ARR/Tariff Proposals of APTRANSCO for FY2005-06 - PowerPoint PPT Presentation

1 / 67
About This Presentation
Title:

ARR/Tariff Proposals of APTRANSCO for FY2005-06

Description:

ARR/Tariff Proposals ... Based on Historical or Future trends Evaluation of Generating Stations: Availability or PLFs of Generating stations Availability of Fuel ... – PowerPoint PPT presentation

Number of Views:89
Avg rating:3.0/5.0
Slides: 68
Provided by: RAG48
Learn more at: http://www.pmger.org
Category:

less

Transcript and Presenter's Notes

Title: ARR/Tariff Proposals of APTRANSCO for FY2005-06


1
ARR/Tariff Proposals of APTRANSCO for FY2005-06
  • Objections/Suggestions
  • by
  • Er. K.Raghu
  • 28.02.2005

2
Consideration of Issues Raised During Public
Hearings
  • Several important issues are raised during public
    hearings- in addition to those raised in the
    original petitions
  • But most of these issues raised during public
    hearings are ignored by the Commission- do not
    find any mention in the tariff order
  • Only issues raised in the Original Petitions are
    considered
  • I request the Commission to consider all the
    issues raised during the public hearings also.

3
  • This presentation consists of issues which have
    bearing on ARR of APTRANSCO

4
1.Separation of Trading From APTRANSCO
5
Separation of Trading from Transco
  • Section 39 of Electricity Act,2003 provides for
    separation of Trading function from APTRANSCO (
    from 10th June2005)
  • At present APTRANSCO is in the business of
    Trading, because of Power Purchase Agreements it
    entered with various Generating Companies.
  • Separation of Trading means ?Separation of PPAs
    from APTransco
  • Then who should Take the responsibility of these
    PPAs? This will have serious repercussions on the
    power sector future in the state.

6
Separation of Trading from Transco
OPTION-2
PPAs
Tradeco
OPTION-3
OPTION-1
  • Transco

Genco
Discoms
It appears that the Government has already
decided to allocate PPAs to Discoms
(OPTION-1)ignoring other options
7
Separation of Trading from Transco
  • Difficulties/Disadvantages in allocating PPAs to
    Discoms
  • Difficulties in Allocation
  • Factors affecting Allocation
  • Power Requirement of Discoms Based on Historical
    or Future trends
  • Evaluation of Generating Stations Availability
    or PLFs of Generating stations
  • Availability of Fuel
  • Additional Fuel Allocations
  • Balance Life of Generating stations

8
Separation of Trading from Transco
  • NPV or PV of Fixed Costs/Variable costs
  • GVK, Spectrum,MP Plants Fixed Cost payments vary
    with time as they are based on capital cost
    recovery method.
  • Other Gas Projects FC Payments are more or less
    uniform over project life, as it is based on unit
    cost of Electricity
  • Impact of lifting APM

9
Separation of Trading from Transco
  • Imbalances It would create imbalances among
    Discoms with respect to Power demand and
    availability.
  • Burden of New institutions like Balancing and
    Settlement Committee (BSC)
  • Impact of Open Access
  • If surcharge from OA consumer does not fully
    compensate for the loss of cross subsidy ( as per
    draft guidelines of MOP/Report of Task force on
    Power sector investments and Reforms), then
    Discoms with better consumer mix would sufferas
    their present BST is kept high, taking existing
    favourable Consumer mix into consideration.

10
Separation of Trading from Transco
  • Need For Uniform Retail Supply Tariff
  • Uniform RST among discoms can not be done away
    with immediately
  • Allocation of PPAs on Permanent basis among
    Discoms would create problems
  • Against the spirit of Reforms
  • Would not result in achieving Multi Buyer Model
    (MBM) in its true spirit
  • Discoms will lose focus on revenue
    collections-results in creation of Mini
    Electricity Boards

11
Separation of Trading from Transco
  • Legal Complications- advantage to IPPs and other
    Generators if PPAs are in multiple hands
  • In view of the above I request the Commission to
    re-examine the whole issue of separation of
    Trading function from Transco.

