Title: EU procurement of ITER RH packages
1EU procurement of ITER RH packages
- Carlo Damiani on behalf of the RH GroupF4E
Barcelona Machine System Division
2Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
3Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
4Introduction 1 - ITER Procurement
5Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
6PP overview23P2 - In-vessel divertor RH
equipment
Present scope (details to be confirmed) - 1
Cassette Multi-functional Mover (CMM, consisting
of CMM tractor, end effectors and umbilical) 1
spare - 1 right-hand-side cassette toroidal
mover (CTM) and umbilical 1 spare - 1
left-hand-side cassette toroidal movers (CTM) and
umbilical 1 spare - 1 set of tools for cassette
cooling pipes 1 spare - 1 set of tools for
cassette locking system 1 spare - 2
Manipulator arms (MAM) 1 spare - other tooling,
dust cleaner, rescue devices?
- Status
- - Design of DIV-RH and interfaces (e.g. CTM MAM
and umbilical) on going - CMM prototype for tests in Divertor Test
Platform 2 recently installed in DTP2
Next steps (see also planning section later) -
design, interface finalisation and pre-series
prototyping and testing - production
preparation - production and delivery to site
7PP Overview23P3 Transfer Cask System (50 EU)
- Present scope (under revision right now by IO in
liaison with the DAs, EU-CN sharing to be
finalised) - 21 cask units (including rescue units) each
composed of cask and in-cask equipment, pallet
and Air Transfer System - Spares (30 of supply spare parts)
Divertor cask
- Status
- - Design of ATS, casks and interfaces on going,
preparation of prototyping and testing - PP scope and sharing being reviewed
- Rescue devices investigated
- Next steps (see also planning section later)
- finalise review, discussion and agreement on
scope/sharing - design, interface finalisation and pre-series
prototyping and testing - production and delivery to site
Upper plug cask
8PP Overview23P3 Transfer Cask System - more
- Transfer cask studies have focused on
trajectories studies and control system
requirements recently rescue studies on a failed
cask have been completed
From the picture below it can be seen that the
DIV RH and TCS have to work in a coordinated way,
by means of the two controllers and their
supervisor
9PP Overview23P4 In vessel viewing system
- Present scope (to be confirmed)
- 6 IVVS systems() each consisting of probe,
deployer and housing (shared with Glow Discharge
Cleaning System) - Spares TBD (spare parts and/or 1 spare system)
- () only 3 were foreseen in the ITER Project
Integration Document at start of operation
- Status
- Lab tests on proof-of-principle probe mock-up
- Requirements, interfaces (in particular space
sharing with GDC) and PP content/sharing being
reviewed
In-vessel viewing probe mock-up
- Next steps (see also planning section later)
- agreement on scope and requirements design,
interface finalisation and pre-production
prototyping and testing - production preparation
- production and delivery to site
IVVS plan view (above) and section view (on the
right)
10PP Overview23P5 NBI Remote Handling
- Present scope (to be finalised)
- monorail crane serving the NB cell, equipped
with specific lifting interfaces with the NB
components (and compatible with DIA plugs) - source/accelerator transport cradle
- MAM and tooling (including pipe tooling)
- ground-based vehicle?
- rescue devices?
- TBD spares
NB cell with monorail crane
- Status
- Conceptual design done
- Work on interfaces and integration to be
continued - PP being reviewed
? Crane and neutraliser
- Next steps (see also planning section later)
- scope finalisation design, interface
finalisation (limited pre-production prototyping
and testing TBD) - production preparation
- production and delivery to site
NB rear maintenance
11PP Overview - General
- Each RH system (EU is in charge of 3 and ½ of
them) is a different combination of various
devices (moving machinery, crane, manipulator
arms, tooling, umbilical, control system) that
have to work in a coordinated way by means of its
own control system - To control each of these RH systems, in the RH
control room the HMI (the work-cell) will be
typically a combination of master arms, GUI with
monitors showing the status of the devices
(status, speed, position, pressure, safety
margins, interlocks, etc.), the visual
information (from on-board or fixed cameras) and
from Virtual Reality (probably 3-D), and the
operational instructions (sequence of elementary
tasks to be performed for a given RH mission) - We (F4E) have to understand/agree the way the
overall RH control system is linked with the rest
of CODAC (e.g. lift, ports, corridors, etc.)
