approval of Commission
for the Amended PPA.
40Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
- Since the project was ready to produce energy,
commission has allowed the plant generate energy
and directed APTRANSCO to purchase energy from
BSES at 169 ps/unit, pending approval of Amended
PPA by the Commission - The above approved tariff is substantially higher
than the variable cost of energy ( About Rs
1.00)? this difference between the Total cost (
169 ps) and the variable cost ( about 69 ps) can
be treated as advance amount paid towards
repayment of fixed cost.
41Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
- Subsequently, the commission has consented to the
amended PPA of BSES project, and presently energy
from this project is being purchased as per the
terms of the amended PPA. - Thus the entire Fixed cost of the BSES project
would be recovered from the tariff as per the
terms and conditions laid down in the amended PPA
from the CoD ie 24/12/2002. - This means that the fixed cost paid to this
project before COD is in addition to the total
fixed cost commitment of APTRANSCO to the BSES as
per the PPA.
42Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
- Thus this entire Fixed Cost amount paid to the
BSES prior to the COD has to be recovered now,
including the interest component- otherwise it
amounts to excess fixed cost payments to BSES in
violation of the PPA. - APTRANSCO had purchased energy from this project
- from 21/02/2002 to 24.12.2002 _at_ 169 ps/unit.
- Total quantum of energy purchased from this plant
was about 650 MU.
43Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
- Assuming the variable cost component to be
69ps/unit ( variable cost based on natural gas as
per the supply price of GAIL has to be
considered ) - fixed cost to be recovered is 100 ps/unit.
- Total amount to be recovered from BSES excluding
interest (650/10)x1Rs65Cr. Interest component
has to be added to this amount. - Hence, we request the Commission to recover the
entire excessive amount of Rs 65 cr paid to BSES
prior to the COD. - An amount of Rs 22.8 cr is shown as other
charges paid to BSES during 2003-04. This amount
is not shown in others during FY 2005 and FY
2006. - The same may please be clarified.
44Excess Payments to Non-conventional Energy
Projects
- Restrict payments to contracted capacity only
- Presently payments to NCE projects are being made
based on average monthly PLFs - This is resulting in higher payments to NCE
projects, because NCE projects are at times
generating energy above their contracted
capacities with APTRANSCO. - If NCE projects produce energy above their
contracted capacities, the same shall not be
allowed. - We request the commission to direct APTRANSCO to
install meters capable of taking readings in
15min. block periods, and make payments to NCE
projects accordingly, limiting the payments to
contracted capacities. - We also request the Commission to recover the
excess payments already made
45Excess Payments to Non-conventional Energy
Projects
- New NCE Projects/capacities
- It is reported in the press that the Commission
is directing APTRANSCO to purchase energy from
new NCE projects/capacities - Already NCE projects are imposing unbearable
burden on APTRANSCO and consumers of the state. - Also energy from these projects is not firm and
not reliable - Section 86(e) of the Electricity Act, 2003
enjoins the commission to promote cogeneration
and generation of electricity from renewable
sources of energy and also specify , for purchase
of electricity from such sources , a percentage
of the total consumption of electricity in the
area of a distribution licensee
46Excess Payments to Non-conventional Energy
Projects
- But, it can seen that the purchases from NCE
projects to the total purchases by APTRANSCO in
AP is higher compared to majority of the states
in India and there is no need to allow new
purchases from NCE projects any further. - EA, 2003 also allows third party sales and as
such there is no need for APTRANSCO to buy this
expensive energy - Also, there is no reason why only direct
consumers of Discoms should bear the burden of
these NCE projects. - No where in the EA, 2003 it is stated that only
direct consumers of the utility shall bear entire
burden due to NCE projects.
47Excess Payments to Non-conventional Energy
Projects
- In fact, Section 86(e) of EA,2003 enjoins upon
the Commission to specify, for purchase of
electricity from such sources, a percentage of
the total consumption of electricity in the area
of a distribution licensee. - Thus while specifying the percentage of
purchases from NCE projects it shall consider the
total consumption in the area of a distribution
licensee.
48Excess Payments to Non-conventional Energy
Projects
- This implies that the burden due to these NCE
projects shall be borne by all the consumers in
the area of Distribution licensee. - It means that even the Open Access consumers
shall bear the additional burden due to these NCE
projects. - I request the Commission to distribute the burden
due to NCE projects uniformly on all the
consumers including Open Access consumers.
494. Closure of Nellore Thermal Station
50Closure of Nellore Thermal Station(NTS)
- It is learnt that APGENCO has decided to close
down the NTS - The decision is irrational
- Closure is due to irrational merit order
procedure which takes only the variable cost in
to consideration for dispatch of energy from
generating stations - NTS is located at load centre- reduces TD losses
and also improves voltages in the region. If all
these factors are considered, cost of power from
NTS would be lower than average RST of Discoms
51Closure of Nellore Thermal Station(NTS)
- Also considering the objections from public
during 2004 public hearings, Commission had
directed APTRANSCO to examine the benefits
likely to accrue, by identifying the linkages
between generating stations and the load centers,
duly factoring the transmission losses in to the
variable cost and submit a report to the
Commission by 1st june 2004. - APTRANSCO in its ARR stated that Revised
proposals will be submitted to APERC by
15.12.2004
52Closure of Nellore Thermal Station(NTS)
- Transmission losses and Distribution losses are
not uniform across the entire state. - Transmission system is spread across the entire
state and Transmission losses also vary from
discom to discom. - Also Distribution losses are different in
different distribution companies - Thus the merit order would not be identical for
all the discoms
53Closure of Nellore Thermal Station(NTS)
- It can be seen that Commission is considering
these variations for calculating cost-to-serve
for various consumer categories and also in
allocation of government subsidies among Discoms. - Hence it would be logical to consider these
variations apart from other factors such as
impact of load centre etc,. and revise the merit
order for individual discoms accordingly.