12
Separation of Trading from Transco
  • Alternative
  • Allocation of PPAs to APGENCO would be a better
    option as it avoids all the above disadvantages
  • Electricity Act,2003 does not prohibit generators
    from taking up Trading activity- so not against
    spirit of reforms
  • SLDC can remain with APTRANSCO as trading is
    separated from Transco.
  • Discoms can concentrate on Consumer service and
    Revenue collections
  • Expertise on power trading is already available
    with APGENCO

13
Separation of Trading from Transco
  1. Transition to Multi Buyer Model would be
    smooth- slowly Discoms can enter into new
    agreements with Generators for additional power
    requirements
  2. No additional expenditure- only a trading license
    is required
  3. Helps in developing rational Merit Order
    Procedure.
  4. Eliminates unnecessary friction between
    Generators and Discoms
  5. Allows Genco to effectively utilise its resources
    in the ABT regime.

14
Separation of Trading from Transco
  • In view of the above I request the commission to
    advise the Government to entrust the Trading
    function to APGENCO, at least on a temporary
    basis, by allocating all the existing PPAs.
  • If allocation of PPAs to Discoms proves
    successful elsewhere in the country, government
    may consider the same after evaluating those
    experiences.

15
2. Review of Power Purchase Agreements
16
Review of PPAs
  • Commission in its Tariff Order for 2003-04
    stated that it would consider the review of the
    concluded PPAs after the detailed judgement of
    the Honble High Court at Mumbai was available.
  • Maharashtra High court order was submitted to the
    Commission during 2004-05 Tariff Hearings.
  • Commission in its Tariff Order for 2004-05 stated
    that At this stage, the Commission does not
    consider that any proceedings be initiated for
    the above purpose.
  • However it directed APTRANSCO to renegotiate
    with the IPPs to reduce the cost of power
    purchase keeping in view the substantial
    reduction in interest cost and facility of
    swapping etc,.

17
Review of PPAs
  • Commission in its order did not explain why it
    had not considered Mumbai High Courts order on
    review of PPAs.
  • The PPA review taken up by the Government has
    many inherent limitations as the Government is
    not a party to the Power Purchase Agreement
  • Its effectiveness depends purely on means out
    side legal framework.
  • I request the Commission to immediately take up
    review of all the PPAs without leaving the matter
    entirely to the Government or APTRANSCO.

18
3. Excess Payments to IPPs in Violation of
PPAsi).Spectrumii).GVKiii).BSESiv).NCE
projects
19
Stop Excess Payments to IPPs- Violation of PPAs
  • The following are a few instances where IPPs are
    paid in excess of what is due to them as per the
    PPAs.
  • I request the Commission to immediately stop
    excess payments being made to IPPs in violation
    of the PPAs.
  • This does not amount to review of PPAs.
  • Excess payments to SPECTRUM
  • Incentives
  • Presently excess payments are being made to
    Spectrum Project (216 MW) at Kakinada towards
    incentives.
  • As per the Govt. Of India notification no. S.O.
    251(E) Dt. 30/03/1992 published by MOP in Gazette
    of India Extrordinary under P-II sections 3-
    subsection (ii)?

20
Stop Excess Payments to IPPs- Violation of PPAs
  • Full fixed charges shall be recoverable at
    generation level of 6000 hours/KW/year. For
    Generation above 6000 hours/kw/year, the
    additional incentive payable shall not exceed
    0.7 of ROE, for each percentage point increase
    of PLF above the normative level of 6000
    hours/kw/year.
  • The above GOI notification is included as part of
    the PPA and the notification is signed by both
    the parties.

21
Stop Excess Payments to IPPs- Violation of PPAs
  • In line with the above notification an incentive
    clause is included in the PPA which states that
  • the Board ( ie APTRANSCO) shall pay for the
    actual generation and notional generation above
    the threshold level of a PLF of 68.49 an
    incentive in the nature of increased ROE in
    accordance with the following formula

22
Stop Excess Payments to IPPs- Violation of PPAs
  • PLF Level of Incentive
  • PLF lt 68.5 0.4 increase in ROE for every 1
    increase in PLF above 68.5
  • 80.5 lt PLFlt 85.5 0.5 increase in ROE for every
    1 increase in PLF above 68.5
  • PLFgt85.5 0.6 increase in ROE for every 1
    increase in PLF above 68.5
  • It also states that the Notional generation above
    85 PLF shall not be considered for the purpose
    of payment of incentive
  • Since generation above 85 will not be considered
    for notional generation, it would be better to
    restrict the purchases from IPP to 85PLF

