EU procurement of ITER RH packages - PowerPoint PPT Presentation

About This Presentation
Title:

EU procurement of ITER RH packages

Description:

... ITER Procurement RH Procurement Packages 23P1 Blanket remote handling equipment 23P2 In-vessel divertor maintenance equipment(2) 23P3 Transfer cask system(3) ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 18
Provided by: CarloD4
Category:

less

Transcript and Presenter's Notes

Title: EU procurement of ITER RH packages


1
EU procurement of ITER RH packages
  • Carlo Damiani on behalf of the RH GroupF4E
    Barcelona Machine System Division

2
Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
3
Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
4
Introduction 1 - ITER Procurement
5
Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
6
PP overview23P2 - In-vessel divertor RH
equipment
Present scope (details to be confirmed) - 1
Cassette Multi-functional Mover (CMM, consisting
of CMM tractor, end effectors and umbilical) 1
spare - 1 right-hand-side cassette toroidal
mover (CTM) and umbilical 1 spare - 1
left-hand-side cassette toroidal movers (CTM) and
umbilical 1 spare - 1 set of tools for cassette
cooling pipes 1 spare - 1 set of tools for
cassette locking system 1 spare - 2
Manipulator arms (MAM) 1 spare - other tooling,
dust cleaner, rescue devices?
  • Status
  • - Design of DIV-RH and interfaces (e.g. CTM MAM
    and umbilical) on going
  • CMM prototype for tests in Divertor Test
    Platform 2 recently installed in DTP2

Next steps (see also planning section later) -
design, interface finalisation and pre-series
prototyping and testing - production
preparation - production and delivery to site
7
PP Overview23P3 Transfer Cask System (50 EU)
  • Present scope (under revision right now by IO in
    liaison with the DAs, EU-CN sharing to be
    finalised)
  • 21 cask units (including rescue units) each
    composed of cask and in-cask equipment, pallet
    and Air Transfer System
  • Spares (30 of supply spare parts)

Divertor cask
  • Status
  • - Design of ATS, casks and interfaces on going,
    preparation of prototyping and testing
  • PP scope and sharing being reviewed
  • Rescue devices investigated
  • Next steps (see also planning section later)
  • finalise review, discussion and agreement on
    scope/sharing
  • design, interface finalisation and pre-series
    prototyping and testing
  • production and delivery to site

Upper plug cask
8
PP Overview23P3 Transfer Cask System - more
  • Transfer cask studies have focused on
    trajectories studies and control system
    requirements recently rescue studies on a failed
    cask have been completed

From the picture below it can be seen that the
DIV RH and TCS have to work in a coordinated way,
by means of the two controllers and their
supervisor
9
PP Overview23P4 In vessel viewing system
  • Present scope (to be confirmed)
  • 6 IVVS systems() each consisting of probe,
    deployer and housing (shared with Glow Discharge
    Cleaning System)
  • Spares TBD (spare parts and/or 1 spare system)
  • () only 3 were foreseen in the ITER Project
    Integration Document at start of operation
  • Status
  • Lab tests on proof-of-principle probe mock-up
  • Requirements, interfaces (in particular space
    sharing with GDC) and PP content/sharing being
    reviewed

In-vessel viewing probe mock-up
  • Next steps (see also planning section later)
  • agreement on scope and requirements design,
    interface finalisation and pre-production
    prototyping and testing
  • production preparation
  • production and delivery to site

IVVS plan view (above) and section view (on the
right)
10
PP Overview23P5 NBI Remote Handling
  • Present scope (to be finalised)
  • monorail crane serving the NB cell, equipped
    with specific lifting interfaces with the NB
    components (and compatible with DIA plugs)
  • source/accelerator transport cradle
  • MAM and tooling (including pipe tooling)
  • ground-based vehicle?
  • rescue devices?
  • TBD spares

NB cell with monorail crane
  • Status
  • Conceptual design done
  • Work on interfaces and integration to be
    continued
  • PP being reviewed

? Crane and neutraliser
  • Next steps (see also planning section later)
  • scope finalisation design, interface
    finalisation (limited pre-production prototyping
    and testing TBD)
  • production preparation
  • production and delivery to site

NB rear maintenance
11
PP Overview - General
  • Each RH system (EU is in charge of 3 and ½ of
    them) is a different combination of various
    devices (moving machinery, crane, manipulator
    arms, tooling, umbilical, control system) that
    have to work in a coordinated way by means of its
    own control system
  • To control each of these RH systems, in the RH
    control room the HMI (the work-cell) will be
    typically a combination of master arms, GUI with
    monitors showing the status of the devices
    (status, speed, position, pressure, safety
    margins, interlocks, etc.), the visual
    information (from on-board or fixed cameras) and
    from Virtual Reality (probably 3-D), and the
    operational instructions (sequence of elementary
    tasks to be performed for a given RH mission)
  • We (F4E) have to understand/agree the way the
    overall RH control system is linked with the rest
    of CODAC (e.g. lift, ports, corridors, etc.)

