Title: Bulk Power Transmission in India
1Welcome
POWERGRID
Bulk Power Transmission in India Issues,
Challenges and Technology Options
Theme Paper
VK Prasher Executive Director Power Grid
Corporation of India Ltd vkprasher_at_powergridindia.
com vkprasher_at_yahoo.com
2Topics
- Evolution of Indian Power System
- Indian Power Scenario
- National Grid
- Transmission System Requirements
- Issues and Approach
- Technology Options
3Evolution of Indian Power Grid
- Phenomenal expansion since independence
- Generation 1349 MW 1,11,500 MW
- (in 1947) (in 2003)
- Grid
- Local grid at the time of independence.
- State Grids emerged in 1960s.
- Regional Grids in 1970s.
- Five Regional Grids Northern, Western,
Southern, Eastern North-eastern - National Grid under progress.
4POWERGRID
Thank You
5Present Power Supply Scenario
- Installed capacity - 104,500 MW
- Coal 71
- Hydro 25
- Nuclear others 4
- Peak demand
- Peak power - 81,555 MW
- Energy (average) - 1430 MU/day
- Availability
- Peak power - 71,260 MW
- Energy (average) - 1325 MU/day
- Shortage
- Peak power - 10,300 MW (12.6)
- Energy - 107 MU/day (7.5)
6Power Sector demarcated in five regions
7Existing Transmission System
- Figs. are in ckt. km
- State Central Total
(POWERGRID) - HVDC 1,504 3,532 4,836
- 800 KV 400
550 950 - 400 kV 13,000
32,500 45,500 - 220/132 kV 2,06,000
9000 2,15,000 - Application of State-of-the-art technologies -
HVDC bipole, - HVDC back-to-back, SVC, Series Compensation,
FACTS etc. - Application of improved OM technologies
Hotline maintenance, Emergency Restoration
System, Thermovision scanning etc.
8Recently Commissioned Major Links
- Talcher Kolar HVDC bipole line
- Capacity 2000 MW , Distance 1400 kms one of
the longest line - Inter-connecting Eastern to
Southern region - Commissioned 9 months ahead of
schedule - ER-WR Synchronous Inter Connection (Through
Raipur Rourkela 400 kV D/c line) - First major synchronous line inter-connecting two
big regions WR 30,000 MW and ER 15,000 MW - With this link power system of 48,000 MW is
running in synchronous mode.
9Talcher-Kolar and Raipur-Rourkela
10Capacity Addition Programme
- Goal Power on Demand by 2012
- Capacity Addition 100,000 MW in next 10 years
- 2006-07 - 45,000 MW
- 2011-012 - 55,000 MW
- Future Power Supply Scenario
Peak Demand (MW) Installed Capacity (MW)
Present 81,555 104,500
2006-07 115,000 149,500
2011-12 157,000 204,500
11(No Transcript)
12(No Transcript)
13Growth of Cumulative capacity of Inter-regional
links
14Plan for National Grid
- Phase 1 Already completed
- Interconnection of Regional Grids through HVDC
Back-to-Back links having cumulative capacity of
5000 MW Already Completed - Phase 2 Partly completed
- Hybrid system comprising of high capacity HVDC
and HVAC lines (both 765 kV and 400 kV) - Most of transmission lines would be part of
associated transmission system of large sized
generation project. - Cumulative inter-regional capacity would be
23,000 MW - Phase 3 to be completed by 2012
- Ring of 765 kV transmission lines
inter-connecting ER, WR and NR - Cumulative caapcity would be 30,000 MW
15HVDC and FACTS (After 2002)
- HVDC Schemes
- 2000 MW HVDC Bipole between Talcher in Eastern
Region and Kolar in Southern Region Already
commissioned in 2002 - 2nd 500 MW HVDC back-to-back at Gazuwaka
interconnecting Eastern Region and Southern
Region Scheduled by March, 2005 - 2500 MW HVDC Bipole between Balia and Bhiwadi in
Northern Region Scheduled in 2009-10 - FACTS Scheme
- TCSC (40 fixed plus 5-15 variable) on existing
Rourkela Raipur 400 kV D/c line Completed,
testing under progress - TCSC (40 fixed plus 5-15 variable) on
Purnea-Muzaffarpur and Muzaffarpur-Gorakhpur 400
kV D/c line Scheduled for commissioning by
June, 2006
16Transmission System Requirements
- Low cost to consumer
- The transmission system should be suitable for an
evolving system and allow implementation in
stages - It should meet system requirements regarding
active and reactive power in the face of
variation in load demand and following
contingencies.
17Transmission System Requirements
- The evolved system should have long term
suitability and should not be too expensive
initially or become redundant in future. - It should meet Availability / Reliability
requirements even when other elements in the
system are out within limits.
18Issues and Effects
ROW Constraint
Uncertainty in addition of generation
Bulk Power Long Distance Lines
Staging New Technologies
Reactive Power Planning
Stability
19Issues and Approach
- Utilization of existing resources to the maximum
extent - upgradation of voltages
- replacement with high capacity / HVDC lines
- Operation at high temperature
20Issues and Approach
- Transmission of bulk power over long distances
over time - Long bulk power transmission lines 400 kV, 800
kV ac, HVDC etc. - staging - Use of modular / multi-terminal HVDC
systems - reactive power control
21Issues and Approach
- Severe Right of Way constraints
- Use of compact lines
- Upgradation of voltage rating of existing lines
- Re-conductoring
- Multicircuit lines
- Use of high voltage / HVDC lines
- Dynamic Thermal Circuit Rating
22Issues and Approach
- Uncertainty in generation, Open market
- Matching Transmission Lines
- Greater change of flow reactive power support
- Staging may be essential
- Modular constructions
23Issues and Approach
- Inter area oscillations, Stability
- Unified Load Dispatch Systems
- Controlled exchange of power
- Steady state and dynamic reactive power support
- Free governor, PSS tuning
24Technology Options
- FACTS
- TCSC
- SVC
- STATCOM
- UPFC
25Technology Options
- HVDC systems
- Long distance bulk power systems
- Back-to-Back systems
- Multi-terminal schemes
- Voltage Source Converters
- Unit schemes, transformer less schemes etc.
- Tapping of power
26Technology Options
- 800, 1100 kV ac lines
- High temperature conductors
- Dynamic shunt reactors
- Dynamic Thermal Circuit Rating
27Thank you