23
Stop Excess Payments to IPPs- Violation of PPAs
  • Incentive Payable at 85 PLF
  • 0.5 increase in ROE for every 1 increase in
    PLF above 68.5
  • ?(85-68.5) X 0.5/100 X ROE
  • EQITY Rs 117.92 Crore ( As per ARR of
    APTRANSCO- Page 69)
  • ROE allowable as per PPA 16 on Equity ROE
    (16/100) X 117.92 Rs 18.86 crores

24
Stop Excess Payments to IPPs- Violation of PPAs
  • Therefore Incentive Payable to Spectrum at 85
    PLF
  • 16.5 x (0.5/100)x 18.86 crore Rs 1.55 crore
  • Whereas APTRANSCO has shown incentive payable to
    Spectrum as Rs 9.73 crore
  • This is Rs 8.18 crore more ( 6.27 times) than
    what is required to be paid as per PPA.

25
Stop Excess Payments to IPPs- Violation of PPAs
  • APTRANSCO has stated that it has calculated
    incentive based on the formula Equity x
    (PLF-68.5)x0.005 .
  • According to Transco this formula is provided in
    the PPA of Spectrum.
  • But the above formula is not provided in the PPA
    of SPECTRUM
  • APTRANSCO has assumed a formula similar to the
    one provided in the incentive clause in GVK PPA.
  • SPECTRUM PPA on incentives only states that at
    85 PLF,
  • Level of incentive 0.5 increase in ROE for
    every 1 increase in PLF above 68.5
  • Where as formula assumed by the APTRANSCO takes
    increase of 0.5 on Equity and not ROE

26
Stop Excess Payments to IPPs- Violation of PPAs
  • This has resulted in excess payment of incentive
    of Rs 8.18crore/Anum ( As per PPA provision it is
    only Rs 1.55 cr)
  • NO SCOPE FOR ANY AMBIGUITY
  • In fact there is no scope for ambiguity in the
    application of incentive provision as ROE is
    clearly defined in the PPA.
  • Clause 2.5(e) of GOI notification dt 30/3/92
    incorporated in the PPA clearly states that
    Return On Equity shall be computed on
    the paid up and subscribed capital relatable to
    the generating unit, and shall be 16 of such
    capital.

27
Stop Excess Payments to IPPs- Violation of PPAs
  • And thus ROE is a single unit, which is equal to
    16 of paid up and subscribed capital. In the
    present case ROE 16/100 X 117.92 Rs 18.86
    crores
  • Therefore, 0.5 increase in ROE means
  • incentive of 0.5/100 x 18.86
  • and not 0.5/100 x 117.92
  • I request the Commission to restrict the payment
    of incentive to Spectrum project to Rs1.55 crore

28
Stop Excess Payments to IPPs- Violation of PPAs
  • Excess Payments to GVK Project
  • Incentives
  • Presently excess payments are being made to GVK
    Project (220 MW) at Jegurupadu towards
    incentives.
  • As per the Govt. Of India notification no. S.O.
    251(E) Dt. 30/03/1992 published by MOP in Gazette
    of India Extrordinary under P-II sections 3-
    subsection (ii)

29
Stop Excess Payments to IPPs- Violation of PPAs
  • Section 1.6 of above notification states that
    Full fixed charges shall be recoverable at
    generation level of 6000 hours/KW/year. For
    Generation above 6000 hours/kw/year, the
    additional incentive payable shall not exceed
    0.7 of ROE, for each percentage point increase
    of PLF above the normative level of 6000
    hours/kw/year.
  • The above GOI notification is included as part of
    the PPA and the notification is signed by both
    the parties.

