Title: DSM and Resource Planning
1- DSM and Resource Planning
- Jayant Sathaye, Amol Phadke and Ranjit Bharvirkar
- Energy Analysis Program
- Lawrence Berkeley National Laboratory
- Berkeley, CA
- Bob Lieberman
- Regulatory Assistance Project
- Presented at the
- Forum of Indian Regulators
- 11 June 2009
- Work supported by the US Departments of State and
Energy
2Lawrence Berkeley National Laboratory
- Managed by the University of California for the
US Dept of Energy - Founded in 1931, about 4000 staff
- 12 Nobel Prizes IPCC (2008) Jayant Sathaye
- Utility programs
- Distribution loss reduction
- Demand-side management programs
- Load research and generation planning
- Transmission reliability
- Renewable energy
-
3Regulatory Assistance Project (RAP)
- RAP is a non-profit organization providing
technical and educational assistance to
government officials on energy and environmental
issues. RAP is funded by US Department of Energy,
several foundations, and international agencies.
We have worked in 40 states and 16 nations. - Bob Lieberman
- Illinois utility regulator for the last five
years. Term ended June 1st, 2009 - Ran Chicago-based NGO that developed and ran
energy efficiency and demand response programs - Implemented integrated resource planning in
Illinois
4Contents
- I Overview and Macro impacts
- Dr. Jayant Sathaye
- II. Demand Side Power Purchase
- -- Dr. Amol Phadke
- III ARR and Tariff Impact and Regulatory
Treatment of DSM - -- Dr. Amol Phadke
- IV Implementing DSM and Regulatory Perspective
- -- Ranjit Bharvirkar
- -- Bob Lieberman
- V. Next Steps
5Asia Pacific Partnership (APP)
- 8 Participating Countries Australia, Canada,
China, India, Japan, Republic of Korea and the
United States - Eight task forces including one on power
generation, transmission, distribution and demand
management - Goal To develop, deploy and transfer cleaner,
more efficient technologies and to meet national
pollution reduction, energy security and climate
change concerns consistent with the principles of
the U.N. Framework Convention on Climate Change
(UNFCCC). - Assist partners to build human and institutional
capacity to strengthen cooperative efforts, and
to seek opportunities to engage the private
sector.
6Electricity Demand Savings Potential (Percentage,
2030)
7(No Transcript)
8(No Transcript)
9Memoranda of Understanding (MOU)
- Maharashtra MOU signed in December 2007
- Maharashtra Electricity Regulatory Commission
- Former Chairman Dr. Pramod Deo
- California Energy Commission
- Commissioner Dr. Art Rosenfeld
- California Public Utilities Commission
- Commissioner Dian Grueneich
- Lawrence Berkeley National Laboratory
- Former Director Dr. Steve Chu (Current Energy
Secretary) - Similar MOUs signed with the Delhi Electricity
Regulatory Commission (Shri Berjinder Singh) and
the Forum of Regulators (Dr. Pramod Deo) in March
2009
10Maharashtra and Delhi MOU Scope of Cooperation
- The Parties will endeavor to promote information
exchanges and future joint research activities in
the following areas - Energy efficiency and Demand Side Management
policies and programs - Regulatory policies for renewable energy
development - Integrated Resource Planning
- Electricity regulation and governance
- Transmission pricing framework
- Balancing market framework in Maharashtra
- Market development through open access and
consumer choice
11Demand-side Management of Efficiency Project
Motivation
- Reducing carbon emissions from electricity use
DSM Programs (NAPCC, 11th Five Year Plan) - Electricity shortage accompanied by blackouts and
load shedding is common across India - In Maharashtra, electricity deficit was 4800 MW
in 2008 or more than 25 of available capacity
12Maharashtra Electricity shortage
29 shortage
11/30/2020
Dr. Jayant Sathaye
12
13Maharashtra Project Motivation
- Electricity shortage
- Affects industrial production quantity and
quality, - Lower production and sales lead to reduced sales
tax payment - Government loses sales tax revenue
- LBNL estimates sales tax loss of 20 cents/kWh
- Shortage met partially by extensive use of
inefficient diesel and gasoline micro generators
and hence high CO2 emissions - Savings potential
- Energy savings potential of about 6,800 GWh/year
- CO2 savings potential of 3-5 Mt CO2/year
14India Power Supply Capacity and Peak
DemandReference Scenario with Shortage
- Assuming that from 2009 onwards deficit is 10
and12,500 MW of new capacity - is constructed each year for three years
- Total investment for the 11th Five Year Plan
would be Rs. 250 thousand crores
15India Power Supply Capacity and Peak
DemandEfficiency Scenario with No Shortage
- Assuming that from 2007 onwards efficiency
improvements (4300 MW/year) reduce deficit.