54Closure of Nellore Thermal Station(NTS)
- In the wake of EA2003, it is not wise to close
down NTS. As per the Electricity Act2003, the
Commission is contemplating introduction of Open
Access in distribution starting from Sept2005. - It may be logical for APTRANSCO not to buy energy
from NTS as it may not fall in its Merit Order,
but it will be beneficial for APGENCO to find
Consumers of its own or sell energy to traders
like PTC etc,.instead of closing down the
station. - It appears that the decision to close down the
NTS is taken without carrying out proper Residual
Life Assessment(RLA) studies
55Closure of Nellore Thermal Station(NTS)
- Whatever may be the criteria stated for the
Closure of NTS, it would highlight the defects in
the load forecast approved by the Commission. - If all the projects approved by the Commission
and CGS which are under various stages of
construction start their commercial production,
it is no surprise that all the projects of Genco
will have to be backed down. - In view of the above I request the Commission to
- advise the Government not to close down the NTS
station - revise the merit order procedure and
- advise APGENCO to explore the possibility of
trading energy from NTS.
565. Collection of LD from Gas Projects
57Collection of Liquidated Damages from Gas Projects
- Non-Collection of Liquidated Damages
- None of the Short Gestation projects approved by
the Government during 1997 achieved completion as
per the CoD of PPAs. - As per PPAs Transco shall collect Liquidated
damages to the tune of over Rs 400 cr from these
projects for the failure to complete as per the
schedule - This issue was brought to the notice of the
Commission - Commission agreed with the petitioners view, but
instead of directing APTRANSCO to collect these
charges, allowed APTRANSCO to decide on the
matter. - Till now APTRANSCO has not collected these
charges from Gas Projects. - Commission should direct APTRANSCO to collect
these LDs from gas projects
586. Review of PPAs of Gas Projects
59Review of PPAs of Gas Projects
- Issues involved in the recent order
- Commission on 14/12/04 has passed an order on 4
Gas Projects allowing - a)The scheduled date of completion to be extended
day for day for any delay arising from (i)
non-availability of Natural gas for commercial
operation up to 31-12-2006 and (ii) the time
required for commissioning as per the
construction schedule due to non-availability of
Natural gas.
60Review of PPAs of Gas Projects
- Commission in its order has not made it clear if
it is convinced about the gas availability after
31.12.2006, so that the consumer is not burdened
with huge fixed costs. - GAIL and IPPs have gone back on their earlier
assurances on availability of natural gas to
these projects. - This is the basic premise on which Commission has
earlier gave consent to these projects - Hence Commission should review all these PPAs
afresh through public process.
61Review of PPAs of Gas Projects
- There are many more issues- not just availability
of natural gas- which were raised by the public
during the hearings of these gas projects, which
still have relevance. - For Ex
- APTRANSCO has stated that the burden of fixed
costs due to these projects is Rs 1020 cr. While
projecting this figure Transco made two
assumptions - The APM regime would continue in future
- It can sell entire energy purchased from these
projects - But chances of above assumptions going wrong are
very high, as - GoI had already announced that it would soon lift
the APM on natural gas and other petroleum
products - Transco may not be able to buy/sell the entire
energy from these projects due to several
factors such as
62Review of PPAs of Gas Projects
- various provisions of EA,2003 viz Open Access,
Parallel Licensing, Stand Alone systems etc,.
which will considerably reduce the demand - Efficiency measures introduced by the Government
in Agriculture sector would substantially bring
down consumption - Other new initiatives to reduce TD losses
- If the above factors are taken in to
consideration, because of Take-or-pay
provisions in the Gas Supply Agreements, Fixed
cost burden due to these 4 gas projects would be
about Rs2650 cr - In view of the serious implications of these
projects on the consumers of this state, we
request the Commission to review these PPAs
through public process.
63Collection of Liquidated Damages from Gas Projects
- Also if there is any LD clause for the delay in
the execution of the Gas Projects in the
construction contracts (EPC) entered by the IPPs,
the said amount must be passed on to the
consumers
647. Two Part Tariff
65Purpose of Two Part Tariff
- It is not clear why APTRANSCO is proposing two
part tariff - two part tariff would discourage energy savings
by Discoms as it would commit Discoms for minimum
purchases from Transco. - This results in higher burden on consumer due to
expensive power purchases - It can recover the entire fixed costs based on
the total purchases of discoms at the end of the
year - Necessary adjustment mechanism can be introduced
- Hence I request the Commission to reexamine the
two part tariff proposal by APTRANSCO
66Prayer to the Commission
- To consider issues raised during public hearings
also - Advise Govt to entrust Trading function to
APGENCO - Review all PPAs in the light of Mumbai High Court
order - Stop/Recover excess payments being made to IPPs
in violation of PPAs(GVK,Specturm,BSES and NCE
projects) - To transfer the burden of NCE projects on OA
consumers also - Advise Govt not to close down NTS.
- Collect liquidated damages from gas projects
- Review of PPAs of all the gas projects in view of
non-availability of Gas - Transfer LD paid by EPC contractors to IPPs, if
any - To review Two-Part Tariff proposal of APTRANSCO.
67