30
Stop Excess Payments to IPPs- Violation of PPAs
  • However the same is not reflected in the
    Incentive clause incorporated in the Clause
    3.10.2 of the PPA.
  • Clause 3.10.2 states that The Board shall pay for
    actual generation and notional generation above
    the target level of PLF of 68.49 on incentive
    payment according to the following formula
  • Incentive paymentEquity x (PLF-68.5)x 0.00525
  • In the above formula it is mistakenly stated as
    Equity which should have been ROE as per the GOI
    notification

31
Stop Excess Payments to IPPs- Violation of PPAs
  • Implicaiton
  • As per GOI notification incentive shall not
    exceed 0.7xROE 0.7 x16/100 x Equity
    0.00112X Equity
  • Whereas the incentive clause provides for
    incentive of 0.00525x equity, which is 4.68 times
    the UPPER LIMIT fixed by the GOI

32
Stop Excess Payments to IPPs- Violation of PPAs
  • There is a contradiction between two provisions
    within the same PPA (ie. incentive clause in
    GOI notification and clause 3.10.2 of PPA).
  • APTRANSCO is paying incentives to GVK as per
    clause 3.10.2 which is resulting in higher
    payments to GVK. This is against the PPA and GOI
    notification
  • APTRANSCO has shown an amount of Rs 21.21 crore
    towards incentive for the year 2005-06. It should
    have been Rs 3.39 crores. Thus an additional
    amount of Rs 17.82 crore is paid to GVK every
    year against the PPA provisions.

33
Stop Excess Payments to IPPs- Violation of PPAs
  • Since, GVK has also agreed to abide by the GOI
    notification, which clearly limits the incentives
    to 0.7 of ROE, the incentive payment to GVK
    shall be limited to the same
  • I request the Commission to restrict the payment
    of incentive to GVK project to Rs 3.39 crore,
    instead of Rs21.21 crore as shown by APTRANSCO.

34
Stop Excess Payments to IPPs- Violation of PPAs
  • Excess payments towards ROE
  • At present APTRANSCO is making payments to both
    GVK and Spectrum projects towards ROE
  • which is equal to 16 of Equity, paid in twelve
    monthly installments
  • Monthly installments paid to these projects is
    1/12 of (16 of ROE)
  • This is resulting in ROE of over 17.2 of equity
    per anum considering the interest benefits to the
    IPPs.
  • But section 1.5 of the GOI notification dated
    30/3/1992 incorporated in the PPA and signed by
    Private parties clearly states that the above
    amount of 16 of ROE shall be for the entire
    year.

35
Stop Excess Payments to IPPs- Violation of PPAs
  • The notification also states that, if payments
    are made on monthly basis, necessary adjustments
    shall be made on actuals at the end of the year.
  • It can be seen that APTRANSCO is not making any
    adjustments towards the end of the year, leading
    to excessive payments to IPPs, in violation of
    the PPAs.
  • Total Equity of GVK and Spectrum projects is
    244.8117.92 Rs 364.72 crore
  • Thus additional payment made to these projects
    1.2/100 x 364.72 Rs 4.37 crore/Anum
  • This is clear violation of the PPA provisions
  • Hence I request the Commission to direct the
    Transco to make necessary adjustments towards the
    end of the Year to adjust the excess ROE paid to
    these IPPs.

36
Stop Excess Payments to IPPs- Violation of PPAs
  • Recover the Excess payments made to GVK and
    Spectrum Projects
  • Huge amounts are already paid to GVK and Spectrum
    projects towards incentives and ROE in violation
    of the provisions of the PPA
  • Excess payments already made every year
  • Towards incentive17.82(GVK)8.49(Spectrum)Rs26.3
    1 cr
  • Towards ROE
    Rs 4.37 cr
  • Total excess payments Rs30.38 cr
  • Total amount to be recovered from these two
    projects
  • 30.38 x 8 years of operation Rs 243.04 crore
  • Interest also must be recovered
  • Hence, I request the Commission to direct
    APTRANSCO to recover the amounts from GVK and
    Spectrum, which are paid in violation of the
    provisions of the Agreements

37
Stop Excess Payments to IPPs- Violation of PPAs
  • COMMISSION TO IDENTIFY ALL SUCH VIOLATIONS
  • The above excess payments made to the IPPs is due
    to violation of PPA provisions and reduction of
    these costs can not be treated as review of PPAs
  • There is every likelihood of many more such
    violations, whose elimination would reduce the
    cost on APTRANSCO and eventually on the consumer.

38
Stop Excess Payments to IPPs- Violation of PPAs
  • For ex
  • Failure on the part of IPPs to achieve ramp up
    rate of 4 MW/Minute would allow APTRANSCO to
    impose penalty of double the shortfall of such
    shortfall in energy.
  • As per GOI notification incorporated in the PPAs,
    all Components of Fixed Cost ( not just ROE )
    shall be calculated on annual basis and may be
    recovered in monthly installments and due
    adjustments shall be made towards the end of the
    year
  • I request the Commission to identify all such
    violations immediately and reduce the payments to
    IPPs and pass on the benefits to the Consumers.