Potential exists to eliminate
deficit. - Construction of new power plants is reduced to
about 9400 MW/year - Total investment for efficiency and supply power
plants is still the same as that in the reference
scenario Rs. 250 thousand crores
16Efficiency Scenario with No Shortage Efficiency
Options
Energy Efficiency Measure Investment (Rs./kW) Daily Use (Hours/day) Peak Demand Savings (MW) 2008 Electricity Savings (TWh) 2008
Variable speed drives in industry 4,700 11 948 3.8
Ag. Pump Rectification 9,400 8 655 1.9
Motor rewinding and downsizing 10,810 10 914 3.3
High efficiency agricultural pump sets 8,460 8 715 2.1
Improved high efficiency refrigerators 14,100 12 320 1.4
CFL and Electronic Ballasts 9,400 4 821 1.2
Total Energy Efficiency Savings (MW) 4,372 13.7
Supply Capacity Additions (MW) 46,624 9,772
17Macro-economic Results
- Assuming identical investment in each of the two
scenarios for the 11th Plan Rs. 250 thousand
crores - Annual average electricity savings of efficiency
scenario - 41 TWh/year
- Assuming business use of saved electricity is 50
-- 20 TWh/yr - Total increase in business output
- Rs. 180 thousand crores/year
- Potential sales tax Rs. 12 thousand crores per
year - Assuming Rs. 6/kWh sales tax
18Demand Side Power Purchase
19Demand Side Power Purchase Basics
- Demand side Power Purchase is a bundled set of
energy efficiency (EE) programs that are designed
to deliver the energy and capacity equivalent of
a power purchase on the supply side. - purchase negawatts and negawatt-hours that
are functionally equivalent to the kilowatts and
kilowatt-hours procured - Can resemble a conventional peaking power
purchase by emphasizing efficiency measures (and
demand response) that reduce electricity during
periods of peak power consumption. - Can resemble a base-load power purchase
emphasizing measures to reduce consumption during
all hours of the day.
20Will you Approve This Peak Load Power Purchase?
One year contract 500 MW during the four hours of evening peak over the year 730 GWh 500 MW during the four hours of evening peak over the year 730 GWh
Mysterious Regular
Rs/Unit 1.2 5
Total Cost Rs Cr/ Year 88 Cr. 365 Cr.
21What is this Mysterious Power Purchase?
- Saving 400 MW during the evening peak hours at
the load end gt 500 MW generation at the bus bar - What does it take to saving 400 MW at the load
end - Replacing 88 lakh incandescent with CFLs
- 45 Watt saving/replacement 88 lackh
replacements 400 MW saving - How much does it cost
- If the utility decides to give the CFLs at the
price of incandescent lamps, 100 Rs subsidy
needed/bulb - Total expenditure 88 Cr less that one third of
the expenditure of the supply side !
22Comparing Supply and Demand Side Power Purchase
- Cost of demand side power purchase per unit
- (Annualized incremental capital cost)/(saving per
year ) - CFL example (88 Cr)/(730 GWh) 1.2 Rs/Unit
- One important different Demand side power
purchase appears happens at the consumer end
(avoids losses) - Power purchase cost of 5 Rs/Unit translates to
more than 8 Rs/Unit when it lands at the
consumers doorstep due to lossess
23Many Demand Side Power Purchase Options Delhi
Example
CFL T5 LPG WH NG WH Solar WH AC Refrigerators
Peak power saving at bus bar (W) 49 29 2,647 2,647 2,647 233 13
Total Energy saving kWh/yr 79 46 529 529 529 565 133
Cost of Demand Side Power Purchase Rs/kWh 1.29 2.25 2.74 1.26 5.00 1.16 0.70
24Demand Side Power Purchase Merit Order Stack
Utility Benefit
Average Tariff
Consumer Benefit
25Least Cost Power Rationale DERC Example
- The Commission is keen to see that
distribution licensees undertake DSM initiatives,
not only because DSM initiatives provides an
opportunity for conservation of power use but
also because these initiatives when integrated
with supply, provides a least cost solution for
distribution licensees to meet their power
demand
26Advantages of Demand Side Power Purchase
- Cost-effective resource
- Cheaper than a conventional power purchase
- For e.g. Rs 350 Cr Savings/year for a 500 MW
evening peak power purchase for the CFL example - Additional option to reduce power needs
- Large economic benefits of reducing load
shortages - Environmental benefits
- Reduced local pollution
- Reduced carbon emissions
- Reduced resource requirements land, water,
-
27Session III ARR and Tariff Impact of Demand Side
Power purchase
28ARR and Impact on Consumer
- One line summary
- If the demand side power purchase cheaper than
the supply side, impacts on the consumer are
going to be positive!