12Outline- Remote Handling Procurement Packages
(PP)- Overview of the various PP- CODAC
related aspects and issues
13CODAC related aspects and issues - 1
- For the RH PP, IO will only issue FS (plus
partial reference designs), supported by RD
where needed (see footnote, taken from former
ITER Project Integration Document PID) - These FS must be complemented by the definition
of a set of interface requirements the
geometrical interfaces of the components to be
handled, VV ports and ducts, hot cell, building,
the interfaces with the ITER CODAC, etc. (the
interface takes the level of to-be-handled
component, e.g. DD for the divertor) - The level of integration and consistency of the
current ITER design is not yet at a stage that
would allow proceeding with in-kind supplies of
the EU RH PP (through the Procurement
Arrangements) - Because of this, a significant effort in terms
of design, finalisation of the interfaces,
prototyping and testing is still required
- All RH equipment for Class 1 and 2 operations
must be designed in detail prior to ITER
construction. - The feasibility of Class 1 tasks
shall be verified prior to ITER construction and
may involve the use of mock-ups. - The
feasibility of Class 2 tasks shall be verified
prior to ITER construction where deemed practical
and necessary and may involve the use of
mock-ups. - The procedure of maintenance of
Class 3 components shall be defined prior to ITER
construction.
14CODAC related aspects and issues - 2
- therefore our approach is to move to the final
production of the PP after prototypes are
designed, built and tested, in order to identify,
finalise and experimentally verify both the RH
strategy and those critical interfaces which
represent the essential features of the design
and of components maintainability - another important ingredient of our RH strategy
is the review and agreement with IO of the PP
scope and responsibilities, because the content
of the 2001 PP must be updated and completed,
including CODAC interfaces - the EU RH PP consists of a variety of movers,
transport casks, crane, manipulator arms,
tooling, covering several functions therefore we
should move towards standardization of the design
of RH devices from different PP but with similar
functions this should be driven by IO and should
include the control systems - (most of) the RH PP will be used for components
first installation - a new (proposed ) element of the strategy is the
use of RH facilities for IO team training - a key issue is the radiation resistance of the
RH components (but with dose rates spanning over
four orders of magnitude!) this requires a
systematic approach and a specific strategy to be
elaborated
15An example of RH test facilitythe Divertor Test
Platform 2 (DTP2)
May 2008
January 2008
May 2008
16CODAC related aspects and issues - 3
- The RH procurement packages are not huge in
financial terms (e.g. compared with items like
the magnets) but require a lot of design and
technical integration (with RAMI!), therefore we
will probably have to charge the industrial
suppliers with a role of architect - Prototyping and testing of the various RH PP in
specific facilities are essential in order to (1)
validate the maintenance scheme and the
interfaces, (2) develop the procedures to be used
straight out during 1st assembly, (3) possibly
train IO team for 1st assembly - Technological items like force feedback
manipulators, but not only, require a HMI already
well developed since the beginning - There are time constraints for the development
of the RH control system work-cells in the RH
control room - Based on the points before, it is unlikely that
the various RH systems will be procured naked,
i.e. with very limited supervisory system
capabilities (e.g. only control cubicle and touch
screen and/or hand-held panels) - We could end up instead in having each PP
delivered with its own work-cell implemented by
the industrial supplier/integrator. This is
exactly what is being discussed with IO RH team
at the moment - This proposed approach puts issues in front of
us in particular related to CODAC are - - limit of the supply, standardisation, FAT/SAT
- - integration of the RH systems in the overall
RH control system and in in CODAC - - new developments, improvements, change of
obsolete components
17- A complicated path in front of us