39
Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
  • BSES is one of the Short Gestation Project
    approved by the GoAP, accordingly PPA was signed
    on 31.3.1997 with APTRANSCO
  • Amendment Agreement submitted to the Commission
    in December 2001 for its consent.
  • Construction of 220MW BSES project at Samarlakota
    was completed before the approval of Commission
    for the Amended PPA.

40
Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
  • Since the project was ready to produce energy,
    commission has allowed the plant generate energy
    and directed APTRANSCO to purchase energy from
    BSES at 169 ps/unit, pending approval of Amended
    PPA by the Commission
  • The above approved tariff is substantially higher
    than the variable cost of energy ( About Rs
    1.00)? this difference between the Total cost (
    169 ps) and the variable cost ( about 69 ps) can
    be treated as advance amount paid towards
    repayment of fixed cost.

41
Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
  • Subsequently, the commission has consented to the
    amended PPA of BSES project, and presently energy
    from this project is being purchased as per the
    terms of the amended PPA.
  • Thus the entire Fixed cost of the BSES project
    would be recovered from the tariff as per the
    terms and conditions laid down in the amended PPA
    from the CoD ie 24/12/2002.
  • This means that the fixed cost paid to this
    project before COD is in addition to the total
    fixed cost commitment of APTRANSCO to the BSES as
    per the PPA.

42
Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
  • Thus this entire Fixed Cost amount paid to the
    BSES prior to the COD has to be recovered now,
    including the interest component- otherwise it
    amounts to excess fixed cost payments to BSES in
    violation of the PPA.
  • APTRANSCO had purchased energy from this project
  • from 21/02/2002 to 24.12.2002 _at_ 169 ps/unit.
  • Total quantum of energy purchased from this plant
    was about 650 MU.

43
Recovery of Excess Fixed Costs Paid to BSES
before Commercial Operation Date
  • Assuming the variable cost component to be
    69ps/unit ( variable cost based on natural gas as
    per the supply price of GAIL has to be
    considered )
  • fixed cost to be recovered is 100 ps/unit.
  • Total amount to be recovered from BSES excluding
    interest (650/10)x1Rs65Cr. Interest component
    has to be added to this amount.
  • Hence, we request the Commission to recover the
    entire excessive amount of Rs 65 cr paid to BSES
    prior to the COD.
  • An amount of Rs 22.8 cr is shown as other
    charges paid to BSES during 2003-04. This amount
    is not shown in others during FY 2005 and FY
    2006.
  • The same may please be clarified.

44
Excess Payments to Non-conventional Energy
Projects
  • Restrict payments to contracted capacity only
  • Presently payments to NCE projects are being made
    based on average monthly PLFs
  • This is resulting in higher payments to NCE
    projects, because NCE projects are at times
    generating energy above their contracted
    capacities with APTRANSCO.
  • If NCE projects produce energy above their
    contracted capacities, the same shall not be
    allowed.
  • We request the commission to direct APTRANSCO to
    install meters capable of taking readings in
    15min. block periods, and make payments to NCE
    projects accordingly, limiting the payments to
    contracted capacities.
  • We also request the Commission to recover the
    excess payments already made

45
Excess Payments to Non-conventional Energy
Projects
  • New NCE Projects/capacities
  • It is reported in the press that the Commission
    is directing APTRANSCO to purchase energy from
    new NCE projects/capacities
  • Already NCE projects are imposing unbearable
    burden on APTRANSCO and consumers of the state.
  • Also energy from these projects is not firm and
    not reliable
  • Section 86(e) of the Electricity Act, 2003
    enjoins the commission to promote cogeneration
    and generation of electricity from renewable
    sources of energy and also specify , for purchase
    of electricity from such sources , a percentage
    of the total consumption of electricity in the
    area of a distribution licensee

46
Excess Payments to Non-conventional Energy
Projects
  • But, it can seen that the purchases from NCE
    projects to the total purchases by APTRANSCO in
    AP is higher compared to majority of the states
    in India and there is no need to allow new
    purchases from NCE projects any further.
  • EA, 2003 also allows third party sales and as
    such there is no need for APTRANSCO to buy this
    expensive energy
  • Also, there is no reason why only direct
    consumers of Discoms should bear the burden of
    these NCE projects.
  • No where in the EA, 2003 it is stated that only
    direct consumers of the utility shall bear entire
    burden due to NCE projects.