29Impact on ARR
- Goal meet 1000 MW of demand increase during the
four peak hours in the evening - Supply side power purchase
- Sign a bilateral contract of 1000 MW for evening
peak delivery (1460 GWh delivered during the
evening peak hours over the years) - Addition to the ARR 730 Cr
- Demand side option
- Facilitate the replacement of 1.7 Cr incandescent
by providing Rs 100/bulb rebate to the consumer - Addition to ARR 170 Cr
30Impact on Tariff Bills
- How is the increase in ARR typically is met
- Tariff increase
- Increase in government subsidy
- Improvement in operations
- Increase sales to high paying consumers
- If the increase in ARR is lower for demand side
power purchase - Tariff increase can be mitigated
- Need for government subsidy can be reduced
- If the Rs 730 Cr of power purchase cost on the
supply side is used for demand side power
purchase, more than three times the units can be
purchased and could potentially eliminate
shortages !
31IV Implementing Demand Side Power purchase
32Barriers to Reducing Electricity Consumption A
Customers Perspective
- Lack of information about electricity savings
opportunities - Lack of ability and/or technical assistance for
analyzing electricity consumption patterns - Lack of financial resources to invest in
electricity savings options (e.g. technology,
etc.) - Lack of appropriate technological options to
reduce electricity consumption
33What is a DSM Program?
- Mechanism to influence customers CAPABILITY and
WILLINGNESS to reduce electricity consumption
34How to Influence Customer CAPABILITY to Reduce
Electricity Consumption?
- Availability of tools to understand electricity
consumption patterns (e.g. plug-in power meters
to measure appliance-level electricity
consumption, software to analyze and identify
electricity savings opportunities, etc.) - Availability of technology to reduce electricity
consumption (e.g. high efficiency T-5 tube-light
to replace inefficient T-12) - RD for developing new technology
35How to Influence Customer WILLINGNESS to Reduce
Electricity Consumption?
- Awareness
- Marketing, promotion, education, etc.
- Technical assistance
- Audits, analysis, equipment installation,
facilitating financing of projects, etc. - Financial incentives
- Rebates, loans at low interest rates, shared
savings, electricity pricing schemes, etc.
36DSM Program Design - Principles
- Systematic road-map for overcoming barriers faced
by customers in their goal of reducing
electricity consumption (and bills) - BOTH in short-term and long-term
- Must be cost-effective i.e. program costs must
be lower than benefits from program - Ensure customer satisfaction
37Types of DSM Programs
- All three reduce energy consumption (kWh) and
peak demand (kW), however, emphasis differs - Energy Efficiency emphasis is on reducing
overall energy consumption and also peak demand
over several years - Peak Load Management emphasis is on reducing
peak demand consistently over a season - Demand Response emphasis is on reducing peak
demand for short periods of time for a few days
during the year
38Energy Efficiency
- Permanent energy (kWh) reduction
- Permanent peak demand (kW) reduction
- Size of impact is predictable
- No reduction or shift in customer value, comfort,
or output - Not dispatchable by distribution company
- Examples rebates on efficient appliances,
energy savings performance contracting, etc.