12
Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
13
CODAC related aspects and issues - 1
  • For the RH PP, IO will only issue FS (plus
    partial reference designs), supported by RD
    where needed (see footnote, taken from former
    ITER Project Integration Document PID)
  • These FS must be complemented by the definition
    of a set of interface requirements the
    geometrical interfaces of the components to be
    handled, VV ports and ducts, hot cell, building,
    the interfaces with the ITER CODAC, etc. (the
    interface takes the level of to-be-handled
    component, e.g. DD for the divertor)
  • The level of integration and consistency of the
    current ITER design is not yet at a stage that
    would allow proceeding with in-kind supplies of
    the EU RH PP (through the Procurement
    Arrangements)
  • Because of this, a significant effort in terms
    of design, finalisation of the interfaces,
    prototyping and testing is still required

- All RH equipment for Class 1 and 2 operations
must be designed in detail prior to ITER
construction. - The feasibility of Class 1 tasks
shall be verified prior to ITER construction and
may involve the use of mock-ups. - The
feasibility of Class 2 tasks shall be verified
prior to ITER construction where deemed practical
and necessary and may involve the use of
mock-ups. - The procedure of maintenance of
Class 3 components shall be defined prior to ITER
construction.
14
CODAC related aspects and issues - 2
  • therefore our approach is to move to the final
    production of the PP after prototypes are
    designed, built and tested, in order to identify,
    finalise and experimentally verify both the RH
    strategy and those critical interfaces which
    represent the essential features of the design
    and of components maintainability
  • another important ingredient of our RH strategy
    is the review and agreement with IO of the PP
    scope and responsibilities, because the content
    of the 2001 PP must be updated and completed,
    including CODAC interfaces
  • the EU RH PP consists of a variety of movers,
    transport casks, crane, manipulator arms,
    tooling, covering several functions therefore we
    should move towards standardization of the design
    of RH devices from different PP but with similar
    functions this should be driven by IO and should
    include the control systems
  • (most of) the RH PP will be used for components
    first installation
  • a new (proposed ) element of the strategy is the
    use of RH facilities for IO team training
  • a key issue is the radiation resistance of the
    RH components (but with dose rates spanning over
    four orders of magnitude!) this requires a
    systematic approach and a specific strategy to be
    elaborated

15
An example of RH test facilitythe Divertor Test
Platform 2 (DTP2)
May 2008
January 2008
May 2008
16
CODAC related aspects and issues - 3
  • The RH procurement packages are not huge in
    financial terms (e.g. compared with items like
    the magnets) but require a lot of design and
    technical integration (with RAMI!), therefore we
    will probably have to charge the industrial
    suppliers with a role of architect
  • Prototyping and testing of the various RH PP in
    specific facilities are essential in order to (1)
    validate the maintenance scheme and the
    interfaces, (2) develop the procedures to be used
    straight out during 1st assembly, (3) possibly
    train IO team for 1st assembly
  • Technological items like force feedback
    manipulators, but not only, require a HMI already
    well developed since the beginning
  • There are time constraints for the development
    of the RH control system work-cells in the RH
    control room
  • Based on the points before, it is unlikely that
    the various RH systems will be procured naked,
    i.e. with very limited supervisory system
    capabilities (e.g. only control cubicle and touch
    screen and/or hand-held panels)
  • We could end up instead in having each PP
    delivered with its own work-cell implemented by
    the industrial supplier/integrator. This is
    exactly what is being discussed with IO RH team
    at the moment
  • This proposed approach puts issues in front of
    us in particular related to CODAC are
  • - limit of the supply, standardisation, FAT/SAT
  • - integration of the RH systems in the overall
    RH control system and in in CODAC
  • - new developments, improvements, change of
    obsolete components

17
  • A complicated path in front of us
Write a Comment
User Comments (0)
About PowerShow.com