47
Excess Payments to Non-conventional Energy
Projects
  • In fact, Section 86(e) of EA,2003 enjoins upon
    the Commission to specify, for purchase of
    electricity from such sources, a percentage of
    the total consumption of electricity in the area
    of a distribution licensee.
  • Thus while specifying the percentage of
    purchases from NCE projects it shall consider the
    total consumption in the area of a distribution
    licensee.

48
Excess Payments to Non-conventional Energy
Projects
  • This implies that the burden due to these NCE
    projects shall be borne by all the consumers in
    the area of Distribution licensee.
  • It means that even the Open Access consumers
    shall bear the additional burden due to these NCE
    projects.
  • I request the Commission to distribute the burden
    due to NCE projects uniformly on all the
    consumers including Open Access consumers.

49
4. Closure of Nellore Thermal Station
50
Closure of Nellore Thermal Station(NTS)
  • It is learnt that APGENCO has decided to close
    down the NTS
  • The decision is irrational
  • Closure is due to irrational merit order
    procedure which takes only the variable cost in
    to consideration for dispatch of energy from
    generating stations
  • NTS is located at load centre- reduces TD losses
    and also improves voltages in the region. If all
    these factors are considered, cost of power from
    NTS would be lower than average RST of Discoms

51
Closure of Nellore Thermal Station(NTS)
  • Also considering the objections from public
    during 2004 public hearings, Commission had
    directed APTRANSCO to examine the benefits
    likely to accrue, by identifying the linkages
    between generating stations and the load centers,
    duly factoring the transmission losses in to the
    variable cost and submit a report to the
    Commission by 1st june 2004.
  • APTRANSCO in its ARR stated that Revised
    proposals will be submitted to APERC by
    15.12.2004

52
Closure of Nellore Thermal Station(NTS)
  • Transmission losses and Distribution losses are
    not uniform across the entire state.
  • Transmission system is spread across the entire
    state and Transmission losses also vary from
    discom to discom.
  • Also Distribution losses are different in
    different distribution companies
  • Thus the merit order would not be identical for
    all the discoms

53
Closure of Nellore Thermal Station(NTS)
  • It can be seen that Commission is considering
    these variations for calculating cost-to-serve
    for various consumer categories and also in
    allocation of government subsidies among Discoms.
  • Hence it would be logical to consider these
    variations apart from other factors such as
    impact of load centre etc,. and revise the merit
    order for individual discoms accordingly.

54
Closure of Nellore Thermal Station(NTS)
  • In the wake of EA2003, it is not wise to close
    down NTS. As per the Electricity Act2003, the
    Commission is contemplating introduction of Open
    Access in distribution starting from Sept2005.
  • It may be logical for APTRANSCO not to buy energy
    from NTS as it may not fall in its Merit Order,
    but it will be beneficial for APGENCO to find
    Consumers of its own or sell energy to traders
    like PTC etc,.instead of closing down the
    station.
  • It appears that the decision to close down the
    NTS is taken without carrying out proper Residual
    Life Assessment(RLA) studies

55
Closure of Nellore Thermal Station(NTS)
  • Whatever may be the criteria stated for the
    Closure of NTS, it would highlight the defects in
    the load forecast approved by the Commission.
  • If all the projects approved by the Commission
    and CGS which are under various stages of
    construction start their commercial production,
    it is no surprise that all the projects of Genco
    will have to be backed down.
  • In view of the above I request the Commission to
  • advise the Government not to close down the NTS
    station
  • revise the merit order procedure and
  • advise APGENCO to explore the possibility of
    trading energy from NTS.