39Energy Efficiency ProgramsLevel of Involvement
of Distribution Company
40Peak Load Management
- Overall energy consumption likely to stay same
- Focus is on changing customer load profile
- Size of impact fixed
- Fixed duration (4 - 6 hours daily) demand (kW)
reduction - Change/transfer in customer value, comfort, or
output - Not dispatchable by distribution company
- Examples tariffs for agricultural pumps
41Demand Response
- Overall energy consumption may vary based on
customer load curtailment strategy - Focus is on changing customer load profile
- Size of impact may vary from event to event
- Small duration (15 min 6 hours) demand (kW)
reduction - May involve a reduction in customer value,
comfort, or output - Dispatchable by distribution company
- Examples cycling of air conditioners,
critical peak pricing tariffs s
42Characteristics of Successful DSM Initiatives
- Deeply committed senior management and program
staff at both State Electricity Regulatory
Commission and distribution company (or
implementing agency) - Clearly defined goals and objectives
- Data-driven, systematic, and comprehensive DSM
program planning processes - you cant manage what you dont measure
- Stable program funding sources and levels
43Best Practices Planning
- Solicit stakeholder input
- Formal interview process or a collaborative
planning process involving key stakeholders - Conduct market analyses around information gaps
and key issues in order to understand existing
conditions - Target resources toward the very largest markets,
and those that are least understood - Establish baseline for tracking program
expenditure and impact
44Best Practices Program Design
- Seek to include programs with related and
complementary goals, - for example, electricity conservation, water
conservation, and renewables (e.g. rooftop solar) - Simplify participation in multiple programs
- Offer one bundle that may consist of energy
efficiency, measures from several different
organizations but is seamless to the customer
45Best Practices Program Design (cont.)
- Efficiently deliver integrated programs to all
end-users regardless of their size - Upstream Vs downstream incentives
- Larger customers, should be assigned a single
point of contact that represents all related
programs - Smaller customers should be offered a whole
building strategy that incorporate measures from
multiple programs.
46Best Practices Adapting to Changes
- Keep abreast of new developments in energy
efficiency technology - Coordinate with BEE and FOR
- Network with peers stay connected to
developments in this field - E.g. FOR/FOIR meetings, interactions with
international experts - Foster close relationships with market actors
rely on them for market intelligence - E.g. attending conferences to exchange ideas
47Best Practices - Staffing
- Clearly define responsibilities and clarify roles
to minimize confusion - Streamlining/facilitating stakeholder interaction
- Reward high performing staff and contractors
- DSM is a new activity and in the initial phases
staff will strong motivation to explore this
field - Encourage and facilitate development of energy
efficiency expertise of staff - DSM training workshop at NPTI June 15-18, 2009
48What can be learned from the US experience?
- Useful
- Identification of the DSM value proposition and
the understanding that saved energy was cheaper
and cleaner than energy consumed - Evolving understanding that customer engagement
and behavior are key drivers in achieving and
sustaining cost-effective energy efficiency - Broad experience (successes and failures) related
to delivering, measuring and valuing energy
efficiency
49What can be learned from the US experience? Cont.
- Not so useful
- Pattern of utility by utility DSM implementation
an accident of institutional history and politics - 30 year focus on technology as the sole DSM
driver - the no-behavior change strategy
- Corollary to above
- 30 year refusal to engage with customers
- revenue enhancement units
50Tales from the frontThe Illinois experience
with DSM
- For nearly 30 years, Illinois regulators and
policymakers refused to implement DSM - Swimming in electricity
- Reserve margins as high as 40
- Concern about raising rates
- Utilities uninterested
- Customers uninterested
51The Illinois experience, cont.
- By 2005
- Volatile energy prices
- Concern about emissions
- Shrinking reserve margins
- No State control over generation (restructured)
52Commission concerns
- Concern of raising rates to pay for DSM
- Concern of political backlash
- Concerns about lack of capacity to manage DSM
initiatives
53Relearning
- Its not as if we are not going to spend the
money. The only question is - What are we going to spend the money on?