56
5. Collection of LD from Gas Projects
57
Collection of Liquidated Damages from Gas Projects
  • Non-Collection of Liquidated Damages
  • None of the Short Gestation projects approved by
    the Government during 1997 achieved completion as
    per the CoD of PPAs.
  • As per PPAs Transco shall collect Liquidated
    damages to the tune of over Rs 400 cr from these
    projects for the failure to complete as per the
    schedule
  • This issue was brought to the notice of the
    Commission
  • Commission agreed with the petitioners view, but
    instead of directing APTRANSCO to collect these
    charges, allowed APTRANSCO to decide on the
    matter.
  • Till now APTRANSCO has not collected these
    charges from Gas Projects.
  • Commission should direct APTRANSCO to collect
    these LDs from gas projects

58
6. Review of PPAs of Gas Projects
59
Review of PPAs of Gas Projects
  • Issues involved in the recent order
  • Commission on 14/12/04 has passed an order on 4
    Gas Projects allowing
  • a)The scheduled date of completion to be extended
    day for day for any delay arising from (i)
    non-availability of Natural gas for commercial
    operation up to 31-12-2006 and (ii) the time
    required for commissioning as per the
    construction schedule due to non-availability of
    Natural gas.

60
Review of PPAs of Gas Projects
  • Commission in its order has not made it clear if
    it is convinced about the gas availability after
    31.12.2006, so that the consumer is not burdened
    with huge fixed costs.
  • GAIL and IPPs have gone back on their earlier
    assurances on availability of natural gas to
    these projects.
  • This is the basic premise on which Commission has
    earlier gave consent to these projects
  • Hence Commission should review all these PPAs
    afresh through public process.

61
Review of PPAs of Gas Projects
  • There are many more issues- not just availability
    of natural gas- which were raised by the public
    during the hearings of these gas projects, which
    still have relevance.
  • For Ex
  • APTRANSCO has stated that the burden of fixed
    costs due to these projects is Rs 1020 cr. While
    projecting this figure Transco made two
    assumptions
  • The APM regime would continue in future
  • It can sell entire energy purchased from these
    projects
  • But chances of above assumptions going wrong are
    very high, as
  • GoI had already announced that it would soon lift
    the APM on natural gas and other petroleum
    products
  • Transco may not be able to buy/sell the entire
    energy from these projects due to several
    factors such as

62
Review of PPAs of Gas Projects
  • various provisions of EA,2003 viz Open Access,
    Parallel Licensing, Stand Alone systems etc,.
    which will considerably reduce the demand
  • Efficiency measures introduced by the Government
    in Agriculture sector would substantially bring
    down consumption
  • Other new initiatives to reduce TD losses
  • If the above factors are taken in to
    consideration, because of Take-or-pay
    provisions in the Gas Supply Agreements, Fixed
    cost burden due to these 4 gas projects would be
    about Rs2650 cr
  • In view of the serious implications of these
    projects on the consumers of this state, we
    request the Commission to review these PPAs
    through public process.

63
Collection of Liquidated Damages from Gas Projects
  • Also if there is any LD clause for the delay in
    the execution of the Gas Projects in the
    construction contracts (EPC) entered by the IPPs,
    the said amount must be passed on to the
    consumers

64
7. Two Part Tariff
65
Purpose of Two Part Tariff
  • It is not clear why APTRANSCO is proposing two
    part tariff
  • two part tariff would discourage energy savings
    by Discoms as it would commit Discoms for minimum
    purchases from Transco.
  • This results in higher burden on consumer due to
    expensive power purchases
  • It can recover the entire fixed costs based on
    the total purchases of discoms at the end of the
    year
  • Necessary adjustment mechanism can be introduced
  • Hence I request the Commission to reexamine the
    two part tariff proposal by APTRANSCO

66
Prayer to the Commission
  1. To consider issues raised during public hearings
    also
  2. Advise Govt to entrust Trading function to
    APGENCO
  3. Review all PPAs in the light of Mumbai High Court
    order
  4. Stop/Recover excess payments being made to IPPs
    in violation of PPAs(GVK,Specturm,BSES and NCE
    projects)
  5. To transfer the burden of NCE projects on OA
    consumers also
  6. Advise Govt not to close down NTS.
  7. Collect liquidated damages from gas projects
  8. Review of PPAs of all the gas projects in view of
    non-availability of Gas
  9. Transfer LD paid by EPC contractors to IPPs, if
    any
  10. To review Two-Part Tariff proposal of APTRANSCO.

67
  • Thank you
Write a Comment
User Comments (0)
About PowerShow.com