54Four issues
- DSM increases rates in the short term
- Energy efficiency was less expensive than
purchased energy - Public Education/key messages
- helping customers
- Commission staff and utility capacity
- Training and capacity building
- Cost recovery
55Need for Co-ordination
- Efficient tube light program is applicable in
almost every state - SERCs should explore coordinating programs
56Role of Regulators
- Establish clear goals for DSM power purchase
based on potential estimates - Allocate resources from ARR for DSM power
purchase - Provide guidance/regulation to facilitate
implementation of DSM power purchase - Tariff options for promoting demand side power
prucahse (can either viewed as pumped storage or
peak power purchase)
57Establish Clear Goals for Constructing Demand
Side Power purchase
- In the initial period, the goal should be to get
a few small demand side power purchase/programs
started to gain experience - In the long run, the achievable potential for
cost effective power purchase should determine
the goals set for utilities - California Loading Order Buy all cost effective
demand side power purchase before any supply side
options are considered - Load research and technology assessment is
critical for potential estimates and target
setting - What kind appliances consumers are using and
how, what is the demand side power purchase
potential and what is the cost
58Allocate Resources for Demand Side Power purchase
- Public benefits charge small surcharge on tariff
to create a fund for DSM Power purchase - Stable funding mechanisms - allows utilities and
ESCOs to expand in the area of DSM Power purchase
- 5 paise/kWh charge 75 Cr of DSM funds in Delhi
- Recovery through ARR/power procurement accounts
- Treat as a an expense (same as the cost of power
purcahse) - Amortize over the life the saving measure
59Next Steps For Regulators
- Allocate staff/consultants
- Dedicated one or two staff or consultants to
begin with at the SERC - Work with FOR to develop and issue a standard set
of guidelines on to facilitate demand side power
purchase - Allocate resources for demand side power purchase
- Firm approval of resources for utilities to
create a DSM cell, hire DSM consultants (if
needed), conduct load research, and prepare
programs - Conditional approval for funding for the first
year (final approval provided after programs are
submitted) - Develop a roadmap for demand side power purchase
via a stakeholder process - Conduct/facilitate a potential study
- Goals and strategy by sector
- Role played various stakeholders
- Co-ordination with other programs
60Questions for Discussion
61Please check this website for LBNL India and
related publications http//ies.lbl.gov Thank
youJayant Sathaye
62Other Slides
63Efficiency Programs
- Two types of efficiency programs
- Standards and labels
- Bureau of Energy Efficiency
- DSM through financial and other incentives --
- Regulatory and utility incentives
- MERC, DERC and FOR
64Comparative Growth in the Power Sector
65Construction Cost Estimates
Plant Type Planned Capacity Addition (11th Plan) Cost Estimates
MW Rs crore/MW
Coal and natural gas 58644 4.51
Large hydro 16553 4.86
Small hydro 1400 5.50
Wind power 12600 4.50
Nuclear power 3380 6.58
Overall 92577 4.66
66Energy Supply with Deficit Reference Scenario --
Annual Capacity and Deficit
Year Actual and Projected Capacity (MW) 10th Plan Actual Capacity Additions (MW) 11th Plan Actual and Estimated Capacity Additions (MW) Actual and Projected Capacity Deficit () Actual and Projected Capacity Deficit (MW) Investment for Projected Capacity _at_ 992 / kW (Million US )
(Col. 1) (Col. 2) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7)
2002 105,046 2,831 12.2 12,816
2003 107,877 4,807 11.2 12,082
2004 112,684 5,742 11.7 13,184
2005 118,426 5,861 12.3 14,566
2006 124,287 8,042 13.8 17,152
2007 132,329 10,732 16.6 21,967 10,648
2008 143,061 5,204 11.9 17,024 5,163
2009 148,265 12,506 10 14,827 12,408
2010 160,771 12,506 10 16,077 12,408
2011 173,276 12,506 10 17,328 12,408
2012 185,782 10 18,578
Total 27,283 53,453 53,036
Planned Additional Capacity 44,185 92,577
67Supply with Efficiency Scenario - 2
Characteristics of Efficiency measures, and
Efficiency Savings and Supply Capacity
Energy Efficiency Measure Investment (Rs./kW) Daily Use (Hours/day) Peak Demand Savings (MW) 2008 Annual Electricity Savings (TWh) 2008
Variable speed drives in industry 4,700 11 948 3.8
Ag. Pump Rectification 9,400 8 655 1.9
Motor rewinding and downsizing 10,810 10 914 3.3
High efficiency agricultural pump sets 8,460 8 715 2.1
Improved high efficiency refrigerators 14,100 12 320 1.4
CFL and Electronic Ballasts 9,400 4 821 1.2
Total Energy Efficiency Savings (MW) 4,372 13.7
Supply Capacity Additions (MW) 9,772
68India Multipliers and Direct Coefficients
69(No Transcript)
70(No